1
1 Background Next to former Vosper Thorneycroft site Area of - - PowerPoint PPT Presentation
1 Background Next to former Vosper Thorneycroft site Area of - - PowerPoint PPT Presentation
1 Background Next to former Vosper Thorneycroft site Area of regeneration Built 1966 Compliance issues 2 Pre-existing layout Inlet Works LLPS PSTs Storm Tank FSTs Sludge Tank ASP 3 Site Issues Main issues
Background
▪ Next to former Vosper Thorneycroft site ▪ Area of regeneration ▪ Built 1966 ▪ Compliance issues
2
Pre-existing layout
3
PSTs Inlet Works Storm Tank Sludge Tank ASP FSTs LLPS
Site Issues
- Main issues
- How to achieve performance on constrained site
- How to maintain performance on constrained site
- How to be a good neighbour in revitalised area
- Approach to answering these issues
- Integrated team
- Compliance planning
- Stakeholder engagement
Process Drivers
- New Total Nitrogen Permit
- UWWTR - 15 mg/l Annual Average (70% Removal)
- WRA - 15mg/l Annual Average
- Adherence with existing Permit from Historic Limitation
- FFT 427 l/s
- Inlet Screen performance
- Catchment Population Growth to 73000 pe
- Historic Odour Nuisance - new limits set to 1.5 ouE/m3 at nearest property
- Pre-requisite planning condition for regeneration and site
5
Process solution
6
Crude Sewer Storm Screen Inlet Screens Terminal PS FOGG Plant Lamellas UFS BNR MBR Sludge Tanks Centrifuges Storm Tank Odour Control Scrubbers LLPS
Architectural Solution
Construction Sequence - 1
8
Construction Sequence - 2
9
Construction Sequence - 3
10
Construction Sequence - 4
11
Innovations
12
Membrane Technology
13
Membrane Technology
- Hollow fibre ultrafiltration MBR. Air and chemicals
are used for cyclical cleaning of the filters. ▪ Pore sizes (0.03 µm) small enough to retain Bacteria & Viruses as well as solids.
- Treatment performance is already significantly
- utperforming the Permit Conditions
- ~5 mg/l BOD vs. Target 25 mg/l
- ~5mg/l SS vs. Target 60 mg/l
- ~15mg/l Nitrogen vs. Target 15 mg/l or 75%
removal
- Nitrogen removal on target for meeting standards
- nce optimised following sludge plant
commissioning
14
UWWTR 24h composite samples (24 samples per year)
Date
BIOCHEMICAL OXYGEN DEMAND (HOMOGENISED) CHEMICAL OXYGEN DEMAND (LOW LEVEL) (HOM) TOTAL NITROGEN SOLIDS (SUSPENDED AT 105C) (HOMOGENISED)
11/07/2018 07:15 5.78 2. 20/07/2018 06:45 3.9 44.8 37.5 3.5 10/08/2018 06:45 6.3 43.9 49.7 3. 17/08/2018 06:32 3.69 38.1 31.8 2. 11/09/2018 06:46 3.22 33.2 18.3 2. 24/09/2018 10:15 1. 23.8 11.1 2.5 05/10/2018 07:24 3.43 26.3 14.4 2. 26/10/2018 09:01 2.46 23.2 13.9 2. 13/11/2018 06:55 2.12 14.4 11.2 2. 27/11/2018 11:22 1. 7.34 9.85 2. 04/12/2018 12:25 2.15 11.8 13.4 2. 08/12/2018 07:42 2.52 11.6 13.1 2. 13/12/2018 07:37 1. 19.7 17.7 2.
Summary
▪ Use of BNR and MBR at Woolston has enabled us to achieve high performance already before completion on very constrained site. ▪ Digital engineering / BIM key to success in planning complex temporary and permanent works. ▪ Without stakeholder support the project would have been unbuildable and vastly more expensive solutions would have been required.
15