APA production site @ Yales Wright Laboratory Dr. Domenico Franco US APA Construction and Proposal Workshop June 10, 2019 1 J.W. Gibbs Professional Shop Wright Laboratory Staffed by professional machinists Precision machining The


slide-1
SLIDE 1

APA production site @ Yale’s Wright Laboratory

  • Dr. Domenico Franco

US APA Construction and Proposal Workshop – June 10, 2019

1

slide-2
SLIDE 2
  • The laboratory’s unique combination of on-site state-of-

the-art research facilities, and technical infrastructure

  • Largest experimental facility of Yale Physics~86,000 sf of

lab and office space> 150 personnel (16 faculty, > 40 graduate students)

  • Experimental research in fundamental physics nuclear,

particle astrophysics/cosmology quantum physics

  • Core campus facilities machine shops, cleanrooms, high

bay

US APA Construction and Proposal Workshop - June. 10, 2019 - Dr. Domenico Franco 2

Wright Laboratory

J.W. Gibbs Professional Shop Staffed by professional machinists Precision machining CNC capability Advanced Prototyping Center Coherent Meta2C laser cutter Flow NanoJet Abrasive water jet cutter Formlabs Form2 SLA and Dremel 3D20 FDM 3D printers Research Support Shop For use by students and researchers with professional supervision Clean Rooms Permanent class 1,000 clean rooms Customizable soft wall clean rooms for high bay Fume hoods and liquid handling

slide-3
SLIDE 3

First floor

3

Prototyping Room

Workshop Clean Rooms Cryo-Lab Workshop The Vault Lab-111

US APA Construction and Proposal Workshop - June. 10, 2019 - Dr. Domenico Franco

Yale Physics

Serving Physics, Science Hill, and campus community

slide-4
SLIDE 4

High-bay area “The Vault”

4

50 m 12 m Parking

  • Very long area of 600 m2
  • Ground level: direct connection with

parking area and main street

  • Wide access main gate
  • 10 Ton crane already present

US APA Construction and Proposal Workshop - June. 10, 2019 - Dr. Domenico Franco

Metal workshop Wood

slide-5
SLIDE 5

High-bay area “The Vault”

5

50 m 12 m Parking

  • Very long area of 600 m2
  • Ground level: direct connection with

parking area and main street

  • Wide access main gate
  • 10 Ton crane already present

US APA Construction and Proposal Workshop - June. 10, 2019 - Dr. Domenico Franco

Metal workshop Wood

slide-6
SLIDE 6

6 US APA Construction and Proposal Workshop - June. 10, 2019 - Dr. Domenico Franco

Unique characteristic: full access!

SBND APAs

slide-7
SLIDE 7

The Vault as is today

7 US APA Construction and Proposal Workshop - June. 10, 2019 - Dr. Domenico Franco

In the last 2 years Wright Lab hosted in the Vault and Lab-111 important scientific projects.

  • Prospect detector

construction

  • SBND APAs winding
  • SBND Field Cage’s

modules assembling All these projects required clean tents

slide-8
SLIDE 8

Milestones

  • Phase 0: deep cleaning and finishing of the Vault area (Fall 2019)
  • Phase 1: Clean tent in the back side of the Vault for Winders assembling

(Early 2020)

  • Phase 2: Clean tent in Lab-111 for processing carts assembling (Fall 2020)
  • Phase 3: Start winding (Beginning of 2021)

US APA Construction and Proposal Workshop - June. 10, 2019 -

  • Dr. Domenico Franco

8

slide-9
SLIDE 9

9 US APA Construction and Proposal Workshop - June. 10, 2019 - Dr. Domenico Franco

APA factory: Phase 1

Lab -111

Clean Area Metal Shop Wood Main Gate

slide-10
SLIDE 10

10 US APA Construction and Proposal Workshop - June. 10, 2019 - Dr. Domenico Franco

APA factory: Phase 2

Metal Shop Wood shop removed and extension of CT Lab-111 with CT hosting the cart assembling and possible cold test facility in Phase 3.

slide-11
SLIDE 11

Phase 3:full extension

US APA Construction and Proposal Workshop - June. 10, 2019 - Dr. Domenico Franco

11

slide-12
SLIDE 12

US APA Construction and Proposal Workshop - June. 10, 2019 - Dr. Domenico Franco

12

Phase 3:full extension

slide-13
SLIDE 13

Ready to winding

US APA Construction and Proposal Workshop - June. 10, 2019 - Dr. Domenico Franco

13

slide-14
SLIDE 14

Alternative

US APA Construction and Proposal Workshop - June. 10, 2019 - Dr. Domenico Franco

14

slide-15
SLIDE 15

Yale APA team (so far – needs to grow!)

  • PIs: Bonnie Fleming, Karsten Heeger
  • Domenico Franco, APA Production Manager: point of contact for

DUNE

  • Tom Langford, APA Assembly Facility Manager: plans and coordinates

activities at Wright Lab

  • At Wright Lab:
  • Jeff Ashenfelter, Associate Director of Operations: local EHS liason, conducts

all WL training, can assist with local project controls.

  • James Wilhelmi: Engineer, calculations for clean area, so far.
slide-16
SLIDE 16

Costs

  • Finishing the Vault floor 12k$
  • Clean tent for Lab-111 55k$
  • Clean tent for the Vault 228k$

US APA Construction and Proposal Workshop - June. 10, 2019 -

  • Dr. Domenico Franco

16

Estimation did on volume base rather than foot print This likely over estimates the actual costs A formal request of quote has been submitted to Modular Cleanrooms, INC. which supplier of PROSPECT cleanroom

Work on evaluating the cost is till in progress!

slide-17
SLIDE 17

Yale West Campus

1 7

  • Wide Area located 15 mins from WL
  • Six core facility for innovative research in

Health, Environment, Energy, Biology

  • Large space for both v and receiving with

monitored humidity and temperature

US APA Construction and Proposal Workshop - June. 10, 2019

  • Dr. Domenico Franco
slide-18
SLIDE 18

Summary

  • WL has developed a plan as a regional APA production facility

for DUNE

  • Understanding space needs
  • Project and schedule specific to WL is ready
  • Team is growing up and hiring process for FTEs needed at WL
  • ver time is ongoing
  • Reorganization of the space will start in the Summer
  • Coordinating work with participating institutions
  • Possibility of storage space in West Campus

US APA Construction and Proposal Workshop - June. 10, 2019 - Dr. Domenico Franco