2018 capital project progress report
play

2018 Capital Project Progress Report Project Scope Window - PowerPoint PPT Presentation

2018 Capital Project Progress Report Project Scope Window Replacements Roof Replacements HVAC Improvements Project Schedule Project Budget 2018 Capital Project Progress Report Wappingers Central School District September


  1. 2018 Capital Project Progress Report  Project Scope  Window Replacements  Roof Replacements  HVAC Improvements  Project Schedule  Project Budget 2018 Capital Project Progress Report Wappingers Central School District September 12, 2018 S eptember 23, 2013 R H I N E B E C K A R C H I T E C T U R E 1

  2. District Wide Scope of Work Phase 3.1 - 2019 Phase 3.2 - 2020 and 2021 Window Replacement HVAC Improvements  John Jay HS  Roy C Ketcham HS  Brinckerhoff ES Replace Boilers and Steam Heating System  Gayhead ES  Kinry Road ES  John Jay HS  Myers Corners ES Replace Steam Heating System  Sheafe Road ES  Myers Corners ES Phase 3.1 Replace Unit Ventilators Roof Replacement  Fishkill Plains ES 2018 Capital Project Progress Report Wappingers Central School District September 12, 2018 S eptember 23, 2013 R H I N E B E C K A R C H I T E C T U R E 2

  3. Previous Window Replacement Work  R. C. Ketcham HS  Van Wyck Junior HS  Fishkill ES  Fishkill Plains ES  James Evans ES  Oak Grove ES  Vassar Road ES  Wappingers Junior HS Van Wyck Jr HS R. C. Ketcham HS Vassar Road ES 2018 Capital Project Progress Report Wappingers Central School District September 12, 2018 S eptember 23, 2013 R H I N E B E C K A R C H I T E C T U R E 3

  4. Window Replacement – John Jay High School - Existing Existing Windows 2018 Capital Project Progress Report Wappingers Central School District September 12, 2018 S eptember 23, 2013 R H I N E B E C K A R C H I T E C T U R E 4

  5. Window Replacement – John Jay High School Existing Windows New Windows 2018 Capital Project Progress Report Wappingers Central School District September 12, 2018 S eptember 23, 2013 R H I N E B E C K A R C H I T E C T U R E 5

  6. Window Replacement – Brinckerhoff and Gayhead Elementary Schools Existing Windows New Windows (Similar to Fishkill Plains ES) 2018 Capital Project Progress Report Wappingers Central School District September 12, 2018 S eptember 23, 2013 R H I N E B E C K A R C H I T E C T U R E 6

  7. Window Replacement – Brinckerhoff Elementary School Existing Cafeteria Similar to Oak Grove ES Cafeteria Cafeteria with New Windows 2018 Capital Project Progress Report Wappingers Central School District September 12, 2018 S eptember 23, 2013 R H I N E B E C K A R C H I T E C T U R E 7

  8. Window Replacement – Kinry Road Elementary School New Windows Existing Windows 2018 Capital Project Progress Report Wappingers Central School District September 12, 2018 S eptember 23, 2013 R H I N E B E C K A R C H I T E C T U R E 8

  9. Window Replacement – Myers Corners Elementary School New Windows Existing Windows 2018 Capital Project Progress Report Wappingers Central School District September 12, 2018 S eptember 23, 2013 R H I N E B E C K A R C H I T E C T U R E 9

  10. Window Replacement – Sheafe Road Elementary School Existing Windows New Windows (Similar to Fishkill Plains ES) 2018 Capital Project Progress Report Wappingers Central School District September 12, 2018 S eptember 23, 2013 R H I N E B E C K A R C H I T E C T U R E 10

  11. Roof Replacement – Fishkill Plains Elementary School 57,000 sf Roof on Tectum and Wood Plank Deck. Installed in 1990’s New roof system to provide 25 year warranty. 2018 Capital Project Progress Report Wappingers Central School District September 12, 2018 S eptember 23, 2013 R H I N E B E C K A R C H I T E C T U R E 11

  12. Project Schedule – Phase 3.1  Construction Documents October 2018  SED Review Complete December 2018  Bid & Award January 2019  Construction Starts June 2019 Project Schedule – Phase 3.2 - HVAC  Construction Documents October 2018  Design Development March 2019  Construction Documents June 2019  Expedited SED Review September 2019  Bid & Award October 2019  Construction Starts June 2020  Construction Complete September 2021 2018 Capital Project Progress Report Wappingers Central School District September 12, 2018 S eptember 23, 2013 R H I N E B E C K A R C H I T E C T U R E 12

  13. Project Budget Scope Construction Budget Incidental Costs Total 3.1 Window Replacements $4,780,800 $956,160 $5,736,560 3.1 Roof Replacement $1,332,000 $266,400 $1,598,400 $4,414,600 $26,487,600 3.2 HVAC Improvements $22,073,000 Total $28,185,800 $5,637,160 $38.822,560 Cost Estimates will be prepared for Phase 3.1 in October 2018, and for Phase 3.2 at each Design Phase (October, March and June 2019) 2018 Capital Project Progress Report Wappingers Central School District September 12, 2018 S eptember 23, 2013 R H I N E B E C K A R C H I T E C T U R E

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend