anantha moorthy u
play

Anantha Moorthy U Rohini Pradeep, Susmita Sinha BACKGROUND OF THE - PowerPoint PPT Presentation

Operation Maintenance (O&M) of Faecal Sludge Treatment Plant (FSTP) Devanahalli, India: Learnings Anantha Moorthy U Rohini Pradeep, Susmita Sinha BACKGROUND OF THE STUDY Technical and Sustainable Institutional FSTP O&M -


  1. Operation Maintenance (O&M) of Faecal Sludge Treatment Plant (FSTP) Devanahalli, India: Learnings Anantha Moorthy U Rohini Pradeep, Susmita Sinha

  2. BACKGROUND OF THE STUDY Technical and Sustainable Institutional FSTP O&M - challenges 6 cu.m/day Approaches 1 2 3 4 5 6 CDD & BORDA Plant Improvising /BMGF & Operational O&M MUNICIPAL for 3 years 2

  3. DEVANAHALLI & FSTP OVERVIEW Town – Profile Population (as per 30,000 Census 2011) FS Containment 85% Pits & 15% others structures Desludging Interval 3 – 5 years Design Capacity 6,000 litres/day Total FS Treated 15,92,000 Litres (data (2015-2018) collected by CDD) Years in Operation 3 (since 2015)

  4. LOW O&M FSTP TECHNOLOGY DESIGN CONSIDERATIONS • Sludge and liquid flow by gravity • Minimal moving parts (only 3 manually operating valves) • Low energy requirement (Solar Roof) • Recovery - Compost + Treated water for Gardening • Minimal human resource – One Operator

  5. O&M - LABOUR REQUIREMENTS Labours for Composting (3) O&M Operator (1) Desludging Operators Additional Labours (1) (3)

  6. O&M - Technical Challenges O&M – Institutional Challenges CHALLENGES

  7. O&M - Technical Challenges O&M – Institutional challenges O&M – CHALLENGES (Solid Liquid Separation) Solid Waste – (2- 20 Kgs / Load) Scum – entering Liquid Stream due to Creates blocking of screens- Frequent poor settleability cleaning of screens

  8. O&M - Technical Challenges O&M – Institutional challenges O&M – CHALLENGES (Sludge handling) Shorter SRT – Due to sludge Sludge accumulation in PGF movement

  9. O&M - Technical Challenges O&M – Institutional challenges O&M – CHALLENGES (Sludge handling) Valve Blockage and Corrosion Blockage in Stabilization tank outlet (Replacement of Valves) during stoppage periods

  10. O&M - Technical Challenges O&M – Institutional challenges O&M – CHALLENGES (Sludge Drying) Sand loss after sludge Algae formation during Slower drying rate removal monsoon

  11. O&M – Institutional challenges O&M - Technical Challenges INSTITUTIONAL CHALLENGES • Reduced plant utilisation rate - lack of support from private operators • Truck stoppages – breakdown • Labour strikes & unavailability of additional labour for scheduled maintenance • Mobilizing funds from ULB for retrofitting infrastructures (Incidental causes)

  12. O&M – Institutional challenges O&M - Technical Challenges FSTP UTILISATION RATE (2015 – 2018) GOVT PVT 3 750+ loads Private Operators FSTP Utilisation rate (33%) 1 Govt Operators

  13. O&M – Institutional challenges O&M - Technical Challenges TMC Devanahalli passed 4 resolutions – to improve plant functions: 1 2 Outsourcing of O&M Regulating disposal at FSTP 3 4 Inclusion of Desludging fees with Monitoring standards for Construction of OSS Property tax

  14. O&M – Institutional challenges O&M - Technical Challenges OUTSOURCING O&M ULB (Government Body) State government approval RFP and Plant handover (2016) Processing Tender document and RFP Call for Bid In (2016) approval (1 year span) 2017 KAM-AVIDA Technical + Financial Bid JV Tender CDD SOCIETY Tender Awarded awarded Cube Bio Energy

  15. COST OF O&M Consumables and Miscellaneous 10% Truck Operation (Repair and Truck Operations Maintenance) Admin cost 20% 15% O&M Support Truck Operation (Fuel) 25% Plant Operation & Mainteance 30% Market For End Product

  16. O&M – Institutional challenges O&M - Technical Challenges SOLUTION TO INSTITUTIONAL CHALLENGES • Post Tender – Optimized Truck operations • Agreement between TMC to provide additional labor • Salary to operators & labor – From TMC but through contractor • Conduct awareness campaigns for different stakeholders on Reuse • Connect gaps in the FSM chain – conversion of insanitary toilets

  17. O&M - Technical Improvements O&M – Institutional challenges TECHNICAL IMPROVEMENTS 1. Replacement of gate valve with Plug valve 2. Increase buffer capacity for additional loads 3. Mangalore tiles to prevent sand loss and sludge handling. 4. Solar Roof for improve evaporation rate

  18. LESSONS LEARNED ON O&M • Integrated O&M plan with long term contract • Choice of technology in Devanahalli is suitable for stoppage and restart periods • Back up plan of O&M schedule – Preparedness is the key • Sustainable O&M model – Stakeholder engagement + Strong Institutional framework • Adaptability – Change the plan with learning

  19. THANK YOU Questions ??? Anantha Moorthy. U Project Engineer, CDD society anantha.m@cddindia.org

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend