Assessment RFP 06-17 (released July 2017) SRD Requested: - - - PowerPoint PPT Presentation

assessment rfp 06 17 released july 2017
SMART_READER_LITE
LIVE PREVIEW

Assessment RFP 06-17 (released July 2017) SRD Requested: - - - PowerPoint PPT Presentation

Oyster River / Glenmore Dike Assessment RFP 06-17 (released July 2017) SRD Requested: - Condition Assessment - Geotechnical Assessment (incl. Seismic) - Conceptual Upgrades & Cost Est. We proposed to provide the above, plus : -


slide-1
SLIDE 1

Oyster River / Glenmore Dike Assessment

slide-2
SLIDE 2

RFP – 06-17 (released July 2017)

SRD Requested:

  • Condition Assessment
  • Geotechnical Assessment (incl. Seismic)
  • Conceptual Upgrades & Cost Est.

We proposed to provide the above, plus:

  • Hydrologic Assessment (study of River Flow Rates)
  • Hydraulic Modelling & Assessment (study of Glenmore Dike performance

during large flow events)

slide-3
SLIDE 3

Glenmore Dike Assessment

 Condition Assessment - Findings

 Unauthorized Recreational Users (ATV / Dirtbikers) have caused minor damage via erosion of accessways  Debris Blocking Drainage Channels  Vegetation Overgrowth has caused

Reduced Access to Some Areas

slide-4
SLIDE 4

Glenmore Dike Assessment

 Geotechnical Assessment via Drilling

slide-5
SLIDE 5

Glenmore Dike Assessment

 Seismic Stability Assessment

slide-6
SLIDE 6

Glenmore Dike Assessment

 Hydrologic Assessment via Statistical

Analysis of River Flow Data

 Hydrotechnical Assessment via 2-D

River Modelling (HEC-RAS software)

slide-7
SLIDE 7

Glenmore Dike Assessment

 Ex. Glenmore Dike Hydrology & Floodplain Mapping were Completed in early-1980’s

slide-8
SLIDE 8

Glenmore Dike Assessment

  • Ex. Glenmore Dike Hydrology & Mapping were Completed in early-1980’s (1981 to 1984)

WSC Flow Data for Oyster River @ Woodhus Creek

Pre-1980 Flow Data Post-1980 Flow Data

slide-9
SLIDE 9

Glenmore Dike Assessment

 Hydrology – Design Flow Rate Determination

 Statistical Analysis of ~40 years river flow data

 Q200 = 493 m3/s

 Climate Change Impact

 Precipitation Increase to 2090 = 15%

 Design Flow Rate = 567 m3/s (200-Year Return

Period Flow, plus Climate Change)

Estimated Future Precipitation Change Due to Climate Change for the Strathcona Regional District (Data from PCIC’s Plan2Adapt Online Tool)

slide-10
SLIDE 10

Glenmore Dike Assessment

 2-D Hydraulic Modelling using HEC-RAS software

(see videos)

slide-11
SLIDE 11
slide-12
SLIDE 12
slide-13
SLIDE 13

Glenmore Dike Assessment

 Hydraulic Modelling Findings

Matches Observations from December 2014 “Emergency Dike Repair” & Validates Need for Repair

slide-14
SLIDE 14

Glenmore Dike Assessment

Upgrade Options: (in order of priority)

 Priority 1: Maintenance & Repairs

 Vegetation Clearing & Replacement of ex. Culvert (incl. new Flap-Gate Chamber)  Est. Cost = $138k (plus $7,000 annual maintenance)

 Priority 2: Upgrade & Raise Dike at North End

 Upgrade the “emergency repair” section to proper dike standard (approx. 90 meters of dike length to

be re-built)

 Est. Cost = $303k

 Priority 3: Dike Re-build for Long-Term Seismic Stability

 In order to completely upgrade the dike to be seismically stable, approximately 510 meters (in addition

to the 90 meters from Priority 2) would be re-built.

 Est. Cost = $3.775M

slide-15
SLIDE 15

Glenmore Dike Assessment

Project Successes:

 Many dike assessments are done piecemeal. However- concurrent, multi-disciplinary assessments

(Condition, Geotech, Hydraulics) led to efficiency in upgrade recommendations based on the sum of all findings, for example:

 Culvert replacement, requiring local dike re-construction;  Area around culvert was identified as seismically unstable;  Extend extents of dike re-construction around culvert to improve seismic stability;  Hydraulic assessment determined dike crest could actually be lowered at this location, leading to savings

compared to re-build to existing height.

 Budget

 Budget cap was determined by grant funding. SRD scope in their RFP included condition & geotechnical

assessment.

 We felt there was sufficient funding to complete additional hydraulic / hydrologic assessment, and all works

were completed on-time and within budget.

slide-16
SLIDE 16

Thank You

McElhanney Consulting Services Ltd. 1307 Shoppers Row Campbell River, BC Contact: Eric Heel, P.Eng. 250-287-7799 Email: eheel@mcelhanney.com