1 agenda welcome introductions meeting schedule stewart
play

1 AGENDA Welcome, introductions, meeting schedule Stewart - PowerPoint PPT Presentation

Bond Oversight Committee 2014 Bond program August 4, 2016 1 AGENDA Welcome, introductions, meeting schedule Stewart Jacobson, Chair Program Management: Oscar Perez & Ron Holleyhead Review Bond Monthly Report Zandra


  1. Bond Oversight Committee 2014 Bond program August 4, 2016 1

  2. AGENDA • Welcome, introductions, meeting schedule – Stewart Jacobson, Chair • Program Management: Oscar Perez & Ron Holleyhead • Review Bond Monthly Report – Zandra Becerra • Review the updated Master Budget - Zandra Becerra • Review New BOT Report – Zandra Becerra • Review the Master Schedule – Ron Holleyhead • Accomplishments Since Last Meeting – Ron Holleyhead • Sullivan ES (ES 47 in Riverstone) Update – Ashley Dixon • Phase I Budget Status Report – Oscar Perez • Next Steps - Ron Holleyhead • Update other projects (IT, Security, Transportation) – Long Pham, David Rider and Mike Brassfield • Small Business Program – Bob Fazakerly • Communication Plan Update – Nancy Porter • Debt Service Fund Update – Steve Bassett • Bond 2018 Planning – Steve Bassett • Open Feedback from BOC Members – Stewart Jacobson 2

  3. MONTHLY REPORT BUDGET REVIEW Value of Project by Schedule Phase (data from February 2016 Monthly report) (data from June 2016 Monthly report) * * Not Started= NA Pre-Design= $ 59,853,550 Pre-Design= $ 118,719,739 Design= $ 111,196,469 Design= $ 219,383,330 Bidding & Negotiation= $ 59,675,360 Construction= $ 43,011,977 Construction= $ 146,268,824 Districtwide* = $ 102,932,320 Districtwide* = $ 107,076,005 TOTAL = $ 484,047,366 ** TOTAL = $ 484,070,235 ** *Districtwide includes district managed work not assigned to a specific location including transportation, technology, land, bond support, security cameras & infrastructure and classroom additions. 3 **Amount includes interest earned to date

  4. MONTHLY REPORT BUDGET/COST REVIEW Program Budget Cost Status (data from June 2016 Monthly report) (data from February 2016 Monthly report) Commitments (including approved Commitments (including approved changes) = $92,308,805 changes) = $137,566,321 New Construction = $ 44,740,690 New Construction = $ 72,349,430 Renovations and Additions= $ 14,452,639 Renovations and Additions= $ 8,072,300 Districtwide* = $ 50,764,251 Districtwide* = $ 39,495,815 Cost To Date = $57,749,047 Cost To Date = $76,297,587 New Construction = $ 26,119,002 New Construction = $ 30,673,980 Renovations and Additions= $ 5,315,982 Renovations and Additions= $ 2,914,941 Districtwide* = $ 40,307,624 Districtwide* = $ 28,715,104 *Districtwide includes district managed work not assigned to a specific location including transportation, technology, land, bond support, security cameras & infrastructure and pending classroom additions. 4

  5. MASTER BUDGET INDICATOR Total Bond: $484M $480M As of July 11, 2016: $400M • Total Bond = $484M (100%) • Committed= $137.5M (28.4%) $300M • Cost To Date= $76.3M ( 15.8%) $200M Committed Cost: 28.4% - $137.5M as of 7/11/2016 $100M Cost to Date: 15.8% - $76.3M as of 7/11/2016 5

  6. NEW BOT REPORT 6

  7. NEW BOT REPORT 7

  8. NEW BOT REPORT (EXHIBIT A) 2014 BOND PROGRAM CONTINGENCY Date Description Current Budget Proposed Budget Surplus (Shortage) Cumulative 07/18/16 Bond 2014 Interest as of May 2016* $0 $0 $70,235 $0 $70,235 Classrooms Additions-Unallocated 05/16/16 funds $10,194,244 $6,906,260 $3,287,984 $0 $3,358,219 Temporary Classrooms Buildings 05/16/16 Relocation $433,878 $1,307,749 $0 ($873,871) $2,484,348 ES47-Sullivan Elementary School 05/16/16 savings as of May 2016 $42,984,737 $40,484,737 $2,500,000 $0 $4,984,348 05/16/16 Bid Package 05-ES50 $32,702,895 $31,696,470 $1,006,425 $0 $5,990,773 05/16/16 Bid Package 06-ES49 $30,447,522 $33,734,879 $0 ($3,287,357) $2,703,416 05/16/16 Bid Package 07 $15,171,388 $12,561,186 $2,627,278 ($17,076) $5,313,618 05/16/16 Bid Package 09 $12,456,496 $9,344,890 $3,347,281 ($235,675) $8,425,224 Bid Package 02-Paving & Lighting 05/16/16 Improvements $3,296,432 $3,296,432 $1,383,482 ($1,383,482) $8,425,224 06/20/16 Bid Package 03-ES48 $30,447,522 $31,393,711 $0 ($946,189) $7,479,035 07/18/16 Bid Package 12 $1,950,330 $2,567,765 $68,625 ($686,060) $6,861,600 07/18/16 Bid Package 13 $1,828,437 $2,247,034 $32,515 ($451,112) $6,443,003 TOTAL AS OF JULY 2016 $181,913,881 $175,541,113 $14,323,825 ($7,880,822) $6,443,003 * Bond 2014 Interest includes $47,335.95 plus additional $22,899.28 of interest reported as per May 31, 2016 reconciliation. 8

  9. MASTER SCHEDULE (PHASE I) • Phase I • 13 Bid Package (BP) all work under construction contract (as of Aug 2016) 9

  10. MASTER SCHEDULE (PHASE II) • Phase II • 2 BP in SD Phase / 7 BP in CD Phase 10

  11. MASTER SCHEDULE (PHASE III) • Phase III • BOT has assigned all AE to 7 remaining Bid Packages 11

  12. ACCOMPLISHMENTS Accomplishments Since Last BOC Meeting Phase I • All Phase I projects have bid and been negotiated. Upon Board of Trustee approval of BP 08, 10, & 11 in August 2016, all construction contracts will be approved for Phase I – BOT approved site and Educational Specifications for the Career and Technical Education (CTE) Facility – Relocated portable buildings Phase II • Completed all scope-to-budget activities • All Phase II projects are in design phase 12

  13. ES 47 – Anne McCormick Sullivan Elementary Current Construction and Activation Activities: • Architectural and MEP punch list • Test and Air Balancing • Fundamental Commissioning • Health and Safety building inspections • Site and road striping/signage installation • Plaster installation – Area A • Exterior canopy installation • Landscaping and play structure installation • IT Network equipment, wireless application protocol (WAP), staff and student technology equipment • Classroom and Administration furniture and equipment 13

  14. PHASE I BUDGET STATUS REPORT Phase I – Construction Contract / Phase II – 50% or 90% CD Phase New Construction Comparison Construction Contingency Other Soft Costs Total Budget $ 126,475,939 $ 8,379,784 $ 19,969,337 $ 154,825,060 Estimate $ 137,306,237 $ 7,749,128 $ 9,769,695 $ 154,825,060 Difference $ (10,830,298) $ 630,656 $ 10,199,642 $ 0 Additions Comparison Construction Contingency Other Soft Costs Total Budget $ 12,824,894 $ 1,247,441 $ 2,146,865 $ 16,219,200 Estimate $ 19,075,744 $ 1,659,479 $ 2,277,965 $ 23,013,188 Difference $ (6,250,850) $ (412,039) $ (131,100) $ (6,793,988) Life Cycle/Deficiency Comparison Construction Contingency Other Soft Costs Total Budget $ 81,132,617 $ 12,698,855 $ 12,581,092 $ 106,412,564 Estimate $ 77,451,648 $ 5,826,664 $ 12,224,224 $ 95,502,536 Difference $ 3,680,969 $ 6,872,191 $ 356,868 $ 10,910,028 Net for New, Additions, Life Cycle/Deficiency $ 4,116,040 Based on Phase I – Construction Contract / Phase II – 50% or 90% CD Phase cost estimates, when all Phase I and II projects are considered together, staff estimates that there are sufficient funds budgeted to complete the Phase I and Phase II projects. When all budget categories are considered together, staff projects a positive budget balance of $4,116,040 . Note - Projections may not sum due to rounding. 14

  15. NEXT STEPS Phase I • Groundbreaking ceremonies • Complete construction • FF&E • Occupancy Phase II • Finalize CD phase • Advertise, bid and negotiate • Issue general contractor agreements Phase III • Issue architect/engineer agreements 15

  16. INSTRUCTIONAL TECHNOLOGY UPDATE IT Infrastructure & Security Camera Projects Total 995 - DSTW - Wireless Electronics 994 - DSTW - WAN Network Electronics 993- DSTW Wireless Contingency 992 - DSTW - WAN Design Contingency 991 - DSTW - Wireless Cabling/Fiber 990 - DSTW - WAN Cabling/Fiber 931 - Infrastructure Cameras $0 $5,000,000 $10,000,000 $15,000,000 $20,000,000 $25,000,000 $30,000,000 $35,000,000 $40,000,000 $45,000,000 991 - DSTW - 931 - Infrastructure 990 - DSTW - WAN 992 - DSTW - WAN 993- DSTW Wireless 994 - DSTW - WAN 995 - DSTW - Wireless Total Cameras Cabling/Fiber Design Contingency Contingency Network Electronics Wireless Electronics Cabling/Fiber % of Budget 39.5% 19.1% 8.0% 5.8% 4.5% 22.6% 55.7% 33.8% Total Exp & Enc $1,184,438 $675,000 $315,000 $74,250 $74,270 $2,818,911 $9,214,449 $14,356,318 Initial Budget $3,000,000 $3,528,000 $3,955,799 $1,280,124 $1,640,902 $12,473,570 $16,555,452 $42,433,847 Total Exp & Enc Initial Budget As of April 1, 2016 16

  17. TECHNOLOGY & SECURITY CAMERA UPDATE Middle School Network Infrastructure * Middle School schedule are experience a delay due to proper asset tracking and documentation requirements. 17

  18. TECHNOLOGY & SECURITY CAMERA UPDATE Elementary School Network Infrastructure 18

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend