plans for production sites
play

Plans for Production Sites UK-PI Meeting University of Manchester - PowerPoint PPT Presentation

Plans for Production Sites UK-PI Meeting University of Manchester 6th March 2019 APA Production Plan Definition of institutional responsibilities for APA production components to be concluded by March UK starts APA production July


  1. Plans for Production Sites UK-PI Meeting University of Manchester 6th March 2019

  2. APA Production Plan  Definition of institutional responsibilities for APA production components • to be concluded by March  UK starts APA production July 2020, site preparation underway  In US • Start preparing sites for APA wiring centers in 2019 • Tailor cost estimate in P6 to the individual APA wiring centers before CD2/3 review (definition of personnel and associated costs) • Winders production in 2020 (2 @ Yale, 2 @ Chicago with help from PSL) • Start APA production Jan 2021  Hold individual reviews of APA wiring centers ~June 2019 to assess space layout, crane equipment, safety procedures, staffing plan (Preliminary Reviews)  Hold individual Production Readiness Reviews

  3. APA Production  Production of APAs for Detector #1  US-APA production (76 APAs): Jan 4, 2021 – Dec 7, 2023  UK-APA production (76 APAs): Jul 6, 2020 – Nov 6, 2023 APA Production/year Production 2020 2021 2022 2023 Site Daresbury 6 24 26 20 Yale 10 13 7 Chicago 10 13 7 PSL 3 7 6 TOT 6 47 59 40  Need to cold test 10% of APA production  Need to investigate options for local storage if early shipping to SD is not possible

  4. Daresbury Laboratory DUNE Factory • Inner hall site of the SRS accelerator identified as factory location • Purpose built factory room • Factory to have 4 winding machines, 10 process carts • Separate shipping area in renovated plant room • Dedicated swing arm pillar cranes for each winding machine 6/3/2019 UK-PI mtg - Alan Grant 4

  5. Daresbury Laboratory DUNE Factory Layout. 6/3/2019 UK-PI mtg - Alan Grant 5

  6. Movement of Materials & APA’s Fixed platform and swing High level area for jib crane for moving Low level area APA shipping preparation. frames between areas. lifting zone. Access to high level from road . Raw material taken in through this entrance (2D plan). 6/3/2019 UK-PI mtg - Alan Grant 6

  7. Pre Processing Area Pre Processing Area – Comb bases & mesh panel fitting APA frames loaded into process carts here. Entrance into preparation area. 6/3/2019 UK-PI mtg - Alan Grant 7

  8. Pre Processing Area - cont Access to Winding area Small part / jig storage. Small part assembly / general work area. Prep area 210m^2 comb base and mesh panel fitting. Emergency Exit 6/3/2019 UK-PI mtg - Alan Grant 8

  9. Factory Area Layout Winder - 2 Winder - 1 Winder - 3 Emergency Exit Plenty of wall space Winder - 4 for off line prep work Winder area 638m^2 Door position shown incorrectly Parking for completed APA’s waiting 6/3/2019 UK-PI mtg - Alan Grant 9 for transfer to shipping area.

  10. Packing & Shipping Area Lifting zone to platform. Fixed platform Post processing / packing & shipping area. 237m^2 Swing jib crane for loading / unloading Packing crate (size trucks from the Overhead crane to cover this area. of existing PSL road. crate). 6/3/2019 UK-PI mtg - Alan Grant 10

  11. Plan View of Factory Roof Beam supports Platform to shipping area 11 6/3/2019 UK-PI mtg - Alan Grant

  12. Production Factory Area Identified – 2016 Crane height approx 7.2m Available Area approx 22m x 37m central hall. Serviced by 15ton crane. 12 12 6/3/2019 UK-PI mtg - Alan Grant

  13. Inner Hall 2016 13 6/3/2019 UK-PI mtg - Alan Grant

  14. Preparation Work Some funding released for DUNE Pre Construction • Concrete e-Beam Bunker removal complete • Removal radial and ancillary cranes complete • Factory room materials ordered • Cranes – 5 off ordered • Shipping room refurbishment well advanced • Quotations expected in coming weeks for  Factory room assy of building  Factory room services  Platform to shipping room  Floor renovation – factory and shipping area 6/3/2019 UK-PI mtg - Alan Grant 14

  15. Inner Hall – Sept 2018 15 6/3/2019 UK-PI mtg - Alan Grant

  16. Shipping area being prepared Exit door to road Entrance door from factory to shipping area 6/3/2019 UK-PI mtg - Alan Grant 16

  17. Access to Road for Transport Vehicle 6/3/2019 UK-PI mtg - Alan Grant 17

  18. Storage – Wall & Roof Panels Delivery March 6/3/2019 UK-PI mtg - Alan Grant 18

  19. APA production site @ Yale’s Wright Laboratory

  20. The Vault as it appears today

  21. The Vault as it appears today

  22. The APA Factory in the Vault

  23. Questions 6/3/2019 UK-PI mtg - Alan Grant 35

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend