2011 final lcr study results humboldt and north coast
play

2011 Final LCR Study Results Humboldt and North Coast/ North Bay - PowerPoint PPT Presentation

2011 Final LCR Study Results Humboldt and North Coast/ North Bay Paul Didsayabutra Senior Regional Transmission Engineer Stakeholder Meeting April 15, 2010 Humboldt and North Coast/North Bay Areas Humboldt Load and Resources (MW) 2011 Load


  1. 2011 Final LCR Study Results Humboldt and North Coast/ North Bay Paul Didsayabutra Senior Regional Transmission Engineer Stakeholder Meeting April 15, 2010

  2. Humboldt and North Coast/North Bay Areas

  3. Humboldt Load and Resources (MW) 2011 Load = 197 Transmission Losses = 9 Total Load = 206 Market Generation = 166 Muni Generation = 0 QF/Self-Gen Generation = 57 Total Qualifying Capacity = 223 Slide 3

  4. Critical Contingencies Humboldt Area Slide 4

  5. Critical Contingencies Humboldt Area Two types of requirements: • Humboldt 60 kV Pocket • Entire Humboldt area Slide 5

  6. Critical Contingencies Humboldt 60 kV Sub-area Humboldt 60 kV Sub-area – Category B Contingency: The outages of one Humboldt 115/60 kV Transformer and one unit of the New Humboldt Bay (on 60 kV side) LCR need: 163 MW (including 57 MW of QF/Self generation and 6 MW of deficiency) Limiting component: Thermal overload on the parallel Humboldt 115/60 kV Transformer Humboldt 60 kV Sub-area – Category C Contingency: The outages of one Humboldt 115/60 kV Transformer and one of the tie-line connecting the New Humboldt Bay units (on 60 kV side) LCR need: 174 MW (including 57 MW of QF/Self generation and 17 MW of deficiency) Limiting component: Thermal overload on the parallel Humboldt 115/60 kV Transformer Slide 6

  7. Critical Contingencies Humboldt Area Humboldt Overall – Category B Nothing extra to the single contingency for the 60 kV pocket. Humboldt Overall – Category C Contingency: The outages of Cottonwood – Bridgeville 155 kV line overlapping with an outage of one of the tie-line connecting the New Humboldt Bay Units LCR need: 188 MW (including 57 MW of QF/Self generation) Limiting component: Thermal overload on the Humboldt -Trinity 115kV Line Slide 7

  8. Changes Since last year: 1) The new Humboldt Bay Repowering Project (HBPP) is modeled 2) Two new transmission projects are modeled  Maple Creek Reactive Support  Garberville Reactive Support While load is lower but total LCR need has increased since system conditions have changed and different limitation is identified  Reactive power is no longer the most critical contingency  The HBPP project changes the amount of generation on 115 and 60 kV sides Your comments and questions are welcome. Your comments and questions are welcome. For written comments, please send to: RegionalTransmission@caiso.com Slide 8

  9. North Coast/Bay Load and Resources (MW) 2011 Load = 1511 Transmission Losses = 63 Total Load = 1574 Market Generation = 728 Muni Generation = 118 QF Generation = 15 Total Qualifying Capacity = 861 Slide 9

  10. North Coast and North Bay Cortina Lakeville Pocket 230 kV Eagle Rock Pocket 115 kV Sonoma 115 kV Kekawaka Laytonville 60 kV 60 kV Corona 115 kV 115 kV Eagle Rock Lakeville 115 kV Vaca Dixon 230 kV 230 kV 230 kV Tulucay Fulton 230 kV 230 kV Fulton Pocket Ignacio Sobrante 230 kV Slide 10

  11. Eagle Rock Sub-Area Eagle Rock Sub-area – Category C Contingency: Eagle Rock-Silverado- Fulton 115 kV line and Cortina #4 230/115 kV bank. LCR need: 217 MW (includes 3 MW of QF/Muni generation) Limiting component: Thermal overload on Fulton-Hopland 60 kV line Eagle Rock Sub-area – Category B Contingency: Cortina #4 230/115 kV bank. LCR need: 93 MW (includes 3 MW of QF/Muni generation) Limiting component: Thermal overload on Fulton-Hopland 60 kV line Slide 11

  12. Fulton and Lakeville Sub-areas Fulton Sub-area – Category C Contingency: Lakeville-Ignacio #1 230 kV line and Crocket-Sobrante #1 230 kV line. LCR need: 546 MW (includes 14 of QF and 57 MW of Muni generation) Limiting component: Thermal overload on Fulton-Lakeville #1 230 kV line Lakeville Sub-area (NC/NB Overall) – Category B Contingency: Vaca Dixon-Lakeville 230 kV line and DEC power plant out of service LCR need: 734 MW (includes 133 MW of QF/Muni generation) Limiting component: Thermal overload on the Vaca Dixon-Tulucay 230 kV line Slide 12

  13. Changes Since last year: 1) Load forecast is down by 40 MW 2) Total LCR need has decreased by 56 MW Your comments and questions are welcome. Your comments and questions are welcome. For written comments, please send to: RegionalTransmission@caiso.com Slide 13

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend