Colf Colfax ax BRT T T Task F ask For orce ce Me Meetin ing - - PowerPoint PPT Presentation

colf colfax ax brt t t task f ask for orce ce me meetin
SMART_READER_LITE
LIVE PREVIEW

Colf Colfax ax BRT T T Task F ask For orce ce Me Meetin ing - - PowerPoint PPT Presentation

Colf Colfax ax BRT T T Task F ask For orce ce Me Meetin ing December 12, 2019 Agenda 1) Colfax BRT Project Updates 2) Pedestrian Safety & Streetscaping 3) Funding Background 4) Design Updates 5) Project Development &


slide-1
SLIDE 1

Colf Colfax ax BRT T T Task F ask For

  • rce

ce Me Meetin ing

December 12, 2019

slide-2
SLIDE 2

2

Agenda

1) Colfax BRT Project Updates 2) Pedestrian Safety & Streetscaping 3) Funding Background 4) Design Updates 5) Project Development & Funding Methodology 6) Project Timelines 7) Near Term Projects 8) Vision Zero Updates 9) Recommended Next Step

slide-3
SLIDE 3

Colf Colfax ax BRT T Pr Proje

  • ject

ct U Upda pdate

slide-4
SLIDE 4

4

Colfax BRT Procurement Update

Colfax BRT NEPA & Preliminary Design Scope Procurement: Current Schedule

  • Issue RFP - 1st Quarter 2020
  • Issue NTP – 3rd Quarter 2020
  • NEPA/PE Duration – 18 to 24 months
slide-5
SLIDE 5

5

1

East Colfax Tentative Timeline

Pre-Design & Environmental (18 to 24 months)

− Determine different transit elements, BRT applications, and length − NEPA Work − Refine cost estimates and funding plans

2

Design Engineering (12 to 18 months)

3

Right of Way (18 to 24 months)

2020 2021 2022 2023 2024 2025 2026 2027 2028

4

Construction (18 to 24 months)

slide-6
SLIDE 6

6

Colfax BRT Project Scope

NEPA and Preliminary Design Scope Elements:

  • Environmental Assessment, NEPA (National Environmental Policy Act)
  • Preliminary Design (survey, ROW, roadway plans, BRT Stations, utilities, drainage, signals, phasing)
  • Travel Modal and Traffic Analysis
  • Public and stakeholder involvement and coordination
  • Cost Estimates
  • FTA CIG (Capital Investment Grant) Application
  • Financial and Funding Analysis
slide-7
SLIDE 7

7

NEPA Process

Scoping

  • Decision on Preferred Alternative

and disclosure of impacts Evaluation of alternatives Scoping

Determine the scale of the project Notify the public and stakeholders and ask for their future involvement Determine the NEPA class

  • f action:

Categorical Exclusion Environmental Assessment Environmental Impact Statement Purpose and Need Develop problem statement Identify the need for the project Perform operational analysis for existing conditions Develop goals and objectives for the project Evaluate Alternatives Develop a reasonable range of alternatives to solve the problems Determine meaningful criteria to evaluate the alternatives Operational criteria Environmental criteria Select a Preferred Alternative Document Environmental Impacts Describe alternatives being considered, including No Action alternative Disclose impacts to natural and human environmental resources Provide mitigation commitments to reduce the impacts where appropriate and reasonable Decision Document Lead Agency signs the NEPA decision document Public notice of decision

Public and Stakeholder Outreach at Milestones

slide-8
SLIDE 8

8

NEPA Preliminary Design Process

The NEPA preliminary design process will include incorporating aspects of streetscaping elements into design. This will include:

  • Safety improvements such as medians and bulb-
  • uts
  • Consideration of aesthetic features (i.e. pavers,

stamped concrete)

  • Opportunities for water quality features
  • Placement of pedestrian scale lighting
  • Placement of street furnishings

City will involve the BIDs in design process.

slide-9
SLIDE 9

Pede dest stria ian Saf Safety & ty & Stre Streets tscaping

Process and Schedule Update

slide-10
SLIDE 10

Funding B Bac ackgr grou

  • und
slide-11
SLIDE 11

11

Elevate Denver Funding

  • $20 million approved in Elevate Denver Bond for Pedestrian

Safety Improvements and Streetscaping within four Colfax BIDs

  • Early Assumptions
  • Funds would be used to make pedestrian safety improvements in

Bluebird and West Colfax BID areas, informed by design plans.

  • Funds would be used to make pedestrian safety and

streetscaping enhancements in Colfax and Mayfair BID areas, informed by respective streetscape master plans.

slide-12
SLIDE 12

12

BID Plans Informed the Amount

  • f the Bond Request
  • Funding amount based on cost

estimates of preliminary engineering designs (West Colfax/ Bluebird) or streetscape plans (Colfax/ Mayfair) from each BID.

  • BID cost estimates included

construction, design, and contingency

  • Cost estimates and designs were

based on side-running BRT at time.

slide-13
SLIDE 13

13

How was $20 million determined?

Based on cost estimates provided by Colfax BIDs:

  • Design and construction costs were pulled from each

plan and totaled.

  • A 20% contingency was added to design and 20%

contingency was added to construction.

  • 5% was added for Water Quality
  • 1% was added for Public Art

Total cost was estimated to be ~20 million

slide-14
SLIDE 14

Desi sign U Upda pdates

slide-15
SLIDE 15

15

Factors that have Changed Since Bond Process Began

East Colfax

  • Based on community input, a decision to move from side-running to center-running BRT was made after

Elevate Denver bond process was complete

  • The design change from side-running to center-running BRT greatly alters the envelope of the pedestrian

and streetscape improvements, meaning the cost estimates assumed for streetscaping work are no longer accurate

  • Additional funding opportunities may be available to strengthen project

West Colfax

  • The City has modified designs based on public input process and future need
  • Community desire for landscaping in medians wasn’t considered in bond cost estimates for West Colfax
slide-16
SLIDE 16

16

Incorporating Streetscaping + Pedestrian Safety with Center-Running BRT Design

Streetscaping Improvements (based on side-running BRT) Streetscaping Improvements (based on center-running BRT)

Pedestrian Lighting Furnishings Trash Receptacles Street Trees Pavers or Stamped Concrete Banners/ Wayfinding

slide-17
SLIDE 17

Project Development & Funding Methodology

slide-18
SLIDE 18

18

Goal is to leverage funding and strengthen project that results in the following outcomes:

  • Meet broader community vision & goals
  • Delivering a multi-modal corridor
  • Expanding tree canopy
  • Improving air & water quality
  • Supports local needs along the corridor
  • Highest quality project possible
  • Meet safety needs of entire corridor
slide-19
SLIDE 19

19

East & West Colfax Stakeholders

slide-20
SLIDE 20

20

East Colfax Project Development Process

Plan

  • Align plan for Colfax with city goals and values
  • Coordination between partners to define project

Design

  • Initiate preliminary (NEPA) design process
  • Produce cost estimates to understand need

Programmatic

  • Investigate additional funding opportunities to leverage
  • Coordination on design with partners to align values and

needs

slide-21
SLIDE 21

21

Plan

  • Align plan for Colfax with city goals and values
  • Coordination between partners to define project

Design

  • Initiate preliminary design process
  • Produce cost estimates to understand need

Programmatic

  • Investigate additional funding opportunities to leverage
  • Coordination on design with partners to align values and

needs

West Colfax Project Development Process

slide-22
SLIDE 22

22

  • Cost estimates will be developed for each design on East and West Colfax
  • Costs are likely to exceed funding so additional funding sources will be leveraged
  • Leveraging additional funding will allow the City to build a more complete project
  • Once the appropriate funding stacks are in place, funding from each source will be

allocated accordingly

Funding Summary

slide-23
SLIDE 23

Timelines

slide-24
SLIDE 24

24

Tentative Project Timelines

The improvements on West Colfax are on a different time-line than the improvements on East Colfax.

  • The design for East Colfax is being coordinated with

BRT

  • NEPA and Preliminary Design process will be initiated in

2020.

slide-25
SLIDE 25

25

West Colfax Tentative Timeline

2

Design Engineering (12 to 18 months)

3

Construction (24+ months)

2018 2019 2020 2021 2022

Planning (12 to 15 months)

− Public Outreach − Concept Development & Refinement

1

2023

slide-26
SLIDE 26

26

1

East Colfax Tentative Timeline

Pre-Design & Environmental (18 to 24 months)

− Determine different transit elements, BRT applications, and length − NEPA Work − Refine cost estimates and funding plans

2

Design Engineering (12 to 18 months)

3

Right of Way (18 to 24 months)

2020 2021 2022 2023 2024 2025 2026 2027 2028

4

Construction (18 to 24 months)

slide-27
SLIDE 27

Near Term Projects

slide-28
SLIDE 28

28

U

Near Term Streetscaping- East Colfax

“Soft” Streetscape Elements

Furnishings Trash Receptacles Bike Racks

Given the timeline of the BRT project, we will be moving forward with the soft streetscaping elements that were recommended from the BID plans.

  • Funding outside of Elevate Denver Bond will be used to move

forward with the soft elements ahead of the BRT project.

  • Soft elements are those that can be installed and then be

moved and reinstalled after BRT construction.

  • BIDs will be involved in picking the “pallet” of furnishings to

build off visions in streetscape master plans.

  • The soft furnishings will help reinforce the unique character

areas of Colfax that were established in the streetscape master plans.

slide-29
SLIDE 29

29

U

Near Term Streetscaping- East Colfax

Near-Term (Prior to BRT Construction) “Soft” Streetscape Elements

Furnishings Trash Receptacles Bike Racks

“Hard” Streetscape Elements Long-Term (During BRT Construction)

Pedestrian Lighting/ Banner Poles Street Trees Pavers or Stamped Concrete

slide-30
SLIDE 30

30

Colfax Wide Safety Priorities

It is critical to leverage funds to make safety improvements corridor wide. 35 priority intersections Criteria

  • Public Works Equity Index
  • Injury & Fatal Crashes
  • Crashes
  • Current & Future Land-use
  • Distance between signals

Colfax Safety Priority Intersections BID Area # West Colfax 9 Colfax 12 Bluebird 1 Mayfair 6 Other 7

slide-31
SLIDE 31

31

Vision Zero Safety Improvements

Near term Improvements at following intersections:

  • Grant
  • Logan
  • Pearl
  • Washington
  • Clarkson
  • Lafayette
  • High
  • Adams
  • Hudson
  • Krameria
  • Monaco
  • Unita
  • Valentia
  • Verbena
  • Wabash

Construction Spring 2020

Temporary Bulb-outs Restricted Right Turns Temporary Median

Example Vision Zero Improvements at Colfax & Adams

slide-32
SLIDE 32

32

Colfax & Fairfax

Public Works is evaluating the option for adding a signal at this location:

  • A review has been completed of pedestrian crossing

behavior

  • A HAWK signal may therefore be warranted but a formal

pedestrian crossing analysis is needed as well as approval from CDOT.

  • We will be ordering traffic volume counts to determine if

a full signal is warranted.

  • Removal of the eastbound left turn pocket to the alley

(with paint and bollards) is being considered to provide an informal pedestrian refuge space.

slide-33
SLIDE 33

33

Stormwater Improvement Project

  • Upsizing stormwater pipe under East Colfax

Avenue at Jackson Street

  • Providing more capacity to carry stormwater to

reduce recurrent flooding

  • Anticipated construction timeline: January – June

2020

  • Drivers will shift to south two vehicle lanes while

excavation occurs on north side.

  • Then, drivers will shift to north two vehicle lanes

while excavation occurs on south side.

slide-34
SLIDE 34

34

Next Steps

  • Strategy/Scoping Meeting w/BIDs to determine next steps for

near term improvement

  • Quarterly Task Force Meetings (On-going)
  • Internal Coordination (On-going)
  • CDOT & RTD Coordination (On-going)
  • West Colfax design process to kick off (Q2 2020)
  • NEPA Process to kick-off (Q3 2020)