Agency Models Transmission Arrangements for Distributed Generation - - PowerPoint PPT Presentation

agency models
SMART_READER_LITE
LIVE PREVIEW

Agency Models Transmission Arrangements for Distributed Generation - - PowerPoint PPT Presentation

Agency Models Transmission Arrangements for Distributed Generation London: 14 July 2006 Structure The Problem (National Grid perspective) Agency Model Options Three Strawmen for discussion The Problems Cost reflectivity of


slide-1
SLIDE 1

Agency Models

Transmission Arrangements for Distributed Generation

London: 14 July 2006

slide-2
SLIDE 2

Structure

The Problem (National Grid perspective) Agency Model Options Three Strawmen for discussion

slide-3
SLIDE 3

The Problems

Cost reflectivity of transmission charges falls as unlicensed

embedded generation increases

  • All generation has an effect on transmission flows
  • Not just about exporting GSPs

Governance framework does not recognise flow from

distribution to transmission without a BEGA

  • No access product

No operational control where transmission affected

  • DNO networks effectively becoming active

Investment planning and locational signals

  • Embedded Generation growth

Specific issues in Scotland

More than just a charging issue, only agency models can resolve

slide-4
SLIDE 4

What do we mean by “Agency”?

Single point of contact/ interface Aggregator of capacity and energy Controller of despatch Who? Options: “GBSO” to extend into DNO networks? 14 DNOs to become “active” – DNO Agency Use Supplier interface – Supplier Agency

X

slide-5
SLIDE 5

Key Considerations

Gross v Net

Should embedded generation net from demand?

  • Transmission Charges based on “spill” or installed capacity?

Appropriate threshold?

Nodes v Zones

Would a defined transmission access product be nodal

  • r zonal?

The degree of change

What are we assuming the agent will do?

slide-6
SLIDE 6

Agency Model Matrix

Gross of Gross of Net of Net of GSP GSP Group GSP GSP Group

Supplier Agency DNO Agency

“TODAY” (sort of)

Very Difficult, SVA at GSP Group level, Would need to Re-register 23m meters Nodal Model Superior Nodal Model Superior “Interconnector model” Possible, but involves a lot

  • f change

Strawman 3 Strawman 2 Strawman 1

slide-7
SLIDE 7

Why these Strawmen - objectives

“Gross” for cost reflective charging “Nodal” (where pragmatic) for operational control Supplier agent for least change, but DNO Agent

could work if it was fully active

We think DNO Agent is a lot of change

slide-8
SLIDE 8

Supplier v DNO Agent

  • Association of bids/ offers with nodes
  • How does DNO resolve constraints and

actively manage the system? – does it need to?

  • SO despatching plant on another system –

safety/ security/ MVar

  • SO would be issuing BOAs via Supplier

Agency

  • Major industry restructuring
  • 14 control rooms
  • DNO trading energy?
  • How BM interaction managed?
  • Methodology to pass transmission

charges to suppliers

  • Treatment of large embedded
  • Reform of exit product
  • If “net” model, max export to Grid not at

system peak

  • Definition of service – response/

reactive Cons

  • Uses existing settlement structure
  • Efficient charging signals
  • Could be implemented in short term
  • Simple conceptually
  • Physical alignment
  • Clear operational boundaries of

responsibility

  • DNO bids and offers on a nodal basis

Pros

Supplier Agency DNO Agency

slide-9
SLIDE 9

Gross Zonal Supplier Agency Model (GZSAM)

  • Introduction to Strawman 1

GSP GSP GSP GROUP EG D D EG Distribution Network Transmission Network

NHHd2 HHd1 HHg1 HHg2 NHHd1 HHg2

M1 M2 Today GZSAM ∑HHd - ∑HHg

Netted off + ∑NHHd

HH £/kW Zonal Dem Tariff NHH p/kWh Zonal Dem Tariff

∑HHd

+ ∑NHHd

HH £/kW Zonal Dem Tariff NHH p/kWh Zonal Dem Tariff

For a Supplier, In the BM, aggregated zonal embedded generation might be offered to the SO in a single “sub-BMU”

HHg1 + HHg2

£/kW Gen TNUoS Tariff

Generation BMU

Demand

Generation BMU +

Generation

£/kW Gen TNUoS Tariff £/kW Gen TNUoS Tariff

zTEC

slide-10
SLIDE 10

National Grid DC Gen DNO National Grid DC Gen DNO SVA LEEG BEGA CVA LEEG

TEC Operational interface TEC Sum of Export capability

National Grid DC Gen DNO National Grid DC Gen DNO SVA LEEG BEGA CVA LEEG

TEC TEC Suppliers (negative demand)

Gross Nodal DNO Agent Model (GNDAM)

  • Introduction to Strawman 2

TODAY GDAM

slide-11
SLIDE 11

Gross Nodal Supplier Agency Model (GNSAM)

  • Introduction to Strawman 3

GSP GSP GSP GROUP EG D D EG Distribution Network Transmission Network

NHHd2 HHd1 HHg1 HHg2 NHHd1 HHg2

M1 M2 Today GNSAM

Netted off

HH £/kW Zonal Dem Tariff NHH p/kWh Zonal Dem Tariff

∑HHd

+ ∑NHHd

HH £/kW Zonal Dem Tariff NHH p/kWh Zonal Dem Tariff

For a Supplier, Each embedded generator above a given threshold might be offered to the SO as a single BMU

HHg1

£/kW Gen TNUoS Tariff

Generation BMU

Demand

Generation BMU +

Generation

£/kW Gen TNUoS Tariff £/kW Gen TNUoS Tariff

TEC

HHg2

£/kW Gen TNUoS Tariff

+

TEC ∑HHd - ∑HHg+ ∑NHHd

slide-12
SLIDE 12

Summary

There are different approaches None of the agency models are simple We think “gross” and “nodal” are important

  • cf. “net” and “zonal” today

No preference which agent DNO conceptually simpler Supplier least change

Other Agency ideas?

slide-13
SLIDE 13

The Problem - National Grid Perspective

  • “Gross” Background

All generation has an effect on transmission flows

Power flow south EG within +ve generation TNUoS charging zones can reduce local demand, but may increase flows south Transmission constraint

GSPs do not have to be exporting to affect transmission

Similarly, EG within negative generation TNUoS charging zones may reduce flows south

slide-14
SLIDE 14

Impact is the same as transmission connected 10MW EG 10MW D D G G

Impact of Embedded Generation

  • “Gross” Background

Transmission System Exporting Zone Transmission System Importing Zone Physical constraint 100MW Power Flow = 100MW EG 10MW G 10MW EG 10MW EG 10MW G 10MW Power Flow = 100+X MW