Chislehurst Road Bridge Reconstruction Construction Overview and - - PowerPoint PPT Presentation

chislehurst road bridge reconstruction
SMART_READER_LITE
LIVE PREVIEW

Chislehurst Road Bridge Reconstruction Construction Overview and - - PowerPoint PPT Presentation

Chislehurst Road Bridge Reconstruction Construction Overview and Phasing Jon Elliott Site Agent 1 Chislehurst Road Bridge Reconstruction Background Why we are building the new bridge? Safety inspections revealed severe structural


slide-1
SLIDE 1

1

Chislehurst Road Bridge Reconstruction

Construction Overview and Phasing

Jon Elliott – Site Agent

slide-2
SLIDE 2

2

Chislehurst Road Bridge Reconstruction

Background Why we are building the new bridge?

  • Safety inspections revealed severe structural weaknesses
  • No longer capable of carrying the 44 ton weight load of a HGV
  • Engineering studies concluded no other alternative than to re-build
  • Risk of collapse over busy rail line
slide-3
SLIDE 3

3

Chislehurst Road Bridge Reconstruction

Thinking Forward What are the benefits of a new bridge?

  • Once rebuilt buses and HGV’s will be able use bridge again

Diversion route will no longer be needed

  • Relieves traffic pressure
  • The new bridge will be low maintenance
  • Will be a much more reliable structure
  • Life span of 120 years, far greater than the current Post Tensioned

1950s bridge design, found to be structurally very weak

slide-4
SLIDE 4

4

Chislehurst Road Bridge Reconstruction

HOCHTIEF’s Key issues Our key issues are;

  • Safety of site staff and the public is paramount
  • Working in a critical rail environment
  • Working in a compact site
  • Working close to the local community
  • Local Community Engagement, ensuring regular and

consistent information

  • Keeping noise to a minimum
  • Sensible plant movement to avoid disturbance
slide-5
SLIDE 5

5

Chislehurst Road Bridge Reconstruction

The Reconstruction works Construction plan

  • Our method is based on a robust access/protection deck able

to contain all the loads from demolition of the existing deck and construction of the new bridge

  • The footpath will remain open over the bridge for the full

period of the site works other than for safety critical works associated with the crane lifts of the rail protection deck and new bridge beams

  • Each half of the bridge will be demolished and reconstructed

sequentially allowing one side to remain open

  • Whilst the first half of the bridge is being demolished service

and utility diversions can take place during the re-build of that side reducing the down time

slide-6
SLIDE 6

6

Chislehurst Road Bridge Reconstruction

  • Existing Bridge from West

Construction Phasing - 1

slide-7
SLIDE 7

7

Chislehurst Road Bridge Reconstruction

  • Install Protection Screens under the bridge
  • Install Foundations,Trestles and Slide Tracks

Construction Phasing - 2

slide-8
SLIDE 8

8

Chislehurst Road Bridge Reconstruction

  • Installed rail protection deck under existing deck
  • Lifting in the beams in pairs at night
  • Sliding the pairs of beams under the bridge

Construction Phasing - 3

slide-9
SLIDE 9

9

Chislehurst Road Bridge Reconstruction

  • Remove the existing surface to reduce the weight
  • Saw Cutting Pre-Stress Tendons, (existing deck load taken on

rail protection deck)

  • Pedestrians and Services remain on the unaffected East

Footway Construction Phasing - 4

  • Saw Cutting in preparation for the lifting out of the existing

beams

slide-10
SLIDE 10

10

Chislehurst Road Bridge Reconstruction

  • Break out/lift out Beam Segments
  • Break up sections of beams off of bridge away from the railway
  • Separate concrete from steel and remove from site

Construction Phasing - 5

slide-11
SLIDE 11

11

Chislehurst Road Bridge Reconstruction

  • First phase demolition completed
  • Installing new steel girders 1 to 4

Construction Phasing - 6

slide-12
SLIDE 12

12

Chislehurst Road Bridge Reconstruction

  • First Phase steelwork complete
  • Divert remaining services to new side of the bridge

Construction Phasing - 7

slide-13
SLIDE 13

13

Chislehurst Road Bridge Reconstruction

  • Completed first phase of deck
  • Service diversions complete
  • Pedestrians diverted to new footway
  • Demolition of East deck completed

Construction Phasing - 8

slide-14
SLIDE 14

14

Chislehurst Road Bridge Reconstruction

  • Complete steelwork
  • Install GRP enclosure below beams

Construction Phasing - 9

slide-15
SLIDE 15

15

Chislehurst Road Bridge Reconstruction

  • Complete new deck
  • Remove rail protection deck
  • Complete enclosure
  • Reinstate working areas

Construction Phasing - 10

slide-16
SLIDE 16

16

Chislehurst Road Bridge Reconstruction

  • Complete – Chislehurst Road Bridge Reconstruction

Construction Phasing - 11

slide-17
SLIDE 17

17

Chislehurst Road Bridge Reconstruction

Construction Overview and Phasing

Jon Elliott – Site Agent