Broadway Developm ent There is little that is more disturbing to - - PowerPoint PPT Presentation

broadway developm ent there is little that is more
SMART_READER_LITE
LIVE PREVIEW

Broadway Developm ent There is little that is more disturbing to - - PowerPoint PPT Presentation

Broadway Developm ent There is little that is more disturbing to the public than to see a significant Public Works project in progress, and to observe the reinstatement of the pavement surface only to have the entire street dug up again for


slide-1
SLIDE 1

Broadway Developm ent

slide-2
SLIDE 2
slide-3
SLIDE 3

“There is little that is more disturbing to the public than to see a significant Public Works project in progress, and to observe the reinstatement of the pavement surface only to have the entire street dug up again for an entirely different purpose a short time later.”

Federation of Canadian Municipalities – Best Practices

slide-4
SLIDE 4
  • Infrastructure is installed at different times
  • Infrastructure has different lifecycles. (Pavement 15 years

versus water pipes 75 years)

  • Components managed by different divisions or entirely

different organizations

  • Different sources of funding

It is extremely important for the various infrastructure renewal programs to be coordinated to the maximum extent possible!!

slide-5
SLIDE 5
  • Inventory of all infrastructure related assets
  • Condition assessments of all the various types of municipal

infrastructure

  • Prioritize information collected from condition assessment

(worst condition, most critical, highest number of users, etc.)

  • Develop multi-year plans for infrastructure replacement
  • Identify growth areas in the City and future development

projects

  • Designing infrastructure to accommodate future development
slide-6
SLIDE 6

Project Scope (Highway 9 to Highway 10):

  • Water distribution system
  • Storm sewer system
  • Sanitary sewer system
  • Roadways
  • Sidewalks
  • Traffic lights
slide-7
SLIDE 7

Water Main

  • 8” to 12” pipe (200-300 mm)
  • Mostly cast iron
  • Large amount of 1909 to 1914 piping
  • Lots of lead services remain
  • Water main breaks increasing in the last ten years

Sanitary Sewer Mains

  • Primarily 12” pipe (300 mm)
  • Pipes made of clay
  • Large amount of 1909 to 1914 piping
slide-8
SLIDE 8

Alexandra Avenue

slide-9
SLIDE 9

Near Alexandra Avenue

slide-10
SLIDE 10

Exhibition Street to Alexandra Avenue

slide-11
SLIDE 11

Storm Sewer Mains

  • Primarily 12” to 24” (200 mm to 400 mm) pipe
  • Pipe material is mostly concrete
  • Most of the piping is 1950 and newer, however some of the

pipe is from 1915.

  • Root infiltration in many areas
  • Catch basins and leads are in poor condition
slide-12
SLIDE 12

Sanitary sewer along Broadway Street

slide-13
SLIDE 13

Broadway Street sanitary sewer from Clark Avenue to Bradbrooke Avenue

slide-14
SLIDE 14

Broadway Street sanitary sewer Clark Avenue to Broadway Avenue

slide-15
SLIDE 15
  • Aging Infrastructure (~100 years old): Increased O& M costs
  • Insufficient capacity due to community growth: Restriction of

future growth

  • New regulations and industry standards: Non-Compliance with

regulators

slide-16
SLIDE 16

 Integrated Engineering

  • Derek Trischuk
  • Darren Anholt
slide-17
SLIDE 17

Questions & Answers

slide-18
SLIDE 18
  • Financial restriction prevented large-scale reconstruction.
  • Condition of underground infrastructure was unknown, as

condition assessments had not yet been conducted.

  • Lack of infrastructure master plans.
  • Upgrades required to accommodate development were not

properly identified.

slide-19
SLIDE 19
  • The street will be reconstructed on a block-by-block basis.
  • The arrangement upon which the excavation will be carried out

will evaluate on the same basis.

  • Many factors will influence the process used. These include

street width, location of underground infrastructure and other underground utilities, type of equipment used by the contractor and even weather conditions.

  • Every effort will be made to ensure traffic flow is maintained as

efficiently as possible.

slide-20
SLIDE 20
  • As part of the engineering planning process, traffic

accommodation and business access will be reviewed in detail with discussion involving business members and stakeholders.

  • Every effort will be made to reasonably minimize the amount of

disruption to the downtown business community. However, will not compensate for financial losses.

slide-21
SLIDE 21
  • Past BCF grant intakes for the City of Yorkton have been for

66% of the total project cost:

  • 33.3% Federal
  • 33.3%, Provincial
  • with City responsible for the remaining 33.3%
  • The City anticipates grant-funding distribution will remain the

same for this application; however, details have not yet been released.

slide-22
SLIDE 22
  • The project would be tendered in 2015.
  • The proposed timeline to rebuild the entire length of Broadway

is three years.

slide-23
SLIDE 23
  • If the project does not receive federal or provincial funding, the project

will be delayed.

  • Future grant opportunities would be pursued upon their release.
  • The project would remain a priority for the City and would be

proposed as a future capital project, however, a multi-year phasing approach would have to be explored due to financial constraints.

  • Roadway resurfacing could take place without replacing underground

infrastructure subject future underground failures and replacements. This is not a recommended option as it is a less efficient use of funds.

slide-24
SLIDE 24
  • Regardless of the method of funding for the project, the City’s

contribution required will be substantial.

  • As part of the City’s long range planning, longer-term

borrowing options will be explored.

slide-25
SLIDE 25
  • Water and sewer services will be upsized to accommodate future

changes in zoning, building code requirements and for fire suppression purposes.

  • At this time service connections have been included in the total

project cost estimate, however, cost sharing or how the service connections will be paid for has not yet been determined.

slide-26
SLIDE 26
  • All City owned trees along Broadway would be evaluated based
  • n age and health. Where possible healthy trees will be

retained.

  • It may be difficult to preserve trees; especially those located

above water and sewer connections.

  • During any reconstruction project it is sometimes difficult to

work around trees without jeopardizing the critical root zone.

  • New trees would replace those that are removed.
  • Locations would be better planned to avoid future disturbances.
slide-27
SLIDE 27
  • The proposed preliminary design maintains existing ROWs.
  • The City has no intent of widening the existing ROW.