well road project accelerated bridge construction using
play

Well Road Project Accelerated Bridge Construction Using - PowerPoint PPT Presentation

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMTs) By: Mark Bucci, P.E. Presentation Outline Project History Project Scope Construction Alternatives Plan Development


  1. Well Road Project – Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT’s) By: Mark Bucci, P.E.

  2. Presentation Outline  Project History  Project Scope  Construction Alternatives  Plan Development  Contractor’s Methodology  Current Project Status

  3. Project History  Site Information ◦ West Monroe, LA ◦ LA 3249 (Well Road) over I-20 Well Road Overpass Truck Stop

  4. Project History  Site Information ◦ High Average Daily Traffic (ADT)  I-20 41,300 ADT  LA 3249 (Well Road) 18,700 ADT ◦ High truck traffic

  5. Project History  Existing Bridge ◦ Built in 1963 ◦ 4 – Simple Span Composite Steel Plate Girder Bridge (55 ft – 70 ft – 85 ft – 50 ft) ◦ Lightweight concrete deck

  6. Project History  Bridge Condition ◦ Deck Deterioration

  7. Project History ◦ Deck Deterioration

  8. Project History ◦ Deck Deterioration

  9. Project History  Bridge Condition ◦ Bearing Corrosion

  10. Project History ◦ Bearing Corrosion (Cont.)

  11. Project History  Bridge Condition ◦ Column Bent Spalling

  12. Project History  Bridge Load Testing (March 2008) ◦ Bridge Diagnostics, Inc. (BDI) performed the testing ◦ Determine the structural capacity considering deck deterioration ◦ Review the load rating ◦ Provide information to assist in determining the best course of action for rehabilitation

  13. Project History  Bridge Load T esting

  14. Project History  Bridge Load T esting ◦ Finite Element Model  Calibrated to match the test results  The structure was load rated ◦ Results  The bridge did not need to be load posted  An overlay could be applied

  15. Project History  T emporary Repairs ◦ Quick Set Concrete Patches

  16. Project History  T emporary Repairs ◦ Asphalt Overlay  Recommended by the District to reduce maintenance

  17. Presentation Outline  Project History  Project Scope  Construction Alternatives  Plan Development  Contractor’s Methodology  Current Project Status

  18. Project Scope  Project created in mid 2008 to perform permanent repairs  Funded by State Surplus  Aggressive delivery schedule  Proposed July 2009 letting

  19. Project Scope  Requirements  Considerations ◦ Replace the deck ◦ High ADT ◦ Minimize impacts to ◦ Heavy Truck Traffic businesses and the ◦ Future widening traveling public ◦ Maintain vertical clearance ◦ Strengthen substructure if necessary

  20. Accelerated Construction

  21. Presentation Outline  Project History  Project Scope  Construction Alternatives  Plan Development  Contractor’s Methodology  Current Project Status

  22. Construction Alternatives  Accelerated Construction ◦ Precast Panel Units

  23. Construction Alternatives  Accelerated Construction ◦ Precast Panel Units

  24. Construction Alternatives  Accelerated Construction ◦ Span Replacement

  25. Construction Alternatives  Accelerated Construction ◦ Span Replacement  Self-Propelled Modular Transporters (SPMT’s)

  26. Construction Alternatives  Accelerated Construction ◦ Span Replacement  Self-Propelled Modular Transporters (SPMT’s)

  27. Construction Alternatives  Accelerated Construction ◦ Span Replacement  Crane

  28. Construction Alternatives  Accelerated Construction ◦ Recommend span replacement  Reduce traffic impacts  Limit overall closure period

  29. Presentation Outline  Project History  Project Scope  Construction Alternatives  Plan Development  Contractor’s Methodology  Current Project Status

  30. Plan Development  Project Initiation ◦ Task order was created with Modjeski and Masters (NTP issued July 2008)  Design and develop plans for the new steel girder spans with a concrete deck  Load rate the repaired bridge  Develop plans to strengthen the substructure if necessary  Establish constructability  Traffic control plan

  31. Plan Development  Steel Girder Replacement Spans ◦ 28’ clear roadway ◦ Weathering steel rolled W-shape girders ◦ Girders to be composite with deck ◦ 7 ½” thick concrete deck ◦ Epoxy coated deck steel

  32. Plan Development  Steel Girder Spans

  33. Plan Development  Bridge Load Rating ◦ Existing bridge was designed using the HS-20 truck ◦ The rating showed that the substructure required strengthening using LRFR (HL-93 truck)

  34. Plan Development  Substructure Strengthening ◦ A spread footing was added between the existing pile footings of column bents ◦ Drilled shafts were added to the existing end bents

  35. Plan Development  Substructure Strengthening ◦ Column Bent Spread Footing

  36. Plan Development  Substructure Strengthening ◦ End Bent Strengthening (Drilled Shafts)

  37. Plan Development  Suggested Method of Construction ◦ Construct spans in a staging area ◦ Move the spans using SPMT’s  Replace the spans over four consecutive nightly closures from 7:00 PM to 7:00 AM  Replace all four spans over a weekend closure beginning at 7:00 PM Friday and re-opening the bridge at 7:00 AM the following Monday

  38. Plan Development  Suggested Method of Construction

  39. Plan Development  Suggested Method of Construction

  40. Plan Development  Suggested Method of Construction

  41. Plan Development  Prefabrication Plan ◦ Geotechnical assessment ◦ Design of temporary supports ◦ Settlement analysis and monitoring

  42. Plan Development  Movement Plan ◦ As-built survey ◦ Moving equipment ◦ Path of movement ◦ Lift point locations ◦ Analysis of temporary loads on spans ◦ Geotechnical assessment ◦ Span monitoring ◦ Contingency planning

  43. Plan Development  Span Monitoring ◦ 10 – Elevation reference points per span ◦ Monitoring Intervals Before Lift  Immediately After Lift  As needed through transport to maintain relative  elevations Final Position 

  44. Plan Development  Traffic Control Plan Road Closed Road Closed T emporary Detour

  45. Plan Development  Traffic Control Plan ◦ T emporary Detour Road

  46. Plan Development  Traffic Control Plan Project Site

  47. Plan Development  Project was let in December 2009 ◦ Engineer’s Estimate $3.95 Million ◦ Contractor’s Bid Price $ 3.17 Million ◦ Awarded to Gibson and Associates ◦ Work Order issued March 2010

  48. Presentation Outline  Project History  Project Scope  Construction Alternatives  Plan Development  Contractor’s Methodology  Current Project Status

  49. Contractor’s Methodology  Staging area within the interchange  T emporary steel pipe trestle  SPMT’s to move the spans  Perform the moves over a weekend closure

  50. Contractor’s Methodology  Staging Area and Movement Path Staging Area

  51. Contractor’s Methodology  T emporary Support

  52. Contractor’s Methodology  T emporary Support

  53. Contractor’s Methodology  Movement Method

  54. Contractor’s Methodology  Movement Method

  55. Presentation Outline  Project History  Project Scope  Construction Alternatives  Plan Development  Contractor’s Methodology  Current Project Status

  56. Current Project Status  Substructure Strengthening

  57. Current Project Status  Substructure Strengthening

  58. Current Project Status  Substructure Strengthening

  59. Current Project Status  Span Construction

  60. Current Project Status  Span Movement ◦ Span movement plan is currently under review ◦ Span movement is tentatively scheduled for early February 2011

  61. The End

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend