Adani Power Limited Power Business Goal - 20,000 MW ADANI POWER AT - - PowerPoint PPT Presentation

adani power limited
SMART_READER_LITE
LIVE PREVIEW

Adani Power Limited Power Business Goal - 20,000 MW ADANI POWER AT - - PowerPoint PPT Presentation

Adani Power Limited Power Business Goal - 20,000 MW ADANI POWER AT A GLANCE Power Business Goal - 20,000 MW BY 2020 MUNDRA 330MW X 4 + 660MW X 5 TIRODA 660MW X 5 (UNDER COMMISSIONING) KAWAI 660MW X 2 (UNDER ERECTION)


slide-1
SLIDE 1

Adani Power Limited Power Business Goal - 20,000 MW

slide-2
SLIDE 2

ADANI POWER AT A GLANCE

  • Power Business Goal - 20,000 MW BY 2020
  • MUNDRA– 330MW X 4 + 660MW X 5
  • TIRODA– 660MW X 5 (UNDER COMMISSIONING)
  • KAWAI– 660MW X 2 (UNDER ERECTION)
  • BITTA– 40MW BIGGEST SOLAR IN INDIA
slide-3
SLIDE 3

ACHIEVEMENTS

  • INDIA’S FIRST 66O MW SUPER

CRITICAL UNIT SYNCHRONISED BY ADANI POWER LTD, MUNDRA IN OCT 2010 IN RECORD TIME OF 36 MONTHS.

  • COMMISSIONED 4Nos. 660MW UNITS

IN A YEAR.

  • ADANI IS THE FIRST COMPANY IN

INDIA TO EARN CARBON CREDIT.

slide-4
SLIDE 4

PRESENTED BY

B.K.PANDEY APML, TIRODA

WELCOME

TO

slide-5
SLIDE 5

START-UP SEQUENCE

  • BOP SYSTEM READYNESS
  • BOILER FLUSHING: COLD/HOT
  • BOILER LINE UP AND LIGHT UP.
  • TURBINE LINE UP.
  • TURBINE ROLLING.
  • SYNCHRONISATION
  • PHASE CHANGE OVER
  • FULL LOAD
slide-6
SLIDE 6

START UP MODES

  • COLD START UP:HP & IP SHAFT METAL

TEMP <204°C

  • WARM START UP: HP & IP METAL TEMP IN

BETWEEN 204 TO 400°C

  • HOT START UP :HP & IP METAL TEMP

>400°C

slide-7
SLIDE 7

HPT IPT LPT A LPT B

CPP

GSC

Condensor (HP) Condensor (LP) HPH - 1 HPH - 2 HPH -3 EXT From CRH LPH -5 LPH -6

LPH -7A LPH -7B LPH -8A LPH -8B

3

Deaerator Boiler

CEP

3x50%

FCS

5 5 6 6

Economiser

1482 TPH 1994 TPH (MD BFBP 1x35%)

7 8 7 8 8 7 7 8

11+1 8 2x7 2x7

RH 1

TDBFP 2X50%

slide-8
SLIDE 8

PRE STARTUP READYNESS

  • HT/LT POWER SUPPLY READINESS
  • WATER SYSTEM: FIRE WATER,SERVICE WATER,DMP,CW &

ACW.

  • CCCW SYSTEM
  • COMPRESSOR SYSTEM
  • AUXILIARY STEAM. (S/B UNIT OR AUX BOILER).
  • START CEP AND MDBFP.
  • CHECK THE BCP SYSTEM IS READY.
slide-9
SLIDE 9

WHY BCP ?

  • TO ASSIST CIRCULATION IN BOILER WATER WALL
  • TO INCREASE THE CIRCULATION VELOCITY
  • TO AVOID DNB (Departure from Nucleate Boiling) IN LOW LOAD.
  • TO REDUCE THE OVER HEATING AND UNDUE STRESSES ON

WATER WALL TUBES.

  • TO AVOID DRY OUT OF WATER WALL TUBES WHEN LOAD IS

REDUCED.

slide-10
SLIDE 10

BCP FILLING ,PURGING & FLUSHING

  • PURPOSE-
  • TO FILL THE MOTOR CAVITY.
  • RECOMMENDED MOTOR FILLING WATER QUALITY
  • CONDUCTIVITY <1 µs/cm
  • BOILER FEED WATER
  • TEMP.<= 45 OC
  • CL- <= 50 PPM
  • pH >= 6.5
  • SUSPENDED SOLIDS <= 5 PPM
  • FILLING,PURGING & FLUSHING WATER REQUIREMENT
  • MOTOR INITIAL FILLING FLOW RATE : MAX. 5 L/MIN
slide-11
SLIDE 11

PRE BOILER FLUSHING

  • START CEP.
  • FILL & DRAIN FROM DEAERATOR UNTIL

REQUIRED WATER QUALITY IS ACHIEVED. ( Fe<500 Ppb.)

  • START MDBFP.
  • START THE BOILER COLD/HOT FLUSHING

TO REDUCE THE Fe & SiO2 CONTENT IN FEED WATER.

slide-12
SLIDE 12

Sampling Fe+

Above 500ppb Below 500ppb

MIXER

Boiler flushing

HOTWELL CW LINE

BCP

START-UP LINE

ECO WW SP SP

slide-13
SLIDE 13

BOILER COLD FLUSHING COLD FLUSHING

  • WATER WALL TEMP REQUIRED 105-120 DEG.C

(TEMP MAINTAINED BY DEAERATOR PEGGING STEAM)

  • COLD OPEN FLUSHING QUALIFIES Fe < 500PPB

SiO2 < 100PPB

  • THEN CPU WILL BE TAKEN IN SERVICE TO REDUCE WATER

LOSS AND IMPROVE QUALITY.

  • COLD CYCLIC FLUSHING QUALIFIES Fe < 100PPB

SIO2 < 50PPB (ALL ANALYSIS FROM SEPARATOR DRAIN)

slide-14
SLIDE 14

BOILER HOT FLUSHING

HOT FLUSHING

  • WATER WALL TEMP REQUIRED 150-190 DEG.C (TAKE

OIL GUNS OF BC ELEVATION)

  • HOT OPEN FLUSHING START UP CRITERIA FE

> 100PPB SIO2 > 50PPB

  • IF HOT CYCLIC FLUSHING CRITERIA IF FE

< 100PPB SIO2 < 50PPB

  • HOT CYCLIC FLUSHING QUALIFIES IF FE

< 50PPB SIO2 < 30PPB

  • AFTER COLD FLUSHING START BCP WITH MINIMUM 30%

FEED FLOW & THROTTLE FRS VALVE.

slide-15
SLIDE 15

BOILER LINE UP AND LIGHT UP

  • FUEL OIL SYSTEM: LDO/HFO PUMPS
  • ESP HEATERS & RAPPERS
  • AIR FLUE GAS SYSTEM: APH,IDF, FDF &

SCANNER FAN.

  • MAINTAIN AIR FLOW : 30% - 40%.
  • FURNACE PURGE: 300 Sec.
  • LIGHT UP BOILER WITH OIL GUNS AT BC (LDO)

ELEVETION.

  • CONTINUE HOT FLUSHING UNTIL REQD.WATER

QUALITY IS ACHIEVED

  • THEN TAKE CD ELEVETION GUNS. IF REQUIRED

TAKE 2 NO. GUNS IN AB ELEVETION.

slide-16
SLIDE 16

BOILER LINE UP AND LIGHT UP

  • CONTINUOUS APH SOOT BLOWING TO BE DONE AT THE

TIME OF OIL FIRING.

  • PR RISING RATE- 0.05 MPA/MIN. BETWEEN 0-1 MPA
  • PR RISING RATE 0.1 MPA/MIN. BETWEEN 1 – 2 MPA
  • PR RISING RATE 0.2 MPA/MIN. ABOVE 2 MPA
  • FURNACE EXIT GAS TEMP MUST BE BELOW 538°C FOR

REHEATER PROTECTION (UNTIL HP-LPBP IS CHARGED).

  • CLOSE SH DRAINS AND VENTS AFTER ACHIEVING DEGREE

OF SH 50 °C ( CLOSE IT AFTER CHARGING HP-LP BYPASS).

slide-17
SLIDE 17

LDO/HFO GUN

Fuel Light Oil Fuel Pressure 0.8MPa-2.0MPa Fuel Flow 500kg/h -3000kg/h Atomizing Air Pressure 0.6MPa-1.2MPa Atomizing Air Flow 100-600kg/h Ignition Method HESI (20 joules/spark) Fuel Heavy Oil Fuel Pressure 0.8MPa- 2.0MPa Fuel Flow 1000-4000 kg/h Atomizing Steam Pressure 0.8MPa-1.2MPa Atomizing Steam Flow 100-400kg/h Ignition Method HESI (20 joules/spark)

slide-18
SLIDE 18

TURBINE LINE UP

  • ENSURE:
  • LUBE OIL SYSTEM: IN SERVICE (0.8 MPA)
  • JACKING OIL SYSTEM:IN SERVICE ( 14 MPA)
  • TURBINE BARRING GEAR: 3-4 RPM
  • SEAL OIL SYSTEM: AIR & H2 SIDE. CHARGED
  • STATOR AND H2 COOLING WATER SYSTEM:CHARGED TEMP CONTROL

IN AUTO)

  • H2 FILLED IN GENERATOR AND MAINTAIN PR 0.35 MPA.
  • EH OIL SYSTEM: IN SERVICE (14 MPA)
slide-19
SLIDE 19

TURBINE LINE UP

  • ENSURE TDBFP IN BARRING.
  • GLAND STEAM CHARGING: ENSURE STEAM TEMP. IS 56°C
  • 111 °C MORE THAN ROTOR TEMP & DEGREE OF SH >

50°C.

  • CHARGE THE GLAND SEAL SYSTEM OF TDBFP.
  • START THE VACUUM PULLING WITH VACUUM PUMP.

MAINTAIN VACUUM -0.9 KG/CM2.

  • CHARGE THE HP-LP BYPASS SYSTEM .MAINTAIN THE MS

STEAM PRESSURE AND FIRING RATE FOR ACHIEVING TURBINE ROLLING PARAMETERS.

slide-20
SLIDE 20

COLD START UP CURVE

slide-21
SLIDE 21

HOT ROLLING

MS TEMP RH TEMP SPEED MS FLOW LOAD MS PRESS

slide-22
SLIDE 22

PRE HEATING OF HP CASING.

  • PREHEATING OF HPT REQUIRED WHEN INNER METAL TEMP <150°C.
  • CRH PR 0.5-0.7 MPA/220-380°C.
  • OPEN PRE HEATING VALVE (REVERSE FLOW VALVE) GRADUALLY.
  • OPEN BDV VALVE FULLY.
  • OPEN CRH DRAIN BEFORE NRV AND HPT-IPT CASING DRAINS.
  • HEATING RATE SHOULD NOT BE MORE THAN 50°C PER HR.
  • HP CASING TOP-BOTTOM & INNER-OUTER WALL METAL TEMP

DIFFRENCE SHOULD BE WITHIN 50°C.

  • AFTER ATTAINING THE CASING TEMP > 150°C CLOSE THE RFV

VALVE AND OPEN HP CYLINDER VENTILATION VALVE TO CONDENSOR.

slide-23
SLIDE 23

TURBINE WARM UP OPERATION

TURBINE STARUP PROCEDURE

RFV

CRH NRV

HPT

HPBP

CRH LINE

Ventilator valve TO CONDENSER

IPT BDV

TO CONDENSER

MS

slide-24
SLIDE 24

TURBINE ROLLING

  • AS PER REQUIREMENT OF START UP CURVE, FIRING TO BE

INCREASED.

  • REQUIRED STEAM PARAMETERS BEFORE ROLLING

– MS PR: 8.73 MPA, TEMP: 330-380 °C – RH PR: 1.1 MPA , TEMP: 330°C

  • THE DEGREE OF SUPER HEAT > 56°C.
  • AFTER LATCHING THE TURBINE, START IP ROLLING WITH HP VENT

TO CONDENSER IN OPEN CONDITION TO KEEP THE HPT IN VACUUM.

  • MSV 1&2 AND RSV 1&2 ARE IN OPEN CONDITION.
  • GIVE THE SPEED SET POINT TO 600 RPM
  • CHECK THE TURBINE SUPERVISORY INSTRUMENT PARAMETER.
  • THE ECCENTRICITY SHOULD BE LESS THAN 0.076 MM.
slide-25
SLIDE 25

TURBINE ROLLING

  • SELECT TARGET SPEED 1500 RPM WITH RAMP RATE OF 100

RPM/MIN.

  • ENSURE ALL HP CV’S OPENS TO 12% TO WARM UP THE HP

CASING.

  • WHEN HP CASING TEMP >320°C.CLOSE THE HP CV’S.
  • SOAK THE TURBINE FOR 4 HRS ACCORDING TO THE START UP

CURVE.

  • CHARGE THE LP HEATER 5 & 6 BEFORE 3000 RPM
  • SELECT TARGET SPEED TO 3000 RPM WITH RAMP RATE OF 100

RPM/MIN.SOAK IT FOR 30 MIN AS PER S/U CURVE.

  • AS PER PROCEDURE SYNCHRONISE THE UNIT.
slide-26
SLIDE 26

LOADING

  • AFTER SYNCHRONISATION INITIAL LOAD WILL BE 30 MW.HOLD IT

FOR 30 MIN AND CHEK THE VIBRATION, BEARING TEMP, DIFF EXPANSION, CASING EXPANSION.

  • CHARGE EXTRACTION STEAM TO DEAERATOR.
  • TAKE MORE OIL GUNS IN EF/AB ELEVETION.
  • TAKE PA FANS & SEAL AIR FAN.
  • AFTER ACHIEVING FURNACE TEMP. MORE THEN 450°C. TAKE COAL

MILL-B AT. STEAM T/PR 380°C/8.7 MPA.

  • INCREASE FUEL FLOW MAINTAINING STEAM TEMP.& RAISE LOAD
  • AT 70 MW IP TO HP CHANGE OVER. CV’S WILL START OPENING,

CLOSE THE BDV AND VENTILATING VALVE.

  • INCREASE THE LOAD AT 3MW/MIN
  • CLOSE THE HP-LP BYPASS GRADULLY.
slide-27
SLIDE 27

350 400 450 500 550 600 650 MINUTES

LOAD (MW)

165 330 495 660

33MW 60MW 198MW 330MW

SYNCHRONISE &CHARGE D/A MILL-B CUT IN IP TO HP CHANGE OVER (70MW) MILL-C CUT IN AT 100MW HPH CHARGED(150 MW) 2ND TDBFP CUT IN(180MW) WET TO DRY CHANGE OVER MILL-A CUT IN(210MW) OIL GUN CUT OUT (260MW) MILL-D CIT IN (300MW) MILL-E CUT IN (430MW) MILL-F CUT IN (540MW)

660 MW

slide-28
SLIDE 28

CONDENSER LP HEATER 7A LP HEATER 8A CONDENSER LP HEATER 7B LP HEATER 8B

LPT A LPT B

HP HEATER 5 HP HEATER 6 LP HEATER 5 LP HEATER 6

2nd 2nd

4th 4th 5th 5th 5th 5th 6th 6th 6th 6th

FROM IPT EXHAUST

slide-29
SLIDE 29

TDBFP START UP

  • TAKE ONE TDBFP IN SERVICE( CHANGE OVER WITH MD BFP) WHILE

DRIVING STEAM IS AVAILABLE. SECOND TD BFP WILL BE TAKEN AT 180 MW.

  • WARM UP THE TURBINE.
  • SLOWLY OPEN THE AUX STEAM MOV TO TURBINE.
  • PARAMETERS FOR ROLLING TDBFP.

STEAM PRESSURE: 0.6~1.3MPA, STEAM TEMP: 50 DEG C MORE THAN CASING TEMP.

  • ROLL THE TDBFP AS PER PROCEDURE.
  • GIVE THE TARGET SPEED 500 RPM AND THAN TO 1000 HOLD FOR 40

MIN.CHECK THE TSI PARAMETER

  • WHEN SPEED REACHES 2840 RPM, GIVE REQUEST COMMAND FROM

FW MENU. THEN SELECT CCS CONTROL IN FROM MEH MENU.

slide-30
SLIDE 30

IP TDBFP-A TDBFP-B

  • Aux. Steam

Header To CRH HP From CRH

M M M M

Deaerator Booster pumps

21-Nov-17

M M M

E E To Condenser

  • Aux. Steam

Header

M M M M M M M

E E Deaerator

1.3 MPa 350 ºC 1.12 Mpa 378 ºC 4 MPa 315.3 ºC

Changeover Valve

TDBFP STEAM SOURCES

slide-31
SLIDE 31

LOADING

  • TAKE THE MILL-C IN SERVICE AT 100 MW. STEAM T/PR:400°C/8.7

MPA.

  • GRADUALLY WITH DRAW THE OIL SUPPORT AS PER THE FLAME

CONDITION.

  • INCREASE THE LOAD TO 150 MW AND TAKE THE HPH-3, HPH-2 &

HPH-1 IN SERVICE. MS T/PR 410°C/8.7 MPA.

  • AT 180 MW TAKE SECOND TDBFP IN SERVICE.
slide-32
SLIDE 32

HP HEATER 3

DEAERATOR

HP HEATER 2 HP HEATER 1

CRH LINE TDBFP A TDBFP B MS LINE

9th stage 5th stage

HP HEATER 1 HP HEATER 2 HP HEATER 3

HRH LINE

DEAERATOR

IP EXHAUST

slide-33
SLIDE 33

PHASE CHANGE FROM WET TO DRY MODE

  • DURING LOAD RAISING >25% BMCR, THE BCP FLOW AND FEED

WATER FLOW TO BE MONITORED CLOSELY.

  • THE BCP FLOW NEED TO BE ADJUSTED W.R.T SEPERATOR TANK

LEVEL AND THE SAME FLOW TO BE ADJUSTED IN FEED WATER FLOW TO MAINTAIN TOTAL FEED WATER FLOW TO ECONOMISER CONSTANT.

  • WHEN BOILER STEAMING RATE RISES TO >30% BMCR, W.R.T FUEL

FIRING, THE SEPERATOR LEVEL REDUCES .

  • ONCE THE CONDITION FULFILLS THE BCP STOPS AND FEED FLOW

CONTROL CHANGES OVER FRS.

  • AFTER STOPPING BCP IT ACTS AS SUB-CRITICAL ONCE THROUGH“.
  • WHEN THE STEAM PR REACHES 22.1 MPA IT IS IN “SUPERCRITICAL

ZONE”

slide-34
SLIDE 34

LOADING

  • TAKE MILL-A AT 210 MW.
  • CUT THE OIL SUPPORT AT 260 MW AS PER THE FLAME CONDITION.
  • TAKE MILL-D AT 300 MW. MS T/PR 475°C/10 MPA.
  • TAKE MILL-E AT 430 MW. MS T/PR 566°C/17 MPA.
  • TAKE MILL-F AT 540 MW. MS T/PR 566°C/24.1 MPA.
  • INCREASE THE LOAD TO “FULL LOAD 660 MW” GRADUALLY.
slide-35
SLIDE 35

Boiler Design Parameters

NO. Parameters Unit 1 100% BMCR Coal consumption (Design) 390.37 t/h 2 Design fuel Indian coal 3 Superheated steam flow 2111 t/h 4 Superheater outlet pressure 25.4 MPa 5 Superheater outlet temperature 569 ℃ 6 Reheated steam flow 1749.1 t/h 7 Reheater inlet pressure 4.73 MPa 8 Reheater outlet pressure 4.49 MPa 9 Reheater inlet temperature 324 ℃ 10 Reheater outlet temperature 569 ℃ Feedwater pressure 28.8 MPa.g 11 Feedwater temperature 280 ℃ 12 Separator’s steam temperature 421 ℃ 13 Air preheater’s outlet air temperature, uncorrected After correcting 153.3 ℃ 147.2 ℃ 14 Calculating thermal efficiency of boiler 87.19%(BMCR)

slide-36
SLIDE 36

TURBINE PARAMETERS

HPT IPT LPT

Pressure (MPa) 24.2 3.961 1.12 I/L Temp (Deg C) 566 566 378 O/L Temp(deg C) 315.3 378 Steam Flow (tph) 1959.25 1649 TURBINE HEAT RATE( KCL/KWH) 1885 No of Stop valves 2 2 No of Control valves 4 4 Steam Admission Parameters at Turbine Inlet

slide-37
SLIDE 37

TURBINE AT FULL LOAD

HPT IPT

RSV

LPT LPT #2 GEN

CRH CRH HRH MS LINE HRH MS LINE 3.96MPa / 566°c 24.2MPa/566ºC TO BLR RH RCV MSV RCV RCV RCV CV CV CV RSV CV CV CV CV RSV CV CV MSV CV CV

LPT LPT #2 LPT GEN #2 LPT LPT #1

MSV CV CV MSV CV MSV CV MSV CV CV MSV CV MSV CV MSV CV CV MSV MSV CV MSV CV CV MSV RSV CV CV RSV CV RSV CV RSV CV CV RSV 1.12MPa / 378°c CONDENSOR A CONDENSOR B

slide-38
SLIDE 38
  • EXCEPT IN AN EMERGENCY, LOAD SHOULD BE REDUCED

GRADUALLY.

  • CUT THE MILL-F AT 540 MW.
  • CUT THE MILL-E AT 470MW.
  • CUT THE MILL-D AT 300 MW.
  • TAKE OIL SUPPORT FOR FURNACE STABILITY ( AT THE TIME OF 3

MILL OPERATION).

  • CUT THE MILL-A AT 210 MW.
  • TAKE THE HPH-1,2,3 OUT OF SERVICE.
  • WHEN THE LOAD < 30% BOILER COMES IN WET MODE FROM

DRY MODE. START THE BCP AND MAINTAIN THE SEPEARTOR LEVEL.

SHUT DOWN

slide-39
SLIDE 39

SHUT DOWN

  • WHEN THE LOAD HAS DECREASED TO 20% OF RATED LOAD TRIP

THE TURBINE ON TURBINE PROTECTION. THIS CLOSES THE THROTTLE VALVES, GOVERNOR VALVES, REHEAT STOP VALVES AND INTERCEPTOR VALVES

  • CHECK DRAIN VALVES OPENS IN AUTO.
  • HP LP BYPASS VALVE OPENS TO MAINTAIN THE FLOW.
  • REDUCE THE BOILER LOAD GRADULLY.
  • TRIP THE BOILER.
  • THE VACUUM BREAKER VALVES SHOULD NOT BE OPENED UNTIL THE

TURBINE UNIT HAS COASTED DOWN.

  • VACUUM SHOULD BE KILLED BEFORE GLAND SEALING STEAM IS

SHUT OFF.

  • AUX OIL PUMP STARTS IN AUTO AT 2850 RPM.
  • JOP START IN AUTO AT 1200 RPM.
slide-40
SLIDE 40

SHUT DOWN

  • WHEN THE VACUUM REACHES ZERO, SHUT OFF THE SEALING STEAM

TO THE GLAND STEAM CONTROL VALVES.

  • SHUT DOWN THE GLAND STEAM CONDENSER EXHAUSTER. SHUT

DOWN CONDENSATE PUMP.

  • SHUT DOWN THE VACUUM PUMP.
  • SHUT OFF THE COOLING WATER SUPPLY TO THE GENERATOR

HYDROGEN COOLERS.

  • ENSURE THAT BARRING GEAR HAS CUT IN.
slide-41
SLIDE 41

SHUT DOWN CURVE

slide-42
SLIDE 42

COOL DOWN CURVE

slide-43
SLIDE 43

TH THANK ANK YOU OU