C Line Rapid Bus 90% Design Karyssa Jackson, Community Outreach Coordinator TAAC August 2, 2017 Shawn Walding, Senior Engineer Metro Transit 1 Todays Discussion Informational Feedback from February Project development


  1. C Line Rapid Bus – 90% Design Karyssa Jackson, Community Outreach Coordinator TAAC August 2, 2017 Shawn Walding, Senior Engineer Metro Transit 1

  2. Today’s Discussion • Informational • Feedback from February • Project development update – Schedule – Funding • Design update – Platform renderings – Vertical separation • Communications outreach update • Preparing for Construction 2

  3. What did we hear from TAAC in February? Stations • Stay consistent • Developed BRT Design Guide • Continue to explore • ATCMTD Grant – Applied in navigational tools for June, potential award in station elements September • Beacon Deployment & Integration Roadwork • Maintain accessible, clear, • Defined through project continuous PAR through specifications construction: 3

  4. • Substantially replaces Route 19 C Line project overview – 8.5 miles from downtown (HCMC) to Brooklyn Center • Serves 7,600 people today, 9,300 by 2030 • Runs in mixed traffic • Faster trip – Pre-boarding fare payment – All-door boarding on 60-foot vehicles – In-lane stop (curb extensions) – Transit signal priority 2

  5. Coordinating C Line on Penn Avenue with Hennepin County, and City of Minneapolis • C Line BRT (Metro Transit) – Stations and related construction – Transit signal priority • Penn Avenue (Hennepin County) – Intersection reconstruction partnership – Reconstruction from Lowry to Broadway – Mill & overlay + ADA improvements, Plymouth–Broadway & Lowry–Dowling • Penn Avenue (Minneapolis) – Lighting 5

  6. Implementation schedule 2013 2014 2015 2016 2017 2018 2019 C Line Planning 2013-2016 TAAC Environmental review Touchpoints 2014-2016 Preliminary design 2016-2017 60% Bid Final design 2017 Construction 2018 Service begins 2019 We are here October-November 2016: Initial design considerations (intersection layouts, shelter & pylon placement) January-February 2017: Review station layout (general station element arrangement, curblines) September 2017: Share final station designs (placement of all station features, design treatments) September 2017-March 2018: Share construction plans 2018: Construction 2019: C Line opens with service on Penn Avenue, Olson Highway 6

  7. C Line Funding • Non-fleet project total cost: $20 million • Funding Plan is to pursue Metro Transit funds to match available federal funding • Planning for funding in place by late August 7

  8. 7 th & Park Temporary Stations on Olson Memorial Highway, Current Recommendation to move to Glenwood in long-term • Light rail construction will impact stations • Recommended long-term relocation to Glenwood (future project timed with light rail) 8

  9. Penn & Plymouth 9

  10. Penn & Golden Valley 10

  11. C Line Community Outreach Station Neighbor Outreach - Businesses and residents located in the immediate vicinity of a proposed station were engaged through in- person visits and mailed letters. The majority of C Line outreach has been focused on direct Neighborhood and Community communication to station neighbors Organizations Presentations and Outreach impacted by future C Line stations. These interactions have revealed specific needs or concerns of neighbors who have disabilities within Pop-Up Outreach – Bus and Stop the C Line corridor and have been integrated into design development. Open Houses – Traditional and Mobile 11

  12. Construction Outreach – How to stay updated Where to find updates: Who to contact: • Sign up for C Line • Project Hotline (Details Update Newsletter - coming soon) metrotransit.org/c-line- • Metro Transit project Community Outreach - • Community Meetings Karyssa Jackson • Presentations • Metro Transit Customer Relation – 612-373- • Project Partners: 3333 – Penn Avenue Community Works – City of Minneapolis 12

  13. metrotransit.org/c-line-project Karyssa Jackson, Community Outreach Coordinator 612-349-7396 | Karyssa.Jackson@metrotransit.org Shawn Walding, Senior Engineer 612-341-5668 | shawn.walding@metrotransit.org BRT/Small Starts Project Office 13

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.