February 2, 2017
Bond Oversight Committee 2014 Bond program
1
February 2, 2017 1 AGENDA Welcome, Introductions, Meeting - - PowerPoint PPT Presentation
Bond Oversight Committee 2014 Bond program February 2, 2017 1 AGENDA Welcome, Introductions, Meeting Schedule Stewart Jacobson, Chair Introduction and Bond Status Update Ron Holleyhead Budget Indicator Zandra Becerra
Bond Oversight Committee 2014 Bond program
1
2
Total Bond: $484.1M
Committed Costs: 53.5% $259.1 M as of 1/10/17 Cost to Date: 29.0% $140.6 M as of 1/10/17
$480M $400M $300M $200M $100M
3
4
Current Commitments / Approved Change Orders $170.4 $3.6 $3.4 $57.9 $235.3 *Estimates / Pending Change Orders $42.9 $51.3 $110.6 $38.6 $243.4 Total Projected Bond Program Cost $213.3 $54.9 $114.0 $96.5 $478.7 2014 Bond Program Budget $484.1 **Projected Program Budget Balance $5.4
*Projected estimate to complete (based on estimates and pending commitments). **As presented to the Board of Trustees on December 2016. Includes program contingency funds. Note : All values are shown in millions.
Note – Percent complete is based on cost to date 5
IBI Group - Architect Satterfield & Pontikes - General Contractor
6
7
IBI Group - Architect Satterfield & Pontikes - General Contractor
8
9
PBK Architects - Architect Drymalla Construction - General Contractor
10
11
Huckabee - Architect Cadence McShane - General Contractor
12
13
Stantec Architects - Architect TBD - General Contractor
14
15
16
17
18
1. All Middle Schools wireless and cameras are installed. 2. There are 3 phases of this project. a. Phase 1 – 20 schools b. Phase 2 – 15 schools c. Phase 3 – 10 schools 3. ES campus cabling is underway. 4. ES campus power cabling is completed. 5. Cabling team (ATEC) estimated to complete 02/15/17. Cabling team (MCA) estimated to complete 05/15/2017. 6. 5 Tier 3 campuses have been moved to Phase 1 from Phase 3 as of Nov 15,2016. (Hunters Glen, E.A. Jones, Lantern Lane, Mission West, Mission Bend) 7. Auditorium - Estimated to complete Feb 1, 2017. (95% completed) 8. Bus Ramp Wireless a. WiFi install at HS / MS (5% complete) b. Estimated completion: April 2017 9. Security camera challenges a. System intermittently drops recording at peak time. b. Servers can only handle about 150 cameras at a time. c. Vendor, IT, and PD are working to resolve i. Vendor rewrote camera management system ii. IT and PD make necessary adjustments on storage and cameras.
19
10. Fiber Wide Area Network
a. Two core sites for the network have been identified, including offsite disaster recovery center b. Completion date for preparation of the core sites is May 1, 2017 c. SPED 507 – Cameras were deployed to 25 cameras at 10 campuses. 12. Data Center renovation is completed.
20
931 - Infrastructure Cameras 990 - DSTW - WAN Cabling/Fiber 991 - DSTW - Wireless Cabling/Fiber 992 - DSTW - WAN Design Contingency 993 - DSTW Wireless Contingency 994 - DSTW - WAN Network Electronics 995 - DSTW - Wireless Electronics Total
% of Budget 98.9% 110.2% 84.5% 5.8% 52.5% 41.4% 78.3% 69.0% Total Exp & Enc $ 2,967,235 $ 3,886,301 $ 3,342,287 $ 74,251 $ 860,940 $ 5,164,082 $ 12,968,916 $ 29,264,012 Initial Budget $ 3,000,000 $ 3,528,000 $ 3,955,799 $ 1,280,124 $ 1,640,902 $ 12,473,570 $ 16,555,452 $ 42,433,847
21
22
23
24
25
Jan 30, 2016- Jan 30, 2017
26
27
28
Summary Statistics Principal Composition
Total Outstanding Principal 835,985,328 $ Total Fixed Rate 754,345,328 90.23% Total Variable Rate 81,640,000 9.77% Total Interest Payments 420,248,324 Callable Principal (%) 75.57% Percent of Principal Retired w/in 5 years 25.61% w/in 10 years 56.46% w/in 15 years 85.56% w/in 20 years 97.49% Noncallable 24.43% w/in 25 years 100.00% Callable & Advance Refundable 62.00% Final Maturity 8/1/2040 Callable & Partially Advance Refundable 7.96% Callable & Non-Advance Refundable 5.61%
Underlying Ratings Voted Authorization
Fitch AA+ Amount Issued Balance S&P AA+ 428,000,000 $ 380,000,000 $ 48,000,000 $ 484,000,000 $ 85,000,000 $ 399,000,000 $ 912,000,000 $ 465,000,000 $ 447,000,000 $ 11/6/2007 11/4/2014 Date 24.43% 62.00% 7.96% 5.61%
29
$0 $10,000,000 $20,000,000 $30,000,000 $40,000,000 $50,000,000 $60,000,000 $70,000,000 $80,000,000 $90,000,000 $100,000,000 Aggregate Debt Service
Principal Interest
Period Ending 8/31
30
Callable Call Call Bond Issue Principal Date Feature Unlimited Tax School Building & Refunding Bonds, Series 2008 159,620,000 $ 8/15/2018 100.000% Adv Refundable Unlimited Tax Refunding Bonds, Series 2009 28,390,000 2/15/2019 0.000% Adv Refundable Unlimited Tax School Building Bonds, Series 2009 166,730,000 8/15/2019 100.000% Adv Refundable Unlimited Tax School Building & Refunding Bonds, Series 2010 66,580,000 8/15/2020 80.032% Adv Refundable Unlimited Tax Refunding Bonds, Series 2012 46,870,000 8/15/2022 0.000% Adv Refundable Unlimited Tax Refunding Bonds, Series 2014 46,145,000 8/15/2024 100.000% Adv Refundable Variable Rate Unlimited Tax School Building Bonds, Series 2015A 33,155,000 AID 100.000% Adv Refundable Variable Rate Unlimited Tax School Building Bonds, Series 2015B 48,485,000 AID 100.000% Adv Refundable Unlimited Tax Refunding Bonds, Series 2016A 35,755,000 8/15/2024 100.000% Adv Refundable
31
Fixed Rate Interest Period Total Interest Issue - Total Expense Ending Series A Series B Expense Interest Expense Difference 3/9/2017 100,783 $ 2,744 $ 103,527 $ 1,448,265 $ (1,344,738) $ Interest Expense Comparison Commercial Paper Notes
32
* Board approved $7 million paydown on Series 2015B on September 19, 2016. ** Based on current construction budget for Career & Technical Education Center (CTE).
34
35
Series 2017 Refunding Bonds
Board Meeting to Approve Parameter Order Submit PSF Guarantee Conference Calls with Rating Agencies Post POS Receive Ratings Pricing Bond Purchase Agreement Signed Closing February 13, 2017 February 25, 2017 March 22, 2017 March 28, 2017 March 29, 2017 April 4, 2017 April 5, 2017 May 3, 2017
36
37
Series 2015B Remarketing
Board Meeting to Approve Conversion Order Reoffering Memorandum Post POS Pricing Bond Purchase Agreement Signed Closing February 13, 2017 June 12, 2017 July 3, 2017 July 11, 2017 July 12, 2017 August 1, 2017
S M T W T F S 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 S M T W T F S 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 S M T W T F S 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 JUNE JULY AUGUST
38
39
40
2018 Technology Bond Planning Description Technology Area Estimated Costs DC Server Growth
Systems and back end infrastructure
$750,000 VDI Infrastructure Expansion (2nd half)
Additional VDI Infrastructure and Licensing to Support pending phases Systems and back end infrastructure
$4,000,000 DC Storage and Backup Growth
Additional Storage Hardware and Support Systems and back end infrastructure
$900,000 DC Software Growth
Backup/Virtual/Cloud Workloads Systems and back end infrastructure
$900,000 Internal Streaming technology for campus announcements
VBrick is the system the district currently uses for the distribution of video content across the
announcements, instructional videos etc. Student and Campus
$500,000 Network Security
Additional network and systems security will enable better protection of data and district systems Network and back end infrastructure
$250,000 Access security (BYOD)
License and implementation costs associated with BYOD deployment (2014 Assessment recommendation) Student and Campus
$500,000 Firewalls
With the establishment of multi-site redundancy, firewalls will ensure protection of district's digital assets and continuity of business Network and back end infrastructure
$500,000
41
2018 Technology Bond Planning Description Technology Area Estimated Costs
Network logs
Network logs enable engineers to diagnose system faults, malicious activities and facilities establishment of proactive measures to minimize network/system outages Network and back end infrastructure
$250,000 Network monitoring & management tools
Network and system monitoring is vital to the upkeep of existing system as well as to minimize and mitigate issues that may negatively impact business continuity Network and back end infrastructure
$250,000 DC Network Growth
Data center network must be kept current in order to service the needs of the district to the full extent Network and back end infrastructure
$600,000 One H.323 Remote Learning Unit per campus
Currently Polycom is used for remote learning and remote video/audio
10 years old. Needs to be refreshed. Network and back end infrastructure
$900,000 Shared Printers
Current configuration and distribution of printers for teacher and student use is limited and insufficient. A shared printing model will better meet the needs
Classroom/Stude nt
$2,000,000
42
2018 Technology Bond Planning Description Technology Area Estimated Costs Cafeteria and Library AV refresh Many cafeterias and libraries across the district lack AV equipment or what is there currently is insufficient to meet the need. Classroom/Student $1,000,000 Campus Auditorium (HS) Many of the auditoriums in High Schools lack sufficient AV. Complete replacement is needed in some locations while others will need to be upgraded to meet current needs. Classroom/Student $1,210,000 Student Devices This includes, Lending Library, Student devices (min. 10 devices per classroom), mobile carts for check out through library along with hotspots for student check-out for home use Classroom/Student $59,285,375 Interactive Projectors Interactive projectors will provide a means for teachers to convey ideas and concepts while students learn interactively by touch and visual senses Classroom/Student $20,400,000 Estimate Total $94,195,375
43
Bond Oversight Committee 2014 Bond program
44