Long-Baseline Neutrino Facility LBNF
Chamber 1 – Initial Occupancy Scenerio Discussions
- T. Lundin
Chamber 1 Initial Occupancy Scenerio Discussions T. Lundin 18 - - PowerPoint PPT Presentation
LBNF Long-Baseline Neutrino Facility Chamber 1 Initial Occupancy Scenerio Discussions T. Lundin 18 December 2017 Agenda Dimensions including tolerances Details of the walls, floors, doors Occupancy Scenarios Availability of
Long-Baseline Neutrino Facility LBNF
LBNF
12.18.17 2
LBNF
12.18.17 3 Current dimensions based on Arup’s 100% preliminary design drawings posted in DocDb 136. At the November final design kick-off meeting with Arup we discussed things that have changed (and may change) and will require modifications to the design
LBNF
12.18.17 4
LBNF
12.18.17
5
WWF and shotcrete is being replaced with non- metallic fiber shotcrete on all walls below the 4850L
LBNF
12.18.17 6
Note minimum and maximum dimensions for items within the excavation
LBNF
12.18.17 7
WWF and shotcrete is being replaced with non-metallic fiber shotcrete on all walls below the
– no hand troweling Floor tolerances will be +/- 3/8 inch. This means that that maximum point deviation from the assumed datum or elevation is +/- 3/8 inch and the maximum stacked or cumulative deviation is also +/- 3/8 inch.
Need floor loading to be defined.
LBNF
12.18.17 8
LBNF
12.18.17 9
LBNF
12.18.17 10
LBNF
12.18.17 11
LBNF
12.18.17 12
LBNF
12.18.17 13
LBNF
12.18.17 14
LBNF
12.18.17 15
LBNF
12.18.17 16
Note that the temporary bulkhead is being removed, and the center access drift is being centered
Cryogenics will be adjusting the footprint cryo equipment in the CUC accordingly.
LBNF
12.18.17 17
Blast doors/bulkheads separate “dirty” excavation and air exhaust spaces from “clean” science spaces
LBNF
12.18.17 18
Title Sub-project responsibility
Machine Shop (mucking ramp?)
Host Lab Survey network to allow positioning of the various components Host Lab Underground evacuation system Host Lab Fire detection system Host Lab GSM phone antenna and wireless network Host Lab Electrical distribution system with European type electrical power (230 V, 50 Hz) Host Lab Safety crews to monitor work done and its preparation Host Lab Survey team Host Lab Emergency intervention team Host Lab Procurement system to allow an effective procurement procedure for small material and tools needed locally Host Lab
LBNF
12.18.17 19
Title Rationale Exhaust ventilation ductwork to the base of the rock septum rather than the top Provide adequate circulation for occupation during warm structure construction. Temporary use of exhaust duct Mezzanine shift 4.8 m from end wall Avoid limiting access to end of detector Add a ninth and tenth connection points for mezzanine supports on rock wall and vertical connection point (horizontal and vertical connection points) provide flexibility for design of cryo equipment on the mezzanine Eliminate blast wall between chambers 1 and 2, shift central access drift to center of pillar Makes crane coverage symmetrical. The bulkhead is finished Jan 21, 2021. Chamber 2 excavation is finished April 19, 2021. Warm structure #1 starts May 3, 2021. CF to provide adequate connections for lighting and fire protection to be added below the mezzanine by others. Cryo needs somewhere to connect
Cryogenics will be adjusting the footprint cryo equipment in the CUC accordingly
LBNF
12.18.17 20
Title Notes CF to provide permanent Alimak type elevators for each chamber (Assume chamber 3 and 4 would be scope
9/13/2017: This is a new requirement, need to identify who has responsibility to come up with this requirement. 10/10/2017: no update. i) Need headcount, load, ii) work deck. Two requirements. 10/25/2017: Conveyance strategy TBD in December 2017. Conductivity testing for concrete slab 9/13/2017: Terri needs to define the need for the test and its requirements. 10/10/2017: We want high resistivity concrete in addition to non conductive rebar. Terri to verify 500 ohm-meter numbers 10/25/2017: Terri waiting for feedback from Veljko Radeko by next Design accommodations for a bridge crane 9/20/2017: Conveyance strategy TBD in December 2017 Additional monorail hoists? With removal of blast wall, do monorails between chambers become continuous over the septum 9/20/2017: Conveyance strategy TBD in December 2017 Mezzanine load increase - 10/16/17 LBNC presentation talked about need to provide updated loading parameters - are loads finalized? 9/20/2017: Documenting latest loading condition is specified. Requirements and ICDs to be updated. 10/10/2017: need update from David 10/25/2017: Cryo to provide worst case load numbers.
LBNF
12.18.17 21
Title Notes Underground data room requirement of 52 includes 2 CF racks (cryo is outside this room, DUNE needs 50) CF to reconfigure data room, meeting, and breakroom space in the CUC during final design 9/20/2017: Clarifying DUNE needs 50 10/25/2017: Need clarification regarding the size of racks. CF to provide cooling for racks. Temporary electrical distribution in chamber pit for cryostat assembly TBD by Dimitar 9/13/2017: Need requirement from cryostat. Terri to talk to CERN regarding this. 10/10/2017: no update 10/25/2017: No update. Jack to follow up with Dimitar. Electrical/data support for infrared cameras? 9/13/2017: No new requirement on CF. 10/10/2017: affects grounding
10/25/2017: Need info from Marzio. A system of emergency shut off switches for power distribution (?) Need to clarify if this for both temporary and permanent systems 9/13/2017: Permanent not in the pit above 4850L. Terri to talk to CERN about this. 10/10/2017: M. Andrews and Terri to talk to CERN in November 2017. 10/25/2017: No update. While not specifically requested, we should do a trade study comparing the cost of running all utilities below the 4850L across the rock pillar with the cost of three monorail hoists (the bridge crane is provided by Marzio, so doesn’t factor into the cost). 9/20/2017: Matt to provide a concept layout of the trench with the utilities in them. 10/25/2017: Need info on piping that will go in the trench. Require info from ARUP
LBNF
12.18.17 22
Title Notes Access Control System (key cards) 9/13/2017: On door to the leased space. Josh and Doug to check. 10/25/2017: In progress Industrial water, compressed air, and emergency telecom at chamber bottom 9/20/2017: Need requirement from cryostat, cryogenics and FD. 10/25/2017: In progress Add a temporary grounding network down into each detector pit 9/20/2017: Need requirement from cryostat, cryogenics and FD 10/25/2017: no update, in progress. Detector chamber floor loading definition Check unistrut and utility support locations and details Check mezzanine support connection locations and details