Cle lean Coal Technology (C (CCT CT) Training Program FY2019 under CEA and JCOAL Cooperation
Annepu Suresh Director (Thermal Planning & Project Development) Central Electricity Authority Ministry of Power
Cle lean Coal Technology (C (CCT CT) Training Program FY2019 - - PowerPoint PPT Presentation
Cle lean Coal Technology (C (CCT CT) Training Program FY2019 under CEA and JCOAL Cooperation Annepu Suresh Director (Thermal Planning & Project Development) Central Electricity Authority Ministry of Power Outline Generation and
Annepu Suresh Director (Thermal Planning & Project Development) Central Electricity Authority Ministry of Power
All ll In India ia In Installe led Ca Capacity 2018 2018-19 19
Hydro, 45399, 12.75% Coal/Lignite, 200705, 56.36% Gas, 24937, 7.00% Diesel , 638, 0.18% Nuclear, 6780, 1.90% RES, 77642, 21.80%
3,56,100 MW
Gross
Electricity Gener eneration in in In India ia 2018 2018-19 19
Hydro 134894 GWh 9.83% Coal 1022265 GWh 74.52% Gas 49834 GWh 3.63% Diesel 212 GWh 0.02% Nuclear 37813 GWh 2.76% R.E.S. 126800 GWh 9.24%
13,71,817 GWh
*
12.2 11.2 11.7 12.3 13.8 16.6 11.9 12.7 9.8 10.6 9 4.5 4.7 3.2 1.6 2 0.8 0% 2% 4% 6% 8% 10% 12% 0% 2% 4% 6% 8% 10% 12% 14% 16% 18% PEAK DEFICIT / SURPLUS ENERGY DEFICIT/ SURPLUS
Peak met = 175,528 MW Energy availability =1,267,526 MU
52.40 53.20 56.50 55.00 56.50 53.90 55.30 57.10 61.00 60.00 63.00 64.40 64.70 64.60 67.30 69.00 69.90 72.20 72.70 74.80 74.30 76.80 78.60 77.20 77.68 74.97 73.47 70.13 65.56 64.25 62.24 59.88 60.72 10 20 30 40 50 60 70 80 90 1985-86 1986-87 1987-88 1988-89 1989-90 1990-91 1991-92 1992-93 1993-94 1994-95 1995-96 1996-97 1997-98 1998-99 1999-00 2000-01 2001-02 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17 2017-18 PLF (%) Years
Hydro 2,68,859 12% Coal+Lignite 12,38,906 56% Gas+Diesel 86,182 4% Nuclear 1,10,696 5% RES 5,18,000 23%
Hydro Coal+Lignite Gas+Diesel Nuclear RES
Hydro 1,55,742.0 9.16% Coal+Lignite 10,71,801.0 63.05% Gas+Diesel 82,626.0 4.86% Nuclear 62,643.0 3.69% RES 3,27,000.0 19.24%
Hydro Coal+Lignite Gas+Diesel Nuclear RES
Mar arch, , 2022 2022 IC= IC=4,79,419 MW MW Gen=16,99,812 GWh Gen=22,22,643 GWh Mar arch, , 2027 2027 IC=6 IC=6,19,066 MW
Supply ly sid ide
will constitute 37% and 44% of generation mix in 2022 and 2027, respectively.
De Demand sid ide
sources connected at distribution and sub-transmission voltage levels. These resources are largely ‘uncontrollable’ by system operators even at the state level.
uncertainty.
level.
based
Higher ramping rates during loading/unloading Faster Startup Lower stable minimum load Frequent & increased load cycling Fast load ramp up and ramp down Low load operation Two shift operation Frequent and increased number
shutdown cycles Reduced effect on life of Equipment Minimal impact on environment
Tokyo
Kitakyushu
Kumamoto
Reihoku: Entrance Reihoku: Turbine Floor
Reihoku: Coal yard Hibikinada: BTG
conveyor system, coal mill condition is excellent.