1/6/2017 1 1/6/2017 Commissioning Benefits Fewer Change Orders - - PDF document
1/6/2017 1 1/6/2017 Commissioning Benefits Fewer Change Orders - - PDF document
1/6/2017 1 1/6/2017 Commissioning Benefits Fewer Change Orders Fewer corrective actions implemented while contractors are on-site Improved planning and coordination Reduced energy consumption during operation Lower operating
1/6/2017 2
Commissioning Benefits
- Fewer Change Orders
- Fewer corrective actions implemented while
contractors are on-site
- Improved planning and coordination
- Reduced energy consumption during
- peration
- Lower operating costs overall
- Better temperature and ventilation control
- Reduced risk of equipment downtime (Data
centers)
Cx Requirements
- Review Owner’s Project Requirments & Basis of
Design
- Develop Cx Plan
- Confirm Cx requirements in construction docs
- Develop construction checklists and test
procedures and verify execution
- Maintain issues and benefits log
- Prepare Cx Report
- Prepare Current Facility Requirments (CFR) and
O&M Manual
Cx Requirements
- Commission systems as they relate
to energy, water, indoor environmental quality, and durability
- Report findings and
recommendations to the owner throughout the process.
- Full Envelope Cx is not required
unless the project team pursues Enhanced Cx, Option 2
1/6/2017 3
1/6/2017 4
1/6/2017 5
1/6/2017 6 Elements of Systems Manual
- Executive Summary
- OPR & BOD
- System single-line diagrams
- Construction record documents
- Approved Submittals
- As-built drawings
- As-built Sequence of Operation
- Original set points for all systems commissioned
- Recommended schedule for re-commissioning
- Recommend schedule for senor recalibration
- Equipment operations and maintenance manuals
- Equipment preventive maintenance schedules
- Confirmation of completed training
- Ongoing system optimization procedures
- Final Commissioning Report
Ongoing Commissioning Plan
- Recommended schedule for
re-commissioning
- Continuous updating of
building operation plan and CFR
- Blank testing materials
including functional performance tests
- Direction for testing new and
retrofitted equipment Path 1 Enhanced Cx-Recap
- Review contractor submittals
- Verify inclusion of systems manual requirements in
construction docs
- Verify inclusion of operator and occupant training requirements
in construction docs
- Verify systems manual updates and delivery
- Verify operator and occupant training delivery and
effectiveness
- Verify seasonal testing
- Review building operations 10 months after substantial
completion
- Develop on-going Cx plan
1/6/2017 7
Path 2 Monitoring Based Cx
- Achieve Path 1
- Develop procedures and identify points to be
measured and evaluated to assess performance of energy and water systems. Must include:
– Limits of acceptable values – Action plan for correction of errors and deficiencies – Training to prevent errors – Energy and water use profiles – Frequency of analyses in 1st year of occupancy (at least quarterly)
Path 2 Monitoring Based Cx
- MBCx allow user to track energy consumption, detect
fault equipment operations, and identify unusual energy
- r power consumption patterns as they occur
Option 2. Envelop Cx
- Complete Cx in accordance with ASHRAE
Guideline 0 and NIBS Guideline 3 for thermal envelope
- Can achieve without Option 1
- Follow requirements of Option 1, Path 1 for
thermal envelope
Envelope Enhanced Cx
- Review contractor submittals
- Verify inclusion of systems manual requirements in
construction docs
- Verify inclusion of operator and occupant training requirements
in construction docs
- Verify systems manual updates and delivery
- Verify operator and occupant training delivery and
effectiveness
- Verify seasonal testing
- Review building operations 10 months after substantial
completion
- Develop on-going Cx plan
1/6/2017 8
Envelope Enhanced Cx
Testing Activities:
- Infrared Camera
- Tracer smoke
- Water bottle
- Calibrated water hose
- Moisture meter
- Field mock-up
- Blower door Assembly
System Tests
- Air infiltration
- Water infiltration
- Exhaust re-entrainment
- Thermal performance
- Building envelope pressure
- Building envelope air leakage
- Daylighting glare control
Envelope Enhanced Cx
Cx Requirements (Data Center Only)
For Projects that select option 1:
- Conduct at least one Cx verification review
- f OPR, BOD, and design documents before
mid-construction documents development
- Back-check the review comments in all
subsequent design submissions
- Conduct an additionalfull verification
review at 95% completion of the design documents and BOD
1/6/2017 9
- Sets baseline for
HVAC, Lighting, Envelope, and Service Water Heating
- Follow Appendix
G for modeling
- Comply with
mandatory provisions
- Based on Cost
Savings
1/6/2017 10
Energy Model
- 5 Energy Models
–1 design model (your building) –4 baseline models (ASHRAE buildings)
- 1 same orientation as design
building + 3 more rotated 90 degrees each time Energy Model
- Must meet minimum energy
requirements first without Renewable Energy
- Non Regulated loads kept
identical unless following the exceptional calculation method –Can follow COMNET Modeling guidelines
1/6/2017 11
Data Centers-2% of the 5% energy savings must come from building power and cooling infrastructure Retail: Process loads for retail may include refrigeration equipment, cooking and food preparation, clothes washing, and other major support appliances. Some baseline equipment in Appendix 3
ASHRAE 50% Advanced Energy Design Guide-Eligible Buildings
- Offices < 100,000 SF
- Retail Buildings > 20,000 &
<100,000 SF
- K-12 School Buildings
- Hospitals > 100,000 SF
1/6/2017 12 Advanced Buildings Core Performance Guide-Eligible Buildings
- Must be less than <100,000 SF
- Healthcare, Warehouse, and
Laboratory projects are ineligible
Decision Flow Chart
New Construction Major Renovation Core and Shell Point (Except Schools, Healthcare
6% 4% 3% 1 8% 6% 5% 2 10% 8% 7% 3 12% 10% 9% 4 14% 12% 11% 5 16% 14% 13% 6 18% 16% 15% 7 20% 18% 17% 8 22% 20% 19% 9 24% 22% 21% 10 26% 24% 23% 11 29% 27% 26% 12 32% 30% 29% 13 35% 33% 32% 14 38% 36% 35% 15 42% 40% 39% 16 46% 44% 43% 17 50% 48% 47% 18
1/6/2017 13
Building-Level Energy Metering
- Building-level or aggregated
submeters
- Electricity, natural gas, chilled
water, steam, fuel oil, propane, biomass
- Utility owned meters ok
- Track minimum 1 month intervals
- Commit to report to USGBC, 5 years
1/6/2017 14
Requirements Install advanced energy metering for the following:
- all whole-building energy sources used by the building; and
- any individual energy end uses that represent 10% or more of the total annual
consumption of the building. The advanced energy metering must have the following characteristics.
- Meters must be permanently installed, record at intervals of one hour or less, and
transmit data to a remote location.
- Electricity meters must record both consumption and demand. Whole-building
electricity meters should record the power factor, if appropriate.
- The data collection system must use a local area network, building automation system,
wireless network, or comparable communication infrastructure.
- The system must be capable of storing all meter data for at least 36 months.
- The data must be remotely accessible.
- All meters in the system must be capable of reporting hourly, daily, monthly, and
annual energy use.
Identifying major energy end uses is the first step in choosing what to meter. Often, in large commercial or industrial buildings, end uses are classified as systems composed of discrete pieces of equipment that can be metered together. For example,
- Chilled water system: chillers, chilled water pumps
- Condenser water system: cooling tower, condenser water pumps
- Hot water system (natural gas): boilers
- Hot water system (electricity): hot water pumps
- Air-handling system: supply fan, return fan, damper motors
Examples of typical end uses for a commercial office building that may require advanced metering include the following:
- Receptacle equipment
- Interior lighting
- Space heating
- Space cooling
- Fans
- Pumps
- Heat rejection
- Exterior lighting
- Service water heating
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
1/6/2017 15 District Energy System (DES)
Downstream: equipment must comply Upstream: 5 year phase out required Reduce annual leakage of CFC to <5%
1/6/2017 16
1/6/2017 17
1/6/2017 18
Commission DR Process including at least one full test of the DR Plan
1/6/2017 19
Follow requirements of Option 1 with ability for the building automation system to accept a future external price or control signal
1/6/2017 20
Community Solar / Solar Gardens
- Project owns system or has 10
year lease
- Located within same utility
service area Renewable Energy Credit
- If green attribute sold, purchase
replacement REC’s or Carbon Offset with 10 year contract
- Use Virtual Rate or Actual Rate
Plus Demand to calculate cost Renewable Energy Credit Interactions
- Must be sub-metered to comply
with Advanced Energy Metering
- Impacts energy cost for proposed