Well Road Project Accelerated Bridge Construction Using - - PowerPoint PPT Presentation

well road project accelerated bridge construction using
SMART_READER_LITE
LIVE PREVIEW

Well Road Project Accelerated Bridge Construction Using - - PowerPoint PPT Presentation

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMTs) By: Mark Bucci, P.E. Presentation Outline Project History Project Scope Construction Alternatives Plan Development


slide-1
SLIDE 1

Well Road Project – Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT’s)

By: Mark Bucci, P.E.

slide-2
SLIDE 2

Presentation Outline

 Project History  Project Scope  Construction Alternatives  Plan Development  Contractor’s Methodology  Current Project Status

slide-3
SLIDE 3

Project History

 Site Information

  • West Monroe, LA
  • LA 3249 (Well Road) over I-20

Well Road Overpass Truck Stop

slide-4
SLIDE 4

Project History

 Site Information

  • High Average Daily Traffic (ADT)

 I-20 41,300 ADT  LA 3249 (Well Road) 18,700 ADT

  • High truck traffic
slide-5
SLIDE 5

Project History

 Existing Bridge

  • Built in 1963
  • 4 – Simple Span Composite Steel Plate Girder

Bridge (55 ft – 70 ft – 85 ft – 50 ft)

  • Lightweight concrete deck
slide-6
SLIDE 6

Project History

 Bridge Condition

  • Deck Deterioration
slide-7
SLIDE 7

Project History

  • Deck Deterioration
slide-8
SLIDE 8

Project History

  • Deck Deterioration
slide-9
SLIDE 9

Project History

 Bridge Condition

  • Bearing Corrosion
slide-10
SLIDE 10

Project History

  • Bearing Corrosion (Cont.)
slide-11
SLIDE 11

Project History

 Bridge Condition

  • Column Bent Spalling
slide-12
SLIDE 12

Project History

 Bridge Load Testing (March 2008)

  • Bridge Diagnostics, Inc. (BDI) performed the

testing

  • Determine the structural capacity considering

deck deterioration

  • Review the load rating
  • Provide information to assist in determining

the best course of action for rehabilitation

slide-13
SLIDE 13

Project History

 Bridge Load T

esting

slide-14
SLIDE 14

Project History

 Bridge Load T

esting

  • Finite Element Model

 Calibrated to match the test results  The structure was load rated

  • Results

 The bridge did not need to be load posted  An overlay could be applied

slide-15
SLIDE 15

Project History

 T

emporary Repairs

  • Quick Set Concrete Patches
slide-16
SLIDE 16

Project History

 T

emporary Repairs

  • Asphalt Overlay

 Recommended by the District to reduce maintenance

slide-17
SLIDE 17

Presentation Outline

 Project History  Project Scope  Construction Alternatives  Plan Development  Contractor’s Methodology  Current Project Status

slide-18
SLIDE 18

Project Scope

 Project created in mid 2008 to perform

permanent repairs

 Funded by State Surplus  Aggressive delivery schedule  Proposed July 2009 letting

slide-19
SLIDE 19

Project Scope

 Requirements

  • Replace the deck
  • Minimize impacts to

businesses and the traveling public

  • Maintain vertical

clearance

  • Strengthen

substructure if necessary

 Considerations

  • High ADT
  • Heavy Truck Traffic
  • Future widening
slide-20
SLIDE 20

Accelerated Construction

slide-21
SLIDE 21

Presentation Outline

 Project History  Project Scope  Construction Alternatives  Plan Development  Contractor’s Methodology  Current Project Status

slide-22
SLIDE 22

Construction Alternatives

 Accelerated Construction

  • Precast Panel Units
slide-23
SLIDE 23

Construction Alternatives

 Accelerated Construction

  • Precast Panel Units
slide-24
SLIDE 24

Construction Alternatives

 Accelerated Construction

  • Span Replacement
slide-25
SLIDE 25

Construction Alternatives

 Accelerated Construction

  • Span Replacement

 Self-Propelled Modular Transporters (SPMT’s)

slide-26
SLIDE 26

Construction Alternatives

 Accelerated Construction

  • Span Replacement

 Self-Propelled Modular Transporters (SPMT’s)

slide-27
SLIDE 27

Construction Alternatives

 Accelerated Construction

  • Span Replacement

 Crane

slide-28
SLIDE 28

Construction Alternatives

 Accelerated Construction

  • Recommend span replacement

 Reduce traffic impacts  Limit overall closure period

slide-29
SLIDE 29

Presentation Outline

 Project History  Project Scope  Construction Alternatives  Plan Development  Contractor’s Methodology  Current Project Status

slide-30
SLIDE 30

Plan Development

 Project Initiation

  • Task order was created with Modjeski and

Masters (NTP issued July 2008)

 Design and develop plans for the new steel girder spans with a concrete deck  Load rate the repaired bridge  Develop plans to strengthen the substructure if necessary  Establish constructability  Traffic control plan

slide-31
SLIDE 31

Plan Development

 Steel Girder Replacement Spans

  • 28’ clear roadway
  • Weathering steel rolled W-shape girders
  • Girders to be composite with deck
  • 7 ½” thick concrete deck
  • Epoxy coated deck steel
slide-32
SLIDE 32

Plan Development

 Steel Girder Spans

slide-33
SLIDE 33

Plan Development

 Bridge Load Rating

  • Existing bridge was designed using the HS-20

truck

  • The rating showed that the substructure

required strengthening using LRFR (HL-93 truck)

slide-34
SLIDE 34

Plan Development

 Substructure Strengthening

  • A spread footing was added between the

existing pile footings of column bents

  • Drilled shafts were added to the existing end

bents

slide-35
SLIDE 35

Plan Development

 Substructure Strengthening

  • Column Bent Spread Footing
slide-36
SLIDE 36

Plan Development

 Substructure Strengthening

  • End Bent Strengthening (Drilled Shafts)
slide-37
SLIDE 37

Plan Development

 Suggested Method of Construction

  • Construct spans in a staging area
  • Move the spans using SPMT’s

 Replace the spans over four consecutive nightly closures from 7:00 PM to 7:00 AM  Replace all four spans over a weekend closure beginning at 7:00 PM Friday and re-opening the bridge at 7:00 AM the following Monday

slide-38
SLIDE 38

Plan Development

 Suggested Method of Construction

slide-39
SLIDE 39

Plan Development

 Suggested Method of Construction

slide-40
SLIDE 40

Plan Development

 Suggested Method of Construction

slide-41
SLIDE 41

Plan Development

 Prefabrication Plan

  • Geotechnical assessment
  • Design of temporary supports
  • Settlement analysis and monitoring
slide-42
SLIDE 42

Plan Development

 Movement Plan

  • As-built survey
  • Moving equipment
  • Path of movement
  • Lift point locations
  • Analysis of temporary loads on spans
  • Geotechnical assessment
  • Span monitoring
  • Contingency planning
slide-43
SLIDE 43

Plan Development

 Span Monitoring

  • 10 – Elevation reference points per span
  • Monitoring Intervals

 Before Lift  Immediately After Lift  As needed through transport to maintain relative elevations  Final Position

slide-44
SLIDE 44

Plan Development

 Traffic Control Plan

Road Closed Road Closed T emporary Detour

slide-45
SLIDE 45

Plan Development

 Traffic Control Plan

  • T

emporary Detour Road

slide-46
SLIDE 46

Plan Development

 Traffic Control Plan

Project Site

slide-47
SLIDE 47

Plan Development

 Project was let in December 2009

  • Engineer’s Estimate $3.95 Million
  • Contractor’s Bid Price $ 3.17 Million
  • Awarded to Gibson and Associates
  • Work Order issued March 2010
slide-48
SLIDE 48

Presentation Outline

 Project History  Project Scope  Construction Alternatives  Plan Development  Contractor’s Methodology  Current Project Status

slide-49
SLIDE 49

Contractor’s Methodology

 Staging area within the interchange  T

emporary steel pipe trestle

 SPMT’s to move the spans  Perform the moves over a weekend

closure

slide-50
SLIDE 50

Contractor’s Methodology

 Staging Area and Movement Path

Staging Area

slide-51
SLIDE 51

Contractor’s Methodology

 T

emporary Support

slide-52
SLIDE 52

Contractor’s Methodology

 T

emporary Support

slide-53
SLIDE 53

Contractor’s Methodology

 Movement Method

slide-54
SLIDE 54

Contractor’s Methodology

 Movement Method

slide-55
SLIDE 55

Presentation Outline

 Project History  Project Scope  Construction Alternatives  Plan Development  Contractor’s Methodology  Current Project Status

slide-56
SLIDE 56

Current Project Status

 Substructure Strengthening

slide-57
SLIDE 57

Current Project Status

 Substructure Strengthening

slide-58
SLIDE 58

Current Project Status

 Substructure Strengthening

slide-59
SLIDE 59

Current Project Status

 Span Construction

slide-60
SLIDE 60

Current Project Status

 Span Movement

  • Span movement plan is currently under

review

  • Span movement is tentatively scheduled for

early February 2011

slide-61
SLIDE 61

The End