Introducing AME
Solar PV Wind Gas and LNG e-nnovation
AME is an infrastructure developer with a strong track record. Focus on Gas and LNG infrastructure, combined cycle power plants, solar PV and CSP and wind generation technologies, and other innovative technologies in the energy infrastructure space including public transport mobility and energy services Co-owner with EDF of the 5th largest generator in
- Chile. 1,200 MW in CCGTS and solar PV currently
- perating in Chile and Peru, together with a
significant development pipeline
- f
projects including CCGT and renewable technologies AME plans to balance its portfolio with 600 MW
- f additional renewable capacity by 2023
AME
Santiago Solar: Case Study of a Metropolitan Solar Plant
4 Confidential AME
Santiago de Chile Population 6 million Energy consumption 20,000 GWh/y
5 Confidential AME
Trade off – radiation vs transmission cost / risk
Santiago has extremely high radiation by world standards, even if it is 20% lower than northern Chile
6 Confidential
20 40 60 80 100 120 1,00 2,00 3,00 4,00 5,00 6,00 7,00 8,00 9,00 10,00 11,00 12,00 1,00 2,00 3,00 4,00 5,00 6,00 7,00 8,00 9,00 10,00 11,00 12,00 1,00 2,00 3,00 4,00 5,00 6,00 7,00 8,00 2.017 2.018 2.019
CMg [USD/MWh] AÑO - MES
CMG por Bloque (Solo Solar)
Crucero - Solar Diego de Almagro - Solar Quillota - Solar
Trade off – radiation vs transmission cost / risk
Day time prices by injection node
7 Confidential
Santiago Solar: A metropolitan solar project
45 km (27 miles) north of Santiago
8 Confidential AME
Timeline
9 Confidential AME
Santiago Solar site (pre-build)
10 Confidential AME
Timeline
11 Confidential AME
Til- til is an area of Santiago which has experienced significant levels of conflict between citizens and businesses in recent years
12 Confidential
Meaningful and genuine dialogue with the community
- Respectful and genuine
consultation
- Real changes made to
project design to adjust to community concerns
- Contributions designed
to be relevant to the project and address real needs
13 Confidential AME
Timeline
14 Confidential AME
In the 2014 tender process, Santiago Solar presented the lowest adjudicated offer, winning with a price of US$79.88/ MWh.
15 Confidential AME
Timeline
16 Confidential AME
Santiago Solar site (pre-build)
17 Confidential AME
Santiago Solar site (pre-build)
18 Confidential AME
Santiago Solar site (pre-build)
19 Confidential AME
125 ha
agricultural land improved
145 ha
reforested with native species
(360 acres) (310 acres)
20 Confidential AME
Timeline
21 Confidential AME 0,0% 20,0% 40,0% 60,0% 80,0% 100,0% 120,0% 140,0% 160,0% 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 WITHDRAWAL % Real/Projected Withdrawal Objective Withdrawal Rate
Regulated client withdrawals real / projected 2010 - 2025
22 Confidential AME
- 50,0
100,0 150,0 200,0 250,0 300,0 ene-10 abr-10 jul-10
- ct-10
ene-11 abr-11 jul-11
- ct-11
ene-12 abr-12 jul-12
- ct-12
ene-13 abr-13 jul-13
- ct-13
ene-14 abr-14 jul-14
- ct-14
ene-15 abr-15 jul-15
- ct-15
ene-16 abr-16 jul-16
- ct-16
ene-17 abr-17 jul-17
- ct-17
ene-18 abr-18 jul-18
- ct-18
ene-19 abr-19 jul-19 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 CMg Quillota 220 CMg Crucero CMg Diego de Almagro
Marginal Prices in the SIC / SEN 2010 – 2019
23 Confidential AME
- 50,0
100,0 150,0 200,0 250,0 300,0 ene-10 abr-10 jul-10
- ct-10
ene-11 abr-11 jul-11
- ct-11
ene-12 abr-12 jul-12
- ct-12
ene-13 abr-13 jul-13
- ct-13
ene-14 abr-14 jul-14
- ct-14
ene-15 abr-15 jul-15
- ct-15
ene-16 abr-16 jul-16
- ct-16
ene-17 abr-17 jul-17
- ct-17
ene-18 abr-18 jul-18
- ct-18
ene-19 abr-19 jul-19 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 CMg Quillota 220 CMg Crucero CMg Diego de Almagro
Marginal Prices in the SIC / SEN 2010 – 2019
24 Confidential AME
Timeline
25 Confidential AME
Timeline
26 Confidential AME
Timeline
27 Confidential AME
28 Confidential AME
*
100
* Based on average home consumption
- f 1.785 kWh /y
(Obrecht, 2016)
FACTS & FIGURES
29 Confidential
Award winning approach
Winner of the Association of Generators’ “Good Practices Contest for a more Sustainable Electric Future, 2018 Women of theYear Award, 2017, Ministry of Energy Outstanding results in the Project Acceptance Index for large scale renewable energy projects, Ministry of Energy and Gernman GIZ Winner of Latin American Green Awards 2019 “Oasification; Forest Solutions for Desertification”
30 Confidential
A few words about the greenhouse…
31 Confidential
Thank you