Accelerated Bridge Construction Examples We have been using ABC - - PowerPoint PPT Presentation

accelerated bridge construction examples
SMART_READER_LITE
LIVE PREVIEW

Accelerated Bridge Construction Examples We have been using ABC - - PowerPoint PPT Presentation

Accelerated Bridge Construction Examples We have been using ABC methods to build bridges since 2007 on approximately 25 projects. We used this approach in response to Tropical Storm Irene The following slides show some examples of


slide-1
SLIDE 1

Accelerated Bridge Construction Examples

  • We have been using ABC methods to build bridges since

2007 on approximately 25 projects.

  • We used this approach in response to Tropical Storm Irene
  • The following slides show some examples of past projects
slide-2
SLIDE 2

Accelerated Bridge Construction

Driven steel piles with precast concrete cap for abutment

slide-3
SLIDE 3

Accelerated Bridge Construction

The first of three Precast Concrete Caps being placed

slide-4
SLIDE 4

Accelerated Bridge Construction

Precast concrete Abutment in place and ready for Superstructure

slide-5
SLIDE 5

Accelerated Bridge Construction

Precast Concrete NEXT Beam lifted into place

slide-6
SLIDE 6

Accelerated Bridge Construction

The second NEXT Beam being placed

slide-7
SLIDE 7

Accelerated Bridge Construction

Three NEXT Beams in place with the final unit ready

slide-8
SLIDE 8

Accelerated Bridge Construction

Precast Bridge Unit (PBU) delivered to site

slide-9
SLIDE 9

Accelerated Bridge Construction

Precast Bridge Unit (PBU) lifted onto abutments

slide-10
SLIDE 10

Accelerated Bridge Construction

Precast Bridge Units (PBUs) connected together

slide-11
SLIDE 11

Rigid Frame Examples

  • Generally arch shapes and flat-top frames are both allowed
  • There are many different configurations available
slide-12
SLIDE 12

Rigid Frames

Site is dewatered and excavated for footing

slide-13
SLIDE 13

Rigid Frames

Precast footing section lifted into position

slide-14
SLIDE 14

Rigid Frames

Footing components are connected together

slide-15
SLIDE 15

Rigid Frames

Abutment is backfilled and compacted

slide-16
SLIDE 16

Rigid Frames

Precast frame is lifted into position on the abutment

slide-17
SLIDE 17

Rigid Frames

More sections added – Note dewatering pipe

slide-18
SLIDE 18

Rigid Frames

Top of frame is waterproofed

slide-19
SLIDE 19

Rigid Frames

Gravel roadway surface is placed over frame section

slide-20
SLIDE 20

Rigid Frames

Side view of frame with guardrail attached

slide-21
SLIDE 21

Building Bridges pre-1995