Background of the ECA Study on IAP and Vlore PPT 2011 Ministerial - - PowerPoint PPT Presentation

background of the eca study on iap and vlore ppt
SMART_READER_LITE
LIVE PREVIEW

Background of the ECA Study on IAP and Vlore PPT 2011 Ministerial - - PowerPoint PPT Presentation

Background of the ECA Study on IAP and Vlore PPT 2011 Ministerial Council of the Energy Community mandates the Secretariat to conduct activities to attract investors in power generation in the Western Balkan countries and to advance the


slide-1
SLIDE 1

Energy Community Secretariat Energy Community Secretariat 1

Background of the ECA Study on IAP and Vlore PPT

  • 2011 – Ministerial Council of the Energy Community mandates the Secretariat to conduct activities to attract

investors in power generation in the Western Balkan countries and to advance the development of the so- called Gas Ring Concept;

  • The Secretariat, with support letters from the WB6 countries, applied for a WBIF regional study South East

Europe Gas Power Consortium;

  • 2012 – WBIF Steering Committee approves the application in 2012 for two study phases;
  • World Bank nominated as implementer of the study, with the Secretariat being a partner. The World Bank

contracted ECA to carry out the study;

  • 2015 – based on the findings of the Interim Report – South East Europe Gas Power Consortium study and

based on the presentation of ECA to the WBIF SC, EC as financier of the study, recommended to deepen the analysis in the 2nd phase to the feasibility analysis of the Vlora PPT and its connection to TAP and the update of the feasibility analysis of the IAP project

  • 2016 – The World Bank and ECS agreed, and cooperated in defining the scope of the 2nd phase and the EC

gave final go ahead in May

  • 2016 – 2017 ECA carried out the analysis and submitted the two reports: IAP financial FS and Vlore TPP FS
slide-2
SLIDE 2

1. Prospects of Gas to Power in Albania, focus on CCGT in Vlore a) Refurbishment, potential expansion and pipeline to TAP offtake b) Definition and assessment of the economic and financial feasibility c) Ownership and financing structures & identifying potential investors d) Proposal for a realistic approach to implementation 2. Review of 2014 study on Ionian Adriatic Pipeline a) Update economic and financial component of the feasibility study b) Focus will be on throughout volume projections, impact on transmission tariffs, and on changes in the price assumptions

In agreement with project partners, focus shifted on gas development

  • pportunities arising from Trans Adriatic Pipeline
  • Scope of work for Phase I of the study covered the potential for gas to
  • power. The results of interim report indicated that the geographic scope

should be narrowed on opportunities arising from the Trans Adriatic Pipeline (TAP) – Gas interconnector Greece-Albania-Italy (part of Southern Gas Corridor with TANAP)

  • Phase II consequently focuses primarily on two following tasks:
slide-3
SLIDE 3

ECONOMIC CONSULTING ASSOCIATES

www.eca-uk.com

Presentation to WBIF Project Financiers’ Group

Gas to Power Phase 2

Skopje, 26 April 2018 Project managed by the World Bank

slide-4
SLIDE 4

4

Contents

 IAP Feasibility Study

IAP in the region – key drivers

Factors to improve IAP feasibility

Grant funding gap

 Vlore Feasibility Study

Gas to power at Vlore: commercial viability

Funding options

slide-5
SLIDE 5

5

IAP’s strategic importance – a key channel for Caspian gas to Central Europe

5 Bcm/y pipeline with tie in points in AL, ME, HR, BiH and possibly Kosovo

Supported by WBIF (Feasibility Study in 2014;

current study on ME and AL sections)

Project Company to be established in 2018 (SOCAR as engineering consultant)

IAP’s strategic importance:

Can play a pivotal role for gasification

  • f West Balkan region

Can be considered part of the EU’s Southern Gas Corridor

Can support decarbonisation of West Balkans

With TAP expansion to 20 Bcm, can support EU supply diversification

IAP PECI/PMI pipelines BRUA IGB TAP Eagle LNG Croatia LNG

slide-6
SLIDE 6

6

IAP Transmission tariff ranges Economic NPV breakdown

Integrating IAP with the Southern Gas Corridor will ensure viability

Cost recovery tariffs for IAP would need to be high

not unusual for international pipeline projects

Low throughput volumes - Offtake markets along its route alone are too small

Integrating project with Southern Gas Corridor ensures viability

International transmission of Caspian gas to European markets will be key

Takes advantage of TAP and of possible capacity expansion to 20 Bcm

Project is economically feasible

Economic NPV: €1.3 billion

CO2 reduction from switching to gas for heating is key driver

2.2 5.2 1.9

3.2 7.1 2.7

5 10.6 3.7 2 4 6 8 10 12 Business Model ❶ Business Model ❷ Business Model ❸

€c/cm

slide-7
SLIDE 7

7

Conditions that can ensure feasibility of IAP (1/2)

❶ Secure

throughput for IAP in short term

❷ Provide grant

funding

Strengthen Croatian transmission (to max south-north transit)

Ensure TAP capacity expansion to 20 Bcm

Ensure significant volumes of Croatia’s demand is met by IAP (Between 40% and 50% of demand)

Expedite gas to power developments in Montenegro, Croatia, Albania and BiH (~1,5 GW extra capacity until 2025)

Accelerate gasification efforts of distribution consumers in Montenegro, Albania and BiH

Grant funding needs to ensure competitive transmission tariff: 60% (~€370 million)

Could be partially covered by WBIF and CEF , however gap remains

❸ Apply tariff

minimising business model

Split the CAPEX treatment of the project:

  • Croatian segment integrated into Plinacro’s asset base
  • AL-ME section as an international pipeline

Does not require separate development, but only applies for tariffication purposes

slide-8
SLIDE 8

8

Conditions that can ensure feasibility of IAP (2/2)

❹ Facilitate

financability of the project

Provide regulatory exemptions

Attract investors that would see IAP as part of a portfolio

IAP on its own does not need to generate high returns, but can be considered as a means to attract higher returns ‘downstream’

Involve Caspian and Middle Eastern gas suppliers could act as project sponsors

Ensure high equity portion of the investment

Provide concessionary loans with low interest rates reducing the debt repayment obligation

slide-9
SLIDE 9

9

IAP grant funding requirements - €370 million could be partially covered by WBIF and CEF

Cost component AL ME HR Total Total investment costs €mm 192 121 298 611 Estimated grant funding requirement €mm 115

(60% of total)

73

(60% of total)

179

(60% of total)

366 

Grant funding can be secured from three main sources:

Western Balkan Investment Framework (WBIF)

can support up to 20% of total project cost

Could be used for Albania and Montenegro

Connecting Europe Facility (CEF)

CEF can provide grants of up to 50% of CAPEX for PCI projects

Would requires Croatian section to be considered a PCI – currently it is not

IPA country allocations

Could be used for Albania and Montenegro section

slide-10
SLIDE 10

Gas to Power Phase 2 IAP Feasibility

Vlore conversion to gas

slide-11
SLIDE 11

11

Summary points for Vlore gas conversion

Commercial viability of Vlore with gas is at best marginal

PPAs likely to be reliant on OSHEE and KESH who can blend it with hydro

Balancing market, spot sales and export sales volumes likely to be very small

Preferred private participation option is leasing model

KESH leases the plant to a private

  • perator including all contracts

If not attractive, a tolling model should be considered

Government reforms needed to attract private operators

Balancing market and electricity market rules Vlore TPP net profits Leasing model

KESH

Operato r

O&M contract LTSA

Ansaldo Engineer

Reha b. EPC Gas supplier Fuel supplier Fuel oil purchase agreements Gas sale agreement Operating Company Leasing Agreement BS contract Albania, Kosovo or

  • ther TSOs

OShEE CfD Greece, Italy,

  • r other

markets Export spot sales Eligible consumers CfD

slide-12
SLIDE 12

12

Roadmap – GoA actions to needed to mitigate risks

Electricity market reforms

Enable Vlore to negotiate long term PPAs – if not possible with eligible consumers – KESH to relinquish some of its OSHEEE contracts

Finalise electricity market rules in line with AMM

Clarify and implement Balancing market provisions, pricing and processes

Coupling between Albania and Kosovo market

Integration of Albania into wider regional electricity market

Determine transitionary leasing agreement for private entities until gas becomes available

Gas market reforms

Finalise HGA to enable gas contract negotiations

Design a realistic gasification strategy for Vlore and Fier areas

Draft gas transmission codes and tariffs

(tariff regulation passed in late 2017) 

Assign responsibility of gas transmission development (decided to be the TSO – Albgaz)

Continued support for IAP to secure diversity

  • f gas supply
slide-13
SLIDE 13

13

Role for WBIF funding could be to support Vlore’s feeder pipeline from TAP

Limited generation means low throughput volumes for Fier – Vlore pipeline

Unless high volume PPA subsidised by KESH/OSHEE are secured

Feeder pipeline to Vlore from TAP

Non-gas demand likely to be limited

Risk of high tariff penalising Vlore offtake even more

Fier – Vlore pipeline could be supported

CAPEX not certain yet – currently investigated by SECO (Swiss Development Cooperation)

~40 km Extension of IAP

Electricity exports into region could displace coal fired power generation

SOCAR support secured by Albgaz as lead engineer

Fier-Vlore pipeline

slide-14
SLIDE 14

ECONOMIC CONSULTING ASSOCIATES

www.eca-uk.com

Fred.Beelitz@eca-uk.com

Managing Director, ECA

slide-15
SLIDE 15

ECONOMIC CONSULTING ASSOCIATES

www.eca-uk.com

Background slides

slide-16
SLIDE 16

16

Key drivers for the development of IAP

Croatia as anchor offtake market

Only established and sizable gas market connected to IAP

IAP as diversity and security of supply option for Croatia

Expansion of TAP and access to wider gas sources

90% of TAP already contracted for the Italian market – expansion to 20 BCM is a precondition for IAP

Other supply sources (Iran, Iraq, Kurdistan) or SOCAR Azeri gas needed

International transmission through Croatia

Prohibitively high tariffs required if IAP does not serve gas beyond Croatia

Planned Croatian transmission strengthening by Plinacro

Competitiveness of gas supplies through IAP

Would be same as TAP, which are linked Italian spot market

Gasification strategies of Albania, Montenegro, and BiH

slide-17
SLIDE 17

17

IAP offtake potential along IAP route is small – Will depend on gasification policies

  • Main potential
  • fftakers (power +

industry) covered by TAP

  • IAP throughput

depends on distributed users in northern part

  • Very limited short-run

demand

Albania Montenegro BiH Croatia

  • Montenegro demand

can be fully covered by IAP

  • Offtake will depend
  • n gas to power

strategy

  • Overall, small

demand potential

  • Highly uncertain, as

no gasification plans

  • Gas to power

potential could provide necessary anchor load

  • Uncertainty around

gas to power plans

  • Treated as a separate

sensitivity in our study

  • Largest potential
  • fftake market
  • Gas on gas

competition will require competitive IAP supply

  • Stagnant gas

demand since 2009 (~3 Bcm)

  • Gas to power plans

have stalled

1.8 1.2 0.0 0.5 1.0 1.5 2.0 2.5 2025 2040 2050 Bcm Best Case Worst Case 2.1 1.1 0.0 0.5 1.0 1.5 2.0 2.5 2025 2040 2050 Bcm 1.1 0.5 0.0 0.5 1.0 1.5 2.0 2.5 2025 2040 2050 Bcm 1.3 0.2 0.0 0.5 1.0 1.5 2.0 2.5 2025 2040 2050 Bcm

slide-18
SLIDE 18

18

Transit beyond Croatia is key for IAP to be viable – IAP to form part of the Southern Corridor

❶ Can sufficient transit be secured to bridge low initial

  • fftake from West Balkan markets?

❷ Can transmission bottlenecks in Croatia be overcome? ❸ Can IAP supplied gas compete

  • n Central European Gas Hubs?

Transit to overcome initial phase of very low throughputs

Possible offtake markets: Hungary (9 Bcm/y), Slovenia

(1 Bcm/y), Austria (9 Bcm/y) and CEGH 

Offtake will depend on IAP tariffs and ability to compete with existing suppliers

Displacing existing supplies however will take more than just low prices

Plinacro does not perceive this to be a problem

Existing connection to Hungary would be sufficient for exports up to 3 Bcm/y – this is even strengthened with LNG development package

To Slovenia, €60 million additional investment is needed

This will crucially depend on the IAP transmission tariff

We use the combined Italian and Slovenian transmission tariffs as comparator

Uncertainty of IAP tariff and possible offtake means that we have treated international transit as a sensitivity parameter

slide-19
SLIDE 19

19

Total potential throughput as estimated by ECA

Higher short- medium-run demand than FS due to transit flows

High dependence

  • n Croatian

demand and transit flows in short-run

Optimistic cases see IAP’s 5 BCM capacity reached by 2040

1000 2000 3000 4000 5000 6000 7000 Worst Base Good Best Worst Base Good Best Worst Base Good Best Worst Base Good Best Worst Base Good Best Worst Base Good Best 2025 2030 2035 2040 2045 2050

mmcm

Albania Croatia Montenegro Transit IAP FS - gas IAP FS - coal

slide-20
SLIDE 20

20

Approach to tariff analysis – three separate business models

Business model ❶ IAP Company Business model ❷ Regulated TSO Business model ❸ AL-ME as IAP Company + HR section as regulated TSO

Project treated as a standalone

IAP Company develops, owns and operates the pipeline

One cost recovery tariff applies for the whole pipeline on the basis of a regulated return

Postage stamp tariff HR ME AL

IAP split in three segments

Each segment developed and financed by national TSOs.

Tariffs apply that are in line with national regulated transmission tariffs

IAP segments integrated into national networks

Combination of ❶ and ❷

Croatian segment integrated in Croatian asset base

Segments in ME and AL combined as a ‘small IAP’ and treated as standalone

Tariff in Croatia based on existing tariff regime

Tariffs for AL-ME section: postage stamp cost recovery HR ME AL HR ME AL

slide-21
SLIDE 21

21

Combination of ME-AL as standalone and the HR segment integrated yield lowest tariffs

All business models above critical threshold level of 1.9 €c/cm

Based on combined Italian and Slovenian transmission tariffs

Small IAP yields lowest tariffs

Despite additional Croatian investments assumed for northern

Regulated TSO worst

  • utcome

BM ❸ implies that non-IAP consumers in Croatia subsidise the Croatian segment

5.0 3.2 2.6 2.2 1.1 1.0 0.9 0.8 1.1 1.0 0.9 0.8 3.0 2.2 1.9 1.7 6.5 3.9 3.1 2.7 2.6 1.7 1.3 1.1 0.0 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0

Worst Base Good Best Worst Base Good Best Worst Base Good Best BM ❶ BM ❷ BM ❸ €c/cm

IAP HR AL ME AL-ME section

slide-22
SLIDE 22

22

Sensitivity – tariffs only fall under the threshold level under the most optimistic of cases

Tariffs with CAPEX variation

Tariff only sufficiently low if CAPEX assumed to be 30% lower and assuming the most

  • ptimistic demand scenario

Under Base Case, CAPEX would need to be 50% lower

Tariff low enough under high throughput and 5-6% rate of return scenarios

But setting 5-6% rate of return gives IRR below 2%

Tariffs with rate of return variation

5.0 3.2 2.6 2.2 3.7 2.6 2.2 1.9 3.3 2.1 1.7 1.5 2.7 2.0 1.7 1.5 7.5 4.8 3.7 3.1 5.0 3.5 2.9 2.4 0.0 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 Worst Base Good Best Worst Base Good Best BM ❶ BM ❸

€c/cm

5.0 3.2 2.6 2.2 4.0 2.6 2.0 1.7 3.3 2.3 2.0 1.7 6.0 3.9 3.1 2.6 4.1 3.0 2.5 2.1 0.0 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 Worst Base Good Best Worst Base Good Best BM ❶ BM ❸

€c/cm

slide-23
SLIDE 23

23

Sensitivity – Additional interconnector to BiH can make a difference, less so for Kosovo

Tariffs with BiH interconnector

Tariff becomes competitive in the most optimistic BiH gas demand scenarios and most

  • ptimistic other throughput

scenarios

Kosovo demand would only be significant if coal fired power generation is replaced by gas - unlikely

Tariffs with Kosovo Interconnector

5.0 3.2 2.6 2.2 3.7 2.6 2.2 1.9 3.3 2.5 2.2 1.9 2.6 2.1 1.9 1.7 0.0 1.0 2.0 3.0 4.0 5.0 6.0 Worst Base Good Best Worst Base Good Best BM ❶ BM ❸

€c/cm

5.0 3.2 2.6 2.2 3.7 2.6 2.2 1.9 3.7 2.6 2.2 1.9 3.0 2.3 2.0 1.7 0.0 1.0 2.0 3.0 4.0 5.0 6.0 Worst Base Good Best Worst Base Good Best BM ❶ BM ❸ €c/cm

slide-24
SLIDE 24

24

Approach

IAP is economically viable – CO2 reduction from switching to gas for heating is key driver

❶ NPV of avoided cost of gas to power

Displaces coal fired power generation

❷ NPV of gas used for heating ❸ NPV of transit revenue ❹ NPV of total infrastructure cost Economic NPV of IAP

Separate calculations for the displacement of fuel oil, coal, wood fuel and electricity Transit tariff calculated as cost recovery tariffs As estimated in the previous sections and the Gas Masterplans

Economic NPV: EUR 1.1 billion

Remains positive across different sensitivity analyses

Key driver: environmental benefits from switching to gas through Co2 reduction

slide-25
SLIDE 25

25

Four potential offtake options for Vlore power

Option 1 Spot market sales on APE

Vlore to compete with imports, which is feasible for gas, difficult with fuel oil

Small volumes: dispatch results have very few months where Vlore is highly utilised Option 2 PPA/CfD with:

OShEE

Eligible customers

KESH could blend hydro and Vlore prices – however, would result in price increases

Current household price: 69 EUR/MWh; Vlore VC: 77 EUR/MWh (fuel oil) / 66 EUR/MWh (gas) Option 3 Balancing service contracts

Kosovo

Albania

ENTSO-E requirements mean 150 MW of reserve in Albania and 270 MW for Kosovo

Requires the set up of Balancing Market Option 4 Exports to Kosovo, Macedonia, Italy (via Montenegro) and Greece

Once gas supply secure, exports are feasible but crucially depend on price of gas

Vlore will have to trade flexibly and short term Low potential Medium potential High potential Medium potential

slide-26
SLIDE 26

26

200 400 600 800 1000 1200

2014 Jan 2014 Jun 2014 Nov 2015 Apr 2015 Sep 2016 Feb 2016 Jul 2016 Dec

MW 200 400 600 800 1000 1200

2014 Jan 2014 Jun 2014 Nov 2015 Apr 2015 Sep 2016 Feb 2016 Jul 2016 Dec

MW 200 400 600 800 1000 1200

2014 Jan 2014 Jun 2014 Nov 2015 Apr 2015 Sep 2016 Feb 2016 Jul 2016 Dec

MW 200 400 600 800 1000 1200

2014 Jan 2014 Jun 2014 Nov 2015 Apr 2015 Sep 2016 Feb 2016 Jul 2016 Dec

MW

Results of dispatch model – in a competitive power market Vlore would hardly be dispatched

Gas price @ Italian price +5% Gas price @ Italian price parity Gas price @ Italian price -5% Gas price @ Italian price +10% Vlore dispatch

slide-27
SLIDE 27

27

Proposed commercial strategy for Vlore – mix of PPA, Balancing Service and exports

Post-gas supply offtake:

  • Vlore TPP standalone PPA/CfD
  • Participate in Balancing Market in

Kosovo and Albania

  • Exports to Kosovo, Macedonia, Greece,

Italy

Vlore power standalone CfDs to provide baseload for gas contract negotiation

If gas CfD with eligible consumers not possible, requires KESH or OShEE to blend Vlore gas with hydro

Participation in Balancing markets in Kosovo and Albania – this could be

  • ne common market

Remaining production exported at short term and hourly basis

Securing CfD/PPA is key for:

Continuous operation and therefore faster reaction time to export spreads

Bargaining position for gas contract negotiation Reserved for Balancing PPA/CfDs/eligible consumers

Capacity (MW)

8760 100 50 70

Exports/APE sales

slide-28
SLIDE 28

28

Vlore unlikely to recover costs – even with high proportion of balancing or a high-priced PPA

Vlore TPP revenues Vlore TPP net profits

Revenues across different contract mixes shown

Includes annualised fixed O&M costs (4.5 million EUR/y)

Excludes annuity of investment

Commercial case for Vlore difficult unless:

Regulated tariffs for balancing services (BS) to recover fixed cost

High value PPAs

Commercially optimised export strategy

PPA BS Exports Even split 34 MW 34 MW 32 MW High PPA 75 MW 12.5 MW 12.5 MW High Reserve 0 MW 100 MW 0 MW High Exports 12.5 MW 12.5 MW 75 MW

slide-29
SLIDE 29

29

Key factor for Vlore competitiveness is the combination of electricity and gas prices

Analysis for base case scenario assuming 75% of capacity sold as export or PPA

Gas price/electricity price combination in 2016 would not have been favourable

5 10 15 20 25 30 35 40 45 20 30 40 50 60 70 80 90 100 Delivered gas price, €/MWh Electricity price, €/MWh

Price combination in this area, where Vlore can generate profits Average monthly Italian gas prices and HUPX electricity prices in 2016

slide-30
SLIDE 30

30

Vlore status quo with gas switching is lowest cost option

Sunk investment cost 112 mm EUR

Gas Pipeline cost ~35 mm EUR

Annual Fixed cost 4.5 mm EUR

Non-fuel Variable cost 138 EUR/OH

Net efficiency 42%

❶ 100 MW at Vlore with gas ❷ Expansion to 300 MW at Vlore with gas ❸ New build 200 MW at Fier

Sunk Investment cost 112 mm EUR

Gas Pipeline cost ~35 mm EUR

Expansion cost 248 mm EUR

Annual Fixed cost 6.8 mm EUR

Non-fuel Variable cost 138 EUR/OH

Net efficiency (old 100 MW) 42%

Net efficiency (new 200 MW) 50%

Sunk Investment cost 112 mm EUR

Expansion cost 263 mm EUR

Annual Fixed cost 8 mm EUR

Non-fuel Variable cost 138 EUR/OH

Net efficiency (diesel) Vlore 44.8%

Net efficiency Fier 50%

79 70 66 63 102 85 42 76 71 116

66 EUR/MWh 76 EUR/MWh 84 EUR/MWh

96 84 77

slide-31
SLIDE 31

31

Five business models were assessed and risks analysed to recommend on suitable structure

Business model options

Option 1: Status Quo

Option 2: Tolling model

Option 3: Leasing model

Option 4: Partial privatisation

Option 5: full privatisation

Risk assessment

  • Offtake risk
  • Financing risk
  • Gas supply risk
  • Fuel oil risk
  • Contract risk
  • Operational risk
  • Regulatory risk
  • Price risk

Recommended Business model based on:

  • Risk analysis
  • Feasibility
  • Ease of

implementation

slide-32
SLIDE 32

32

ECA favoured option: leasing model

KESH owner without commercial or technical risk

KESH remains owner of the plant, but leases asset to an operating company at a fee

No upfront cost for private entity – financing debt remains with KESH

Risks (and commercial rewards) borne by private operator:

Gas contract negotiation

Power contract mix to be optimized by private entity

KESH/GoA no role in operations

Recovered through regulated tariffs – net of leasing fee

Gas pipeline treated separately – developed by AlbGas

KESH Operator O&M contract LTSA Ansaldo Engineer Rehab. EPC Gas supplier Fuel supplier Fuel oil purchase agreements Gas sale agreement Operating Company Leasing Agreement BS contract Albania, Kosovo or

  • ther TSOs

OShEE CfD Greece, Italy,

  • r other

markets Export spot sales Eligible consumers CfD

slide-33
SLIDE 33

33

Second-best option: Tolling model

KESH owner with commercial risk, operational risk for tolling company

KESH owns the plant, contracts for fuel, and sells electricity – commercial risk

Tolling company receives tolling fee and carries operational and technical risks of plant

O&M, rehabilitation and LTSA to be contracted by private tolling company

GoA still plays an important role in the value chain through KESH

Will require a non-standard tolling arrangement incl. rehabilitation costs

TEC-Vlore could take over from tolling company at a predetermined point

KESH Operator O&M contract LTSA Ansaldo Engineer Rehab. EPC Gas supplier Fuel supplier Fuel oil purchase agreements Gas sale agreement Tolling Company Tolling Agreement BS contract Albania, Kosovo or

  • ther TSOs

OShEE CfD Greece, Italy,

  • r other

markets Export spot sales Eligible consumers CfD