4 Hearn Avenue Interchange Phase 3 Project Status December Project Approval & Environmental 2016 - Document Completed January Design Complete 2021 February Ready to List - Construction 2021 Hearn Avenue Interchange Phase 3
SLIDE 2
SLIDE 3
SLIDE 4
4
SLIDE 5
Project Status
Hearn Avenue Interchange Phase 3
December 2016 Project Approval & Environmental
- Document Completed
January 2021 Design – Complete February 2021 Ready to List - Construction
SLIDE 6
Funding - Design
Hearn Avenue Interchange Phase 3
Total Cost to Date: $1,600,156
$2.13M
APPROPRIATED REIMBURSED
$800,078
LOCAL FUNDS
$800,078
SLIDE 7
Funding - Right of Way
Hearn Avenue Interchange Phase 3
Total Cost to Date: $182,928
$800K
APPROPRIATED REIMBURSED
$91,464
LOCAL FUNDS
$91,464
SLIDE 8
Hearn Avenue Interchange Phase 3
Funding - Construction
$3.45M
MEASURE M PROJECT COST ESTIMATE
$23.85M
NEED
$24.0M
SLIDE 9
SLIDE 10
10
SLIDE 11
Fulton Road Improvements
August 2017 Environmental Document – Completed January 2018 Design – Begin December 2020 Design – Complete March 2021 Construction – Begin
Project Status
SLIDE 12
Fulton Road Improvements
Funding - Design Total Cost to Date: $1,505,350
$1M
APPROPRIATED REIMBURSED
$505,350
LOCAL FUNDS
$1M
SLIDE 13
Fulton Road Improvements
Funding - Right of Way Total Cost to Date: $365,394
$200K
APPROPRIATED REIMBURSED
$165,394
LOCAL FUNDS
$200,000
SLIDE 14
SLIDE 15
Project Status
April 2020 Scoping/Environmental – Begin December 2020 Design – Begin April 2021 ROW – Begin
SLIDE 16
Funding - Scoping/Environmental
$1,038
REIMBURSED PROGRAMMED
$52K
LOCAL FUNDS
$167
Total Cost to Date: $1,205
SLIDE 17