chislehurst road bridge reconstruction
play

Chislehurst Road Bridge Reconstruction Construction Overview and - PowerPoint PPT Presentation

Chislehurst Road Bridge Reconstruction Construction Overview and Phasing Jon Elliott Site Agent 1 Chislehurst Road Bridge Reconstruction Background Why we are building the new bridge? Safety inspections revealed severe structural


  1. Chislehurst Road Bridge Reconstruction Construction Overview and Phasing Jon Elliott – Site Agent 1

  2. Chislehurst Road Bridge Reconstruction Background Why we are building the new bridge? • Safety inspections revealed severe structural weaknesses • No longer capable of carrying the 44 ton weight load of a HGV • Engineering studies concluded no other alternative than to re-build • Risk of collapse over busy rail line 2

  3. Chislehurst Road Bridge Reconstruction Thinking Forward What are the benefits of a new bridge? • Once rebuilt buses and HGV’s will be able use bridge again Diversion route will no longer be needed • Relieves traffic pressure • The new bridge will be low maintenance • Will be a much more reliable structure • Life span of 120 years, far greater than the current Post Tensioned 1950s bridge design, found to be structurally very weak 3

  4. Chislehurst Road Bridge Reconstruction HOCHTIEF’s Key issues Our key issues are; • Safety of site staff and the public is paramount Working in a critical rail environment o Working in a compact site o Working close to the local community o • Local Community Engagement, ensuring regular and consistent information Keeping noise to a minimum o Sensible plant movement to avoid disturbance o 4

  5. Chislehurst Road Bridge Reconstruction The Reconstruction works Construction plan • Our method is based on a robust access/protection deck able to contain all the loads from demolition of the existing deck and construction of the new bridge • The footpath will remain open over the bridge for the full period of the site works other than for safety critical works associated with the crane lifts of the rail protection deck and new bridge beams • Each half of the bridge will be demolished and reconstructed sequentially allowing one side to remain open • Whilst the first half of the bridge is being demolished service and utility diversions can take place during the re-build of that side reducing the down time 5

  6. Chislehurst Road Bridge Reconstruction Construction Phasing - 1 • Existing Bridge from West 6

  7. Chislehurst Road Bridge Reconstruction Construction Phasing - 2 • Install Protection Screens under the bridge • Install Foundations,Trestles and Slide Tracks 7

  8. Chislehurst Road Bridge Reconstruction Construction Phasing - 3 • Installed rail protection deck under existing deck • Lifting in the beams in pairs at night Sliding the pairs of beams under the bridge • 8

  9. Chislehurst Road Bridge Reconstruction Construction Phasing - 4 • Remove the existing surface to reduce the weight • Saw Cutting Pre-Stress Tendons, (existing deck load taken on rail protection deck) • Pedestrians and Services remain on the unaffected East Footway • Saw Cutting in preparation for the lifting out of the existing beams 9

  10. Chislehurst Road Bridge Reconstruction Construction Phasing - 5 • Break out/lift out Beam Segments • Break up sections of beams off of bridge away from the railway Separate concrete from steel and remove from site • 10

  11. Chislehurst Road Bridge Reconstruction Construction Phasing - 6 • First phase demolition completed • Installing new steel girders 1 to 4 11

  12. Chislehurst Road Bridge Reconstruction Construction Phasing - 7 • First Phase steelwork complete • Divert remaining services to new side of the bridge 12

  13. Chislehurst Road Bridge Reconstruction Construction Phasing - 8 • Completed first phase of deck • Service diversions complete • Pedestrians diverted to new footway • Demolition of East deck completed 13

  14. Chislehurst Road Bridge Reconstruction Construction Phasing - 9 • Complete steelwork • Install GRP enclosure below beams 14

  15. Chislehurst Road Bridge Reconstruction Construction Phasing - 10 • Complete new deck • Remove rail protection deck • Complete enclosure • Reinstate working areas 15

  16. Chislehurst Road Bridge Reconstruction Construction Phasing - 11 • Complete – Chislehurst Road Bridge Reconstruction 16

  17. Chislehurst Road Bridge Reconstruction Construction Overview and Phasing Jon Elliott – Site Agent 17

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend