APARTMENT BLOCKS DEALING WITH DEFECTS Peter Kearney Partner - - - PowerPoint PPT Presentation

apartment blocks dealing with defects
SMART_READER_LITE
LIVE PREVIEW

APARTMENT BLOCKS DEALING WITH DEFECTS Peter Kearney Partner - - - PowerPoint PPT Presentation

APARTMENT BLOCKS DEALING WITH DEFECTS Peter Kearney Partner - Reddy Charlton Solicitors Deirdre N Fhloinn Consultant Reddy Charlton Solicitors PhD Candidate Trinity College Dublin Apartment Owners Network - 3 May 2017 Where to


slide-1
SLIDE 1

APARTMENT BLOCKS – DEALING WITH DEFECTS

Peter Kearney Partner - Reddy Charlton Solicitors Deirdre Ní Fhloinn Consultant – Reddy Charlton Solicitors PhD Candidate – Trinity College Dublin Apartment Owners Network - 3 May 2017

slide-2
SLIDE 2

Where to start? Physical investigation Legal investigation Insurance

slide-3
SLIDE 3

Investigation Fire safety consultant Building surveyor Engineer

  • Expert assessment of the nature and

extent of the problem

  • Remedial works schedule
slide-4
SLIDE 4

Management companies - MUDs Act

  • Organise liaison group with managing agent
  • Seek information on survey outcome,

remedial works and estimated costs

  • Voting
  • Recovery of costs against developer
  • Service charge should not be used to deal

with defects without consent of members

slide-5
SLIDE 5

Reach out to other owners

slide-6
SLIDE 6

Dealing with repair costs

  • No general State loan or redress

scheme

  • Consider accruing over period of years

rather than in one payment

  • SCSI have called for loan scheme and

State fund for defects

slide-7
SLIDE 7

LEGAL

  • 1. Identify builder, developer, professional

team and all stakeholders

  • 2. Engage legal team to advise on options

depending on nature of claim and factual matrix

  • 3. Notify relevant parties of defects and

potential claim

  • 4. Implement strategy
slide-8
SLIDE 8

Identification

  • Who holds the title documents for

the development?

  • Have the common areas been

transferred?

  • What firm acted in the sale of units?
  • Is this information stored and readily

available?

slide-9
SLIDE 9

Legal Engagement

  • Need to know range of legal options

and appropriate forum for disputes at

  • utset.
  • Need to verify negligence, breach of

contract, verify design etc has occurred and is actionable

  • Documents of title must be reviewed to

determine optimum course of action

slide-10
SLIDE 10

Notification

  • Crucial that correct parties are

notified properly, sufficiently and at the right time

  • “Letter before Action” – an important

document to frame the case

slide-11
SLIDE 11

Strategy

  • Preference is to implement rather than

devise strategy

  • Broader non-legal issues to be

considered

  • What third parties will be involved -

local authorities, media, politicians?

  • Role of Managing Agent
  • How are members informed?
slide-12
SLIDE 12
  • Only first purchaser can sue under Building

Contract: for apartments, building contract for block will cover common areas

  • Developer may have owned land but not built - no

liability for unit

  • If multiple parties at fault, home owners may sue

all: designer / certifier may be 'last man standing'

  • No regulator to deal with complaints: local

authorities not obliged to inspect / enforce

Legal Investigation

slide-13
SLIDE 13
  • Liability outside contract?
  • Designers: negligent design
  • Professionals giving Certificates and

Opinions on Compliance: can be liable for negligent misstatement

  • Builders: in principle can be liable outside

contract for building defects, but law is unclear, and builder may be insolvent or not a mark

Legal Investigation (Contd)

slide-14
SLIDE 14

Statute of Limitations 1957 Builder: 6/12 years from date of breach of contract depending on whether contract signed under seal Designers and certifiers: 6 years from date of 'damage' following negligence - very unclear: Supreme Court decision due on when this period starts

slide-15
SLIDE 15

Statute of Limitations 1957(Contd) What stops the clock?

  • Issuing court proceedings
  • Referral to arbitration

Mediation / conciliation does not stop time running

slide-16
SLIDE 16

Dispute resolution

  • Builder: Law Society Standard Building

Agreement – arbitration

  • Designers and certifiers: litigation
  • If architect appointed by homeowner,

mediation before litigation (new RIAI Standard terms)

slide-17
SLIDE 17

Insurance

  • Check coverage and exclusions
  • Comply with notification requirements:

eg HomeBond consent may be required to incur professional fees for investigation

  • Can be lengthy process : keep in

contact and keep pressure on insurers

slide-18
SLIDE 18

Peter Kearney Partner Reddy Charlton Solicitors pkearney@reddycharlton.ie www.reddycharlton.ie @ReddyCharlton Deirdre Ní Fhloinn Consultant Reddy Charlton Solicitors PhD Candidate – TCD nifhlode@tcd.ie

@DeirdreNiF

slide-19
SLIDE 19

TITLE

CLICK TO EDIT MASTER SUBTITLE

R E D DYC H A R LTO N. I E R E D DYC H A R LTO N. I E

slide-20
SLIDE 20

Disclaimer This information is for guidance purposes only. It does not constitute legal or professional advice. No liability is accepted by Reddy Charlton for any action taken in reliance on this information.