Schedule and Cost Stewart Loken Physics Division Lawrence Berkeley National Laboratory PDG Computing Review, September 17, 2010 Stewart Loken (LBNL), Page 1 Funding History Proposal submitted to NSF and DOE in 2007 NSF funded in 2007


  1. Schedule and Cost Stewart Loken Physics Division Lawrence Berkeley National Laboratory PDG Computing Review, September 17, 2010 Stewart Loken (LBNL), Page 1

  2. Funding History • Proposal submitted to NSF and DOE in 2007 • NSF funded in 2007 • DOE provided initial funding pending review • Proposal reviewed by DOE in 2008 • Proposal approved with recommendation to add 1 additional year and include system maintenance • DOE committed to proposed funding for 3 years PDG Computing Review, September 17, 2010 Stewart Loken (LBNL), Page 2

  3. DOE and NSF Funding PDG Computing Review, September 17, 2010 Stewart Loken (LBNL), Page 3

  4. Funding versus Costs PDG Computing Review, September 17, 2010 Stewart Loken (LBNL), Page 4

  5. Total Funding and Costs PDG Computing Review, September 17, 2010 Stewart Loken (LBNL), Page 5

  6. Current Status of Key Tasks • Initial design and planning  • System architecture  • Database abstraction layer  • Encoder interface and literature search interface mostly  • Database viewer (main building blocks available) • Data analysis environment partly  Review interface • • Other system tasks – Refactor existing auxiliary programs  – Status monitoring – System monitoring partly  – Verifier interface – Editor interface – Ordering system partly  – Institution data entry • Final acceptance test PDG Computing Review, September 17, 2010 Stewart Loken (LBNL), Page 6

  7. Current Status of Key Tasks • Initial design and planning  • System architecture  • Database abstraction layer  • Encoder interface and literature search interface mostly  • Database viewer (main building blocks available) • All difficult parts posing potential risk to • Data analysis environment partly  the project are implemented Review interface • • The encoder interface is by far the most • Other system tasks complex and difficult application to – Refactor existing auxiliary programs  implement – Status monitoring • The encoder interface includes all the building – System monitoring partly  blocks needed for the other applications (so – Verifier interface building the remaining applications will be relatively fast) – Editor interface – Ordering system partly  – Institution data entry • Final acceptance test PDG Computing Review, September 17, 2010 Stewart Loken (LBNL), Page 7

  8. Future Plan - Summary Project completion expected mid August 2011 leaving 1.5 months of contingency until end of FY11 PDG Computing Review, September 17, 2010 Stewart Loken (LBNL), Page 8

  9. Future Plan - Details PDG Computing Review, September 17, 2010 Stewart Loken (LBNL), Page 9

  10. Future Plan - Details PDG Computing Review, September 17, 2010 Stewart Loken (LBNL), Page 10

  11. Future Plan - Details PDG Computing Review, September 17, 2010 Stewart Loken (LBNL), Page 11

  12. Conclusion • Major technical risks have been addressed • The planned system is now operational and will be upgraded incrementally in FY2011 • The project is on schedule and within budget • Planned completion in August 2011 leaves 1.5 months of contingency in FY2011 PDG Computing Review, September 17, 2010 Stewart Loken (LBNL), Page 12

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.