Colf Colfax ax BRT T T Task F ask For
- rce
Colf Colfax ax BRT T T Task F ask For orce ce Me Meetin ing - - PowerPoint PPT Presentation
Colf Colfax ax BRT T T Task F ask For orce ce Me Meetin ing December 12, 2019 Agenda 1) Colfax BRT Project Updates 2) Pedestrian Safety & Streetscaping 3) Funding Background 4) Design Updates 5) Project Development &
1) Colfax BRT Project Updates 2) Pedestrian Safety & Streetscaping 3) Funding Background 4) Design Updates 5) Project Development & Funding Methodology 6) Project Timelines 7) Near Term Projects 8) Vision Zero Updates 9) Recommended Next Step
1
Pre-Design & Environmental (18 to 24 months)
− Determine different transit elements, BRT applications, and length − NEPA Work − Refine cost estimates and funding plans
2
Design Engineering (12 to 18 months)
3
Right of Way (18 to 24 months)
2020 2021 2022 2023 2024 2025 2026 2027 2028
4
Construction (18 to 24 months)
NEPA and Preliminary Design Scope Elements:
Scoping
and disclosure of impacts Evaluation of alternatives Scoping
Determine the scale of the project Notify the public and stakeholders and ask for their future involvement Determine the NEPA class
Categorical Exclusion Environmental Assessment Environmental Impact Statement Purpose and Need Develop problem statement Identify the need for the project Perform operational analysis for existing conditions Develop goals and objectives for the project Evaluate Alternatives Develop a reasonable range of alternatives to solve the problems Determine meaningful criteria to evaluate the alternatives Operational criteria Environmental criteria Select a Preferred Alternative Document Environmental Impacts Describe alternatives being considered, including No Action alternative Disclose impacts to natural and human environmental resources Provide mitigation commitments to reduce the impacts where appropriate and reasonable Decision Document Lead Agency signs the NEPA decision document Public notice of decision
The NEPA preliminary design process will include incorporating aspects of streetscaping elements into design. This will include:
stamped concrete)
City will involve the BIDs in design process.
Based on cost estimates provided by Colfax BIDs:
plan and totaled.
contingency was added to construction.
Total cost was estimated to be ~20 million
East Colfax
Elevate Denver bond process was complete
and streetscape improvements, meaning the cost estimates assumed for streetscaping work are no longer accurate
West Colfax
Streetscaping Improvements (based on side-running BRT) Streetscaping Improvements (based on center-running BRT)
Pedestrian Lighting Furnishings Trash Receptacles Street Trees Pavers or Stamped Concrete Banners/ Wayfinding
Plan
Design
Programmatic
needs
Plan
Design
Programmatic
needs
allocated accordingly
2
Design Engineering (12 to 18 months)
3
Construction (24+ months)
2018 2019 2020 2021 2022
Planning (12 to 15 months)
− Public Outreach − Concept Development & Refinement
1
2023
1
Pre-Design & Environmental (18 to 24 months)
− Determine different transit elements, BRT applications, and length − NEPA Work − Refine cost estimates and funding plans
2
Design Engineering (12 to 18 months)
3
Right of Way (18 to 24 months)
2020 2021 2022 2023 2024 2025 2026 2027 2028
4
Construction (18 to 24 months)
“Soft” Streetscape Elements
Furnishings Trash Receptacles Bike Racks
Given the timeline of the BRT project, we will be moving forward with the soft streetscaping elements that were recommended from the BID plans.
forward with the soft elements ahead of the BRT project.
moved and reinstalled after BRT construction.
build off visions in streetscape master plans.
areas of Colfax that were established in the streetscape master plans.
Near-Term (Prior to BRT Construction) “Soft” Streetscape Elements
Furnishings Trash Receptacles Bike Racks
“Hard” Streetscape Elements Long-Term (During BRT Construction)
Pedestrian Lighting/ Banner Poles Street Trees Pavers or Stamped Concrete
Colfax Safety Priority Intersections BID Area # West Colfax 9 Colfax 12 Bluebird 1 Mayfair 6 Other 7
Near term Improvements at following intersections:
Construction Spring 2020
Temporary Bulb-outs Restricted Right Turns Temporary Median
Example Vision Zero Improvements at Colfax & Adams
Public Works is evaluating the option for adding a signal at this location:
behavior
pedestrian crossing analysis is needed as well as approval from CDOT.
a full signal is warranted.
(with paint and bollards) is being considered to provide an informal pedestrian refuge space.
Avenue at Jackson Street
reduce recurrent flooding
2020
excavation occurs on north side.
while excavation occurs on south side.