broadway corridor phase iiia broadway hildebrand
play

Broadway Corridor Phase IIIA (Broadway-Hildebrand) March 4, 2014 - PowerPoint PPT Presentation

Broadway Corridor Phase IIIA (Broadway-Hildebrand) March 4, 2014 Presented by: Claudia Tovar, P.E., Transportation & Capital Improvements 1 Introductions Transportation & Capital Improvements Department (TCI) Mike Frisbie,


  1. Broadway Corridor Phase IIIA (Broadway-Hildebrand) March 4, 2014 Presented by: Claudia Tovar, P.E., Transportation & Capital Improvements 1

  2. Introductions  Transportation & Capital Improvements Department (TCI)  Mike Frisbie, P.E., Director/City Engineer  Razi Hosseini, P.E., Assistant Director  City of San Antonio Project Management Team  Ruben Guerrero, P.E., Assistant City Engineer  Arnold Ramirez, P.E., Project Manager  Claudia Tovar, P.E., Project Engineer  John Donnelly, Capital Project Officer  Design Consultant: Freese & Nichols, Inc.  Construction Contractor: Texas Sterling Construction 2

  3. Agenda  Project Scope  Phasing Status Update  Challenges  Schedule Update  Communication Plan 3

  4. Project Scope Drainage Improvements to convey the 100 year storm event to be completed in multiple phases of construction:  Roadway Improvements  SAWS water and sewer upgrades  CPS gas upgrades  Under ground conversion of overhead utilities within the Broadway/Hildebrand Intersection  Water quality enhancements  San Antonio River Outfall enhancements  Miraflores Park Restoration 4

  5. Broadway at Burr Existing flooding 5

  6. Completed Phases  Phase 1-11:  Underground utilities  Partial Phase 12:  Underground utilities  Street Reconstruction  Phase 16:  Underground utilities  Street Reconstruction 6

  7. Completed Phases Underground Conversion Installation 7

  8. Hildebrand Street Reconstruction Southside Hildebrand between Broadway and SA River 8

  9. Phases in Construction  Partial Phase 12  Utilities: Water, Sewer  Drainage/Water Quality Enhancements  Street Reconstruction  Partial Phase 13  Utilities: Sewer  Street Reconstruction  Partial Phase 19  Utilities: Water, Sewer  Drainage  Street Reconstruction 9

  10. Phases 12 Construction Completed Roadway, Water, and Sanitary Sewer line 10

  11. Continuation of Phase 12 Construction Water Line Installation 11

  12. Upcoming Phase Phases 13 Construction Current Phase 12

  13. Phases 19 Construction Upcoming Phase Current Phase Sanitary Sewer Installation 13

  14. Upcoming Phases  Phase 14:  Utilities: Sewer  Street reconstruction  Phase 17 (Weekend Closures):  Drainage  Street reconstruction  Phase 18:  Utilities: Water/Sewer  Drainage/Water quality enhancements  Street reconstruction  Partial Phase 19:  Hildebrand intersection  North side of Hildebrand east of Broadway  Phase 20: Final asphalt layer, pavement markings, signage, cleanup 14

  15. Phase 14 Construction Roadway/Sanitary Sewer line construction 15

  16. Phase 17 Construction Drainage/Roadway Construction (intersection ) 16

  17. Continuation of Phase 17 Construction Drainage/Roadway @ intersection 17

  18. Phase 18 Construction Roadway/Utility on Hildebrand 18

  19. Phase 19 Construction Current Phase Upcoming Phase Roadway construction on Hildebrand 19

  20. Phase 20 Construction Traffic signals, curbs & median site plan 20

  21. Challenges  Rain Events  Placement of Utilities in limited working area  Unforeseen Utilities  Soil Conditions  Maintaining Access to Business Owners  Additional Signage  Additional use of off duty Police Officers 21

  22. Unstable Soil Conditions 22

  23. Communication Plan  Signage will be utilized to communicate with motorists  Includes electronic signage  Specialized signs placed at business driveways within the project area to assist in directing traffic  E-mail blasts for project-specific stakeholders and interested parties will be provided weekly, with unexpected happenings reported daily  Continue use of Broadway-Hildebrand project website  TCI Capital Project Officer (CPO) and /or project inspector will continue face- to-face contact with area businesses weekly or more often as needed 23

  24. Project Schedule  Construction Start: January 2013  Estimated Completion Date: July 2014  Contractor is required to work a 6 day work week from sunrise to sundown 24

  25. Questions?  Ruben Guerrero, TCI Assistant City Engineer (210) 207-7887  Arnold Ramirez, P.E., TCI Project Manager (210) 207- 6309  Claudia Tovar, P.E., TCI Project Engineer (210) 207-8398  John Donnelly, TCI Capital Project Officer (210) 207-4019 City of San Antonio web-sites :  www.sanantonio.gov/publicworks  www.sanantonio.gov/cims Broadway – Hildebrand website: www.sanantonio.gov/CIMS/Projects/BroadwayHildebrand/aspx 25

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend