Page 2
5/26/20 BOE Meeting
(Crawlspace Access, Abatement, New Boiler & Cafeteria/Gym HVAC System Replacement) Contract No. 1 – Hazardous Materials Contractor Contract No. 2 – General Construction Contractor Contract No. 3 – Mechanical Contractor (Boiler Room) Contract No. 4 – Electrical Contractor (Boiler Room) Contract No. 5 – Mechanical Contractor (Cafeteria/Gym HVAC) Contract No. 6 – Electrical Contractor (Cafeteria/Gym HVAC)
(Stadium Locker Room/Concession/Restrooms/Storage Building) Contract No. 1 – General Construction Contractor Contract No. 2 – Mechanical Contractor Contract No. 3 – Plumbing Contractor Contract No. 4 – Electrical Contractor
Proctor High School - Fields Support Building: Contract No. 1 – General Construction Contractor Proctor High School - Upper Stadium Concessions Building: Contract No. 2 – General Construction Contractor Donovan Middle School - Fields Support Building: Contract No. 3 – General Construction Contractor
Page 3
5/26/20 BOE Meeting
Page 4
5/26/20 BOE Meeting
Page 5
5/26/20 BOE Meeting
Page 6
5/26/20 BOE Meeting
Page 7
5/26/20 BOE Meeting
Page 8
5/26/20 BOE Meeting
Page 9
5/26/20 BOE Meeting
Page 10
5/26/20 BOE Meeting
Page 11
5/26/20 BOE Meeting
New soccer/lacrosse, softball, baseball, and track work began 4/20/20, and is progressing.
Page 12
5/26/20 BOE Meeting
New soccer/lacrosse, softball, baseball, and track work began 4/20/20, and is progressing.
Page 13
5/26/20 BOE Meeting
Contract Award Resolution – MAY 2020
(Crawlspace Access, Abatement, New Boiler & Cafeteria/Gym HVAC System Replacement) Contract No. 1 - AKTOR Corporation - (Hazardous Materials Contractor) Contract No. 2 - Murnane Building Contractors, Inc. - (General Construction Contractor) Contract No. 3 - Giruzzi Plumbing & Heating Inc. - (Mechanical Contractor - Boiler Room) Contract No. 4 - Usmail Electric, Inc. - (Electrical Contractor - Boiler Room) Contract No. 5 - Giruzzi Plumbing & Heating Inc. - (Mechanical Contractor - Cafeteria/Gym HVAC) Contract No. 6 - Oneida Electric Contractors, Inc. - (Electrical Contractor - Cafeteria/Gym HVAC)
(Stadium Locker Room/Concession/Restrooms/Storage Building) Contract No. 1 - Beebe Construction Services - (General Construction Contractor) Contract No. 2 - HJ Brandeles Corporation - (Mechanical Contractor) Contract No. 3 - HJ Brandeles Corporation - Plumbing Contractor Contract No. 4 - Bagnall Electric, Inc. - Electrical Contractor
Proctor High School - Fields Support Building: Contract No. 1 - McGinnis Nelson Construction - (General Construction Contractor) Proctor High School - Upper Stadium Concessions Building: Contract No. 2 - ALL BIDS REJECTED Donovan Middle School - Fields Support Building: Contract No. 3 - Beebe Construction Services - (General Construction Contractor)
Page 14 5/26/20 BOE Meeting
Boiler Room & Cafeteria/Gymnasium
SED # 41-23-00-01-0-007-011 Bid Results Summary - Contract No. 1: Hazardous Materials
CONTRACTOR BASE BID City/State AKTOR Corporation $ 186,750 Waterville, NY CAYSEA $ 248,000 West Seneca, NY Sullivan Contracting, Inc. $ 234,000 Sauquoit, NY TBC Industries, LLC $ 242,000 Westmoreland, NY
Recommendation for Award of Contract to the Qualified Lowest Bidder: AKTOR Corporation Contract Amount: $ 186,750 44 Tivoli Street Albany, NY 12207
Page 15 5/26/20 BOE Meeting
Boiler Room & Cafeteria/Gymnasium Project
SED # 41-23-00-01-0-007-011 Bid Results Summary - Contract No. 2: General Construction Contractor
CONTRACTOR BASE BID City/State Edgebrook Construction Co., Inc. $ 38,880 Marcy, NY Murnane Building Contractors, Inc. $ 38,200 Whitesboro, NY
Recommendation for Award of Contract to the Qualified Lowest Bidder: Murnane Building Contractors, Inc. Contract Amount: $ 38,200 15 Wood Road Whitesboro, NY 13492
Page 16 5/26/20 BOE Meeting
Boiler Room & Cafeteria/Gymnasium Project
SED # 41-23-00-01-0-007-011 Bid Results Summary - Contract No. 3: Mechanical (Boiler Room)
CONTRACTOR BASE BID City/State Giruzzi Plumbing & Heating Inc. $ 181,000 Utica, NY HJ Brandeles Corporation $ 270,000 Whitesboro, NY
Recommendation for Award of Contract to the Qualified Lowest Bidder: Giruzzi Plumbing & Heating Inc. Contract Amount: $ 181,000 713 Bleecker Street Utica, NY 13501
Page 17 5/26/20 BOE Meeting
Boiler Room & Cafeteria/Gymnasium Project
SED # 41-23-00-01-0-007-011 Bid Results Summary - Contract No. 4: Electrical (Boiler Room)
CONTRACTOR BASE BID City/State Automation Experts $ 49,750 Utica, NY Bagnall Electric, Inc. $ 14,992 Sherburne, NY Oneida Electrical Contractors, Inc. $ 12,218 Oneida, NY Usmail Electric, Inc. $ 11,035 Yorkville, NY
Recommendation for Award of Contract to the Qualified Lowest Bidder: Usmail Electric, Inc. Contract Amount: $ 11,035 800 Calder Avenue Yorkville, NY 13495
Page 18 5/26/20 BOE Meeting
Boiler Room & Cafeteria/Gymnasium Project
SED # 41-23-00-01-0-007-011 Bid Results Summary - Contract No. 5: Mechanical (Cafeteria/Gymnasium HVAC)
CONTRACTOR BASE BID City/State Giruzzi Plumbing & Heating Inc. $ 221,000 Utica, NY HJ Brandeles Corporation $ 224,000 Whitesboro, NY
Recommendation for Award of Contract to the Qualified Lowest Bidder: Giruzzi Plumbing & Heating Inc. Contract Amount: $ 221,000 713 Bleecker Street Utica, NY 13501
Page 19 5/26/20 BOE Meeting
Boiler Room & Cafeteria/Gymnasium Project
SED # 41-23-00-01-0-007-011 Bid Results Summary - Contract No. 6: Electrical (Cafeteria/Gymnasium HVAC)
CONTRACTOR BASE BID City/State Bagnall Electric, Inc. $ 36,853 Sherburne, NY Oneida Electrical Contractors, Inc. $ 32,718 Oneida, NY Usmail Electric, Inc. $ 32,735 Yorkville, NY BID WITHDRAWN: Automation Experts $ 16,375 Utica, NY
Recommendation for Award of Contract to the Qualified Lowest Bidder: Oneida Electrical Contractors, Inc. Contract Amount: $ 32,718 5630 Horatio Street Utica, NY 13502
Page 20 5/26/20 BOE Meeting
SED # 41-23-00-01-7-049-001 Bid Results Summary - Contract No. 1: General Construction Contractor
CONTRACTOR BASE BID
Total City/State Beebe Construction Services, Inc. $1,818,000 $108,000 $1,926,000 Whitesboro, NY Edgebrook Construction Co., Inc. $1,971,240 $117,000 $2,088,240 Marcy, NY
$2,112,000 $ 21,000 $2,133,000 Utica, NY Murnane Building Contractors, Inc. $1,976,000 $ 20,000 $1,996,000 Whitesboro, NY
Recommendation for Award of Contract to the Qualified Lowest Bidder: Beebe Construction Services, Inc. Contract Amount: $1,926,000 PO Box 177 Utica, NY 13501
Page 21 5/26/20 BOE Meeting
SED # 41-23-00-01-7-049-001 Bid Results Summary - Contract No. 2: Mechanical Contractor
CONTRACTOR BASE BID City/State Giruzzi Plumbing & Heating Inc. $ 234,000 Utica, NY HJ Brandeles Corporation $ 221,655 Whitesboro, NY
Recommendation for Award of Contract to the Qualified Lowest Bidder: HJ Brandeles Corporation Contract Amount: $ 221,655 8101 Halsey Road Whitesboro, NY 13492
Page 22 5/26/20 BOE Meeting
SED # 41-23-00-01-7-049-001 Bid Results Summary - Contract No. 3: Plumbing Contractor
CONTRACTOR BASE BID City/State Giruzzi Plumbing & Heating Inc. $ 313,000 Utica, NY HJ Brandeles Corporation $ 275,278 Whitesboro, NY
Recommendation for Award of Contract to the Qualified Lowest Bidder: HJ Brandeles Corporation Contract Amount: $ 275,278 8101 Halsey Road Whitesboro, NY 13492
Page 23 5/26/20 BOE Meeting
SED # 41-23-00-01-7-049-001 Bid Results Summary - Contract No. 4: Electrical Contractor
CONTRACTOR BASE BID City/State Automation Experts $270,200 Utica, NY Bagnall Electric, Inc. $261,148 Sherburne, NY Knapp Electric, Inc. $292,400 Auburn, NY Patricia Electric, Inc. $310,000 Syracuse, NY Usmail Electric, Inc. $305,220 Yorkville, NY
Recommendation for Award of Contract to the Qualified Lowest Bidder: Bagnall Electric, Inc. Contract Amount: $ 261,148 45 Classic Street PO Bix 577 Sherburne, NY 13460
Page 24 5/26/20 BOE Meeting
SED # 41-23-00-01-2-046-001 Bid Results Summary - Contract No. 1: General Construction Contractor
CONTRACTOR BASE BID
Total City/State Beebe Construction Services, Inc. $297,000 $44,500 $341,500 Utica, NY Edgebrook Construction Co., Inc. $338,280 $57,000 $395,280 Marcy, NY
$312,000 $29,000 $341,000 Utica, NY McGinnis Nelson Construction, Inc. $295,000 $45,000 $340,000 Whitesboro, NY
Recommendation for Award of Contract to the Qualified Lowest Bidder: McGinnis Nelson Construction, Inc. Contract Amount: $340,000 4833 Appletree Ridge Manlius, NY 13104
Page 25 5/26/20 BOE Meeting
SED # 41-23-00-01-7-048-001 Bid Results Summary - Contract No. 2: General Construction Contractor
CONTRACTOR BASE BID City/State Beebe Construction Services, Inc. $365,000 $38,000 $403,000 Utica, NY Edgebrook Construction Co., Inc. $448,480 $39,000 $487,480 Marcy, NY
$393,000 $10,000 $403,000 Utica, NY McGinnis Nelson Construction, Inc. $405,000 $39,000 $444,000 Whitesboro, NY
Recommendation for all bids to be rejected, as all bids exceeded the funding allocated for this project
END 5/26/20 BOE Meeting
SED # 41-23-00-01-1-047-001 Bid Results Summary - Contract No. 3: General Construction Contractor
CONTRACTOR BASE BID City/State Beebe Construction Services, Inc. $341,000 Utica, NY Edgebrook Construction Co., Inc. $424,240 Marcy, NY
$363,000 Utica, NY McGinnis Nelson Construction $357,000 Whitesboro, NY
Recommendation for Award of Contract to the Qualified Lowest Bidder: Beebe Construction Services, Inc. Contract Amount: $341,000 PO Box 177 Utica, NY 13501