75 th street path project
play

75 th Street Path Project Feasibility Study Presentation Presented - PowerPoint PPT Presentation

75 th Street Path Project Feasibility Study Presentation Presented By: William Hall, P.E. CrossRoad Engineers, PC 3417 Sherman Drive Beech Grove, IN 46107 WHY THIS PROJECT? IMPROVE QUALITY OF LIFE Public Safety Connectivity and


  1. 75 th Street Path Project Feasibility Study Presentation Presented By: William Hall, P.E. CrossRoad Engineers, PC 3417 Sherman Drive Beech Grove, IN 46107

  2. WHY THIS PROJECT? IMPROVE QUALITY OF LIFE • Public Safety • Connectivity and Access - Walkability • Traffic Benefits • Health Benefits • Social Benefits • Increased Property Values • Lower Crime Rates DESIRED AMENITY

  3. WHY 75 TH STREET? OPTIMAL LOCATION • Town of Meridian Hills Thoroughfare • Maximize Service Area of the Path • Centrally Located • Extend Across the Town’s Boundaries

  4. WHY 75 TH STREET?

  5. WHY 75 TH STREET?

  6. WHY 75 TH STREET? OPTIMAL LOCATION • Town of Meridian Hills Thoroughfare • Maximize Service Area of the Path • Centrally Located • Extend Across the Town’s Boundaries • Connectivity and Access

  7. WHY 75 TH STREET?

  8. WHY 75 TH STREET? OPTIMAL LOCATION • Town of Meridian Hills Thoroughfare • Maximize Service Area • Connectivity and Access • Supplement Existing 75 th Street Bike Lanes

  9. WHY THE NORTH SIDE? PROMOTE USER SAFETY • Minimize Conflict between Users and Vehicles MINIMIZE COST • R/W Needs - Utility Relocations - Topography/Drainage Impacts DATA DRIVEN ANALYSIS • Parcel Feasibility: NW Quad = 88% NE Quad = 63% SW Quad = 11% SE Quad = 13%

  10. WHAT WILL IT LOOK LIKE? RECOMMENDED DESIGN BASED ON: • National Design Guidelines • Anticipated Users and Town Needs • Best Engineering Practice RECOMMENDED DESIGN ELEMENTS: • Path Material: Asphalt • Path Width: 10 ft. (desired) / 8 ft. (minimum) • Path Separation: 6 ft. (desired) • Path Shoulder: 3-5 ft. (desired) / 2 ft. (minimum) • Half R/W Width: 35 ft. (desired)

  11. WHAT WILL IT LOOK LIKE?

  12. WHAT WILL IT LOOK LIKE?

  13. 75 TH STREET PATH STUDY PRELIMINARY PROJECTED BUDGET: • $1,700,000 + • Based on Estimated Construction, Survey, Design, and Inspection Costs ANTICIPATED PROJECT FUNDING: • State and Local Grant Funding • Resident Donations • Town Budget EXPECTED LIFE-CYCLE: • 15 – 20 Years

  14. 75 TH STREET PATH STUDY QUESTIONS?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend