SLIDE 1
ABC - Folded Plate Bridge System Uxbridge Massachusetts Maury - - PowerPoint PPT Presentation
ABC - Folded Plate Bridge System Uxbridge Massachusetts Maury - - PowerPoint PPT Presentation
ABC - Folded Plate Bridge System Uxbridge Massachusetts Maury Tayarani Bridge Project Management Massachusetts Department of Transportation Email: morteza.tayarani@state.ma.usa Phone: 857-368-9282 Presentation Outline 1- Introduction to Mass
SLIDE 2
SLIDE 3
Presentation Outline
1- Introduction to Mass DOT ABC Initiative 2- Introduction to Folded Plate Girder Bridge System 3- Description of the bridge using folded plate by MassDOT- Uxbridge 4- Design Information- Uxbridge 5- Procurement and design process 6- Sequence of fabrication and construction 7- Future MassDOT plans 8- Contact information
SLIDE 4
Mass DOT in 2007 initiated $3 billion Patrick-Murray Accelerated Bridge Program Since 2008, number of deficient bridges has dropped by 19% (as of August 1, 2013)
SLIDE 5
In eight years program
- ver 200 bridges are planned to be replaced or repaired
138 bridge projects – Completed Fast 14 is just one of the MassDOT - ABC projects 38 bridge projects in construction 22 bridge projects scheduled to start in 2014.
SLIDE 6
Presentation Outline
1- Introduction to Mass DOT ABC Initiative 2- Introduction to Folded Plate Girder Bridge System for ABC Application 3- Description of the bridge using folded plate by MassDOT- Uxbridge 4- Design Information- Uxbridge 5- Procurement and design process 6- Sequence of fabrication and construction 7- Future MassDOT plans 8- Contact information
SLIDE 7
Folded Plate Girder System is best suited for ABC application using steel alternate
SLIDE 8
Utilizing ABC philosophy One folded plate bridge systems constructed and is in service in Uxbridge Massachusetts and has been monitored since construction Second folded plate bridge system using is scheduled for construction in summer of 2014 (Nebraska) Additional bridges are in development
- r design stages
SLIDE 9
Development of Folded Plate Bridge System for ABC application involved conducting more than seven years
- f research, under direction of Dr. Azizinamini while he
was at University of Nebraska - Lincoln
SLIDE 10
Part of the research included fatigue test by subjecting the test specimen to more than 7.5 million cycles of loading
SLIDE 11
Folded Plate Bridge System is a proprietary product However, it is available from more than one source
SLIDE 12
Folded Plate Girders are made by bending flat plate into a C shape by using press break Plate thicknesses used are 3/8 inches or ½ inches
SLIDE 13
Maximum length of the folded plate girder is limited to 60 ft., which is the reflection of the maximum press brakes that are available.
SLIDE 14
Eleven Standard Shapes
Folded Plate comes in 11 standard shapes
Each shape come in 3/8 inch or ½ inch thickness
SLIDE 15
Stable Shape During Casting Deck
No need for internal cross frames No need for external cross frames No fatigue prone details Lowest fatigue category detail is B
SLIDE 16
Design is conservatively based on girders being supported at two ends, when casting deck. The actual production is based on girder sitting on flat bed (shored construction) and supported continuously.
SLIDE 17
Open bottom allows easy Inspection This was very important for MassDOT
SLIDE 18
Three main options exist for corrosion protection of steel
1- Galvanizing - Used by MassDOT for folded plate
SLIDE 19
Three options for corrosion protection
- f folded plate girders are
1- Galvanizing – Used by MassDOT 2- Weathering steel – will be used for second Folded Plate Bridge in USA (in Nebraska) 3- Coating, metalizing
SLIDE 20
Presentation Outline
1- Introduction to Mass DOT ABC Initiative 2- Introduction to Folded Plate Girder Bridge System 3- Description of the bridge using folded plate by MassDOT in Uxbridge, MA 4- Design Information- Uxbridge 5- Procurement and design process 6- Sequence of fabrication and construction 7- Future MassDOT plans 8- Contact information
SLIDE 21
Uxbridge Project
As one of the leading States in utilizing ABC And willingness to incorporate new technologies into a bridge program In 2009, Mass DOT decided to use Folded plate as a pilot project in town of Uxbridge
(River Rd. / Ironstone Brook, 40 miles SW of Boston)
SLIDE 22
Existing bridge Uxbridge Massachusetts
SLIDE 23
Presentation Outline
1- Introduction to Mass DOT ABC Initiative 2- Introduction to Folded Plate Girder Bridge System 3- Description of the bridge using folded plate by MassDOT- Uxbridge 4- Design Information- Uxbridge 5- Procurement and design process 6- Sequence of fabrication and construction 7- Future MassDOT plans 8- Contact information
SLIDE 24
New Bridge Using Folded Plate
46 ft. Span (C-C Bearing)
SLIDE 25
New Bridge was designed to be wider
Two 12.0 ft. lanes with two 4.0 ft. shoulders
SLIDE 26
New Bridge using Folded Plate
(4) Pre-top deck Girders @ 9’-5” C-C Spacing 13” Closure Width
SLIDE 27
Interior Pre-top Beam- 100 Inch wide
and 2 inch overlay
SLIDE 28
Exterior Pre-top Beam- 92 inch wide Edge beam cast in the plant for facilitating attachment of the railing
SLIDE 29
Cross section of one girder All Girders are the same
SLIDE 30
Design was based on AASHTO LRFD
Bridge Design Specification using HL93 Loads
SLIDE 31
Strength
- Moment
– Demand 29000 Kip-in – Resistance 35000 Kip-in
- Shear
– Demand 220 Kips – Resistance 580 Kips
SLIDE 32
Service Limit States
- Deflection
– 2 HS20 Trucks = 0.28 in. – Span/800 = 0.69 in.
- Stress in top flange
– Demand 7 ksi – Resistance 47 ksi
- Stress in Bottom Flange
– Demand 39 ksi – Resistance 47 ksi
SLIDE 33
Fatigue Detail Design and Categories
- Lowest Fatigue Category
Lowest fatigue category detail is B
which is at the Bottom Flange at the Tie Plate location
- For Uxbridge, Design based on Infinite Life
– Stress Range = 9 KSI – Resistance = 16 KSI (Threshold)
SLIDE 34
Shear Studs
- 4 Studs per Line
– Based on strength requirements, stud spacing is 11.4 inches – Based on fatigue requirements, stud spacing is 17.5 inches
- Actual stud spacing used is= 11 in.
SLIDE 35
Presentation Outline
1- Introduction to Mass DOT ABC Initiative 2- Introduction to Folded Plate Girder Bridge System 3- Description of the bridge using folded plate by MassDOT- Uxbridge 4- Design Information- Uxbridge 5- Procurement and design process 6- Sequence of fabrication and construction 7- Future MassDOT plans 8- Contact information
SLIDE 36
Uxbridge Project
Engineering estimate by MassDOT was $2 million
This included 600’ of roadway work as well as substructure and superstructure
The winning contract was 20% lower than estimate Job was advertised July 2010 Notice To Proceed Dec. 2010 Bridge Opened to traffic on Nov 2011
SLIDE 37
Folded plate bending – Kansas Galvanizing – Kansas
SLIDE 38
Girders were then shipped to Vermont Casting deck- Carrara- Vermont
SLIDE 39
Contractor – John Rocchio
Four Folded plate with pre-top deck was provided and delivered to the contractor, to the job site, at the cost of $192,000
SLIDE 40
Design of superstructure:
By folded plate provider
Independent Check:
Mass DOT hired consultant to carry out independent design check of folded plate provider and design the substructure
Bridge instrumentation:
University of Mass instrumented and have monitored the bridge Performance since construction.
SLIDE 41
Presentation Outline
1- Introduction to Mass DOT ABC Initiative 2- Introduction to Folded Plate Girder Bridge System 3- Description of the bridge using folded plate by MassDOT- Uxbridge 4- Design Information- Uxbridge 5- Procurement and design process 6- Sequence of fabrication and construction 7- Future MassDOT plans 8- Contact information
SLIDE 42
Girders were first fabricated in the shop by bending flat plate
SLIDE 43
Additional photos of bending the girders
SLIDE 44
Additional photos of bending the girders
SLIDE 45
Additional photos of bending the girders
SLIDE 46
Photo showing one completed girder
SLIDE 47
Summary of Fabrication Steps
1- Bending girders 2- welding the end Plates 3- bolting four tie plates 4- Welding Shear Studs
1 3 2 4
SLIDE 48
Fabrication
Shear studs were called to be attached according to the requirements of AWS D1.5 And the girders were then sent to galvanizing
SLIDE 49
Corrosion protection is provided by galvanizing the girder
SLIDE 50
Fabrication
Unfortunately there were fabrication errors in attaching the shear studs Problem was not noticed until after the galvanizing the girders We had to replace some of the shear studs with bolts
SLIDE 51
After galvanizing , all four girders were transferred to the precast plant
SLIDE 52
For ABC application, the formwork is simple. For Uxbridge the contractor built the formwork
- ver pre-stressing bed and placed the folded
plate in between the formwork
SLIDE 53
Design was based on girder being supported at two ends while casting the deck, However, during Construction, girders were supported over the entire length (shored construction)
SLIDE 54
Casting Deck- Note use of headed shear studs for closure pour
SLIDE 55
Pre-top folded plate units were placed over trailers, following casting and curing deck
SLIDE 56
The shipping width of completed module were 10’-2”. Including 11” headed rebar All four units were ready for shipping by August 2011 Units shipped to job site on October 2011 All four units were shipped to the job site on a same day
SLIDE 57
Type of Substructure Used
Next few slides shows type of substructure elements utilized Pre-fabricated sub-structure elements were used to accelerate the construction processes.
SLIDE 58
Steel piles were placed in pre-drilled holes. The bottom 5 ft. of the pre-drilled holes, were filed with concrete. The rest of the pre-drilled holes were then filled with crushed stone.
SLIDE 59
This slide shows portion of the steel piles extending outside the pre-drilled holes
SLIDE 60
Abutment wall consisted of precast units that were placed adjacent to each other & then post tensioned
SLIDE 61
All pieces of abutment wall being installed
SLIDE 62
View of completed abutment wall, showing the four concrete pedestals, used as girder seats and anchor rods
SLIDE 63
Construction Pad (Not for Bearing) Holes at the top of concrete pedestals were used to grout the cavity
SLIDE 64
SLIDE 65
Girder Units Placed
SLIDE 66
Truck delivering a completed pre-top folded plate girder
SLIDE 67
Placing Girder Unit over abutments
SLIDE 68
Placing Girder Unit
SLIDE 69
SLIDE 70
SLIDE 71
Girder Ends
Cast-in-place concrete used for closure pour and concrete diaphragm to complete the construction
SLIDE 72
From Below
SLIDE 73
Finished Structure
SLIDE 74
Finished Roadway
SLIDE 75
Presentation Outline
1- Introduction to Mass DOT ABC Initiative 2- Introduction to Folded Plate Girder Bridge System 3- Description of the bridge using folded plate by MassDOT- Uxbridge 4- Design Information- Uxbridge 5- Procurement and design process 6- Sequence of fabrication and construction 7- Future MassDOT plans 8- Contact information
SLIDE 76
MassDOT’s Chief Engineer’s office and its directors emphasize the ABC and use of more pre-fabricated bridge elements in future projects. One of MassDOT’s projects is considering using the next generation of the folded plate, consisting of full depth deck with end wall casted in the plan.
SLIDE 77