Central Kitsap High School Building 900 Renovation Design - - PowerPoint PPT Presentation

central kitsap high school building 900 renovation design
SMART_READER_LITE
LIVE PREVIEW

Central Kitsap High School Building 900 Renovation Design - - PowerPoint PPT Presentation

Central Kitsap High School Building 900 Renovation Design Development Review August 28, 2019 Lower Campus Building 900 Schedule Complete June 2018 Project Scope and Estimate Complete August 2018 Conceptual Design Complete -


slide-1
SLIDE 1

Central Kitsap High School Building 900 Renovation Design Development Review

August 28, 2019

slide-2
SLIDE 2

2

Lower Campus – Building 900

Schedule

  • Project Scope and Estimate
  • Conceptual Design
  • Schematic Design
  • Design Development (Board Approval)
  • Bid Opening
  • Construction Starts
  • Admin Spaces/Library Addition Opens

Complete – June 2018 Complete – August 2018 Complete - May 2019 August 28, 2019 March 2020 November 2020 January 2020

slide-3
SLIDE 3

3

Design Development – West Elevation

slide-4
SLIDE 4

4

Design Development – Floor Plans

2nd Floor 1st Floor

slide-5
SLIDE 5

5

Design Development – Floor Plans

2nd Floor 1st Floor CKSD Silverdale Library Shared

slide-6
SLIDE 6

6

Project Budget

MACC CK School District $ 4,115K Kitsap Regional Library $ 3,325K Total MACC: $ 7,440K Contingency (10%) and WSST $ 1,460K Total Construction Cost: $ 8,900K Professional Services $ 1,000K Owner Costs $ 250K FF&E and Moving $ 200K Project Reserves (≈5%) $ 500K Total Additional Costs: $ 1,950K RECOMMENDED PROJECT BUDGET $10,850K

Includes Lower Campus Costs

slide-7
SLIDE 7

7

Lower Campus – Building 900

Schedule

  • Project Scope and Estimate
  • Conceptual Design
  • Schematic Design
  • Design Development (Board Approval)
  • Bid Opening
  • Construction Starts
  • Admin Spaces/Library Addition Opens

Complete – June 2018 Complete – August 2018 Complete - May 2019 August 28, 2019 March 2020 November 2020 January 2020