ARAN BACKFILL SYSTEM SOLUTIONS
Sept 2012
ARAN BACKFILL SYSTEM SOLUTIONS Sept 2012 ARAN Brisbane - - PowerPoint PPT Presentation
ARAN BACKFILL SYSTEM SOLUTIONS Sept 2012 ARAN Brisbane Australia head office Established in Malaysia & Canada Developer of construction & mining projects broad range of experience Partner & Alliance
Sept 2012
range of experience
ransported as Shipping Containers
Aran SiloFeedIII
feeder life.
components.
without need to dismantle bearings, pulleys, or sensors.
GOLD MINE, Western Australia. Simple Paste Backfill Plant. May 2008. ARAN supplied mixer, tailings conveyor and feeder, hopper and grizzly.
GOLD MINE, Western Australia. Simple Paste Backfill Plant. May 2008. ARAN supplied mixer, tailings conveyor and feeder, hopper and grizzly.
The purpose of the weir is to retard the flow of the mixture which allows the paddles more time to blend the materials.
rotation, variable blade direction and variable speed drive)
drawn from the tailings dam
– tails filtration data – USC specific for fill demands – Detailed Rheology study
Thickeners
Modular E-Disc Filter
Intelligent Control & Logic, Sequenced Operations and Interlocks
(project data graph, available on request)
For Large Projects with Long Schedules and Multiple Alliance Members
2011 Shane Dunstan
This presentation will summarise the process by which Aran will coordinate the delivery of packages for the Development and Commissioning of Backfill Systems for Total Backfill System Supply. The Aran alliance team method of project delivery has been developed after considerable industry engagement and project planning analysis. The delivery of a “total backfill system” in “project packages” provides both the mine and the Aran led group of suppliers the strength of confidence and flexibility to deliver a comprehensive backfill system in good time and budget.
The Aran Alliance Team represents the network of companies Aran will lead for the supply and commissioning of all engineering, equipment and technical services for the Backfill System.
The “Total Backfill System” is comprised of up to Five (5) discrete “Project Packages” These Project Packages can be delivered individually and to some degree independently both commercially and technically. They are independent in financial and time schedules. All five Project Packages can be grouped as a single Total Backfill System supply, yet each package will remain as clearly independent commercial milestones.
Backfill Design Site Specific Process Engineering Plant and Equipment Manufacture and Supply Site Specific Plant Variation Engineering and Equipment Supply Site Services
Project Package
Commercial Contract
Schedule Technical
Three prime components to each Project Package:
echnical Scope of Deliverables
Milestones and Payments
commitments between parties.
Backfill Design
Commercial Schedule Technical
Site Specific Engineering
Commercial Schedule Technical
Plant & Equipment
Commercial Schedule Technical
Variations Engineering & Equipment
Commercial Schedule Technical
Site Services
Commercial Schedule Technical
Each package consists of the three prime components
Site Services Package Variations Package Plant & Equipment Package Backfill Design Package Site Engineering Package
The Five Project Packages can be grouped together to form a total backfill although they are five separate contractual elements. The technical, scheduling and contracts for each project are independent although they are interactive.
Site Visit & Material Testing Gather & Review Data Testing: Filtration Strength, Rheology Backfill Design Stability Assessment Paste System Design Fill Distribution Design Barricade Design Delivery of Report Backfill Design Report Presentation and Training
Backfill Design
Site Integration Engineering Engineering Review
integration requirements Site visit Development of site specific packages Site Visit Civil Design
Visit Site for Technical review and systems matching Provide Basic Civil Design of Plant Footing
Site Works Planning
Preparation and Presentation of Site Work Documents Civil Works Plans Plant Assembly and Site Services Installation Scope and Schedule for tendering Commissioning Assistance
Site Specific Process Engineering
Standard Paste Plant Manufacture Procurement Manufacturing Standard Components Plant Factory Assembly Receive all fabrications and components Assembly according to Aran system Factory Testing Testing of Plant systems in factory Factory acceptance Dispatch for shipping to site
Plant and Equipment Manufacture and Supply
Analysis of Site Standard and/or specific requirements
Gap analysis of Standard Aran systems compared to site requested systems Engineering review and proposal of variation to scope
Detailed Engineering of Variations Detailed design of approved variations to Standard Aran plant scope within budget and schedule Delivery of Variations Manufacture and develop approved variations to the plant for delivery
Site Specific Plant Variation Engineering and Equipment Supply
Site Supervision Installation
Project management and system installation planning Aran alliance team supervision and assistance for system installation and services connections
System Commissioning
Aran alliance team supervision and technical assistance with wet commissioning and
stabilisation of the Backfill System Operator and Maintenance Training
Ongoing Services
Backfill Operations Manual Provision of Spare Parts Backfill Optimisation review and recommendations Ongoing training and assistance as required
Site Services
Site Services Variations of Scope Plant & Equipment Site Engineering Backfill Design
Backfill Solution
Aran Equipment Suppliers Backfill Design Consultant Mine Client
Contribution from all involved in the project as partners toward mutual success.
Aran Alliance Project Package Delivery Mine Client Engagement Successful Backfill System
Month 1
– Project Start – Commencement of material testing – Consultation with all project partners – First Engineering visit and site specific project engineering
Month 3
– Site engineering closure – Procurement and Manufacturing commences – Backfill Engineering Draft submitted
Month 4-7
– Review Engineering – Backfill Design study submitted
Month 4-10
– Manufacturing completed – Detailed site construction planning meeting
Month 11
– Shipping of plant commences
Month 12-13
– Plant arrives on site – Site Construction – Commissioning and T raining – Operations
site logistics
tails or sand will be 4 months shorter delivery