1 6 2017 1
play

1/6/2017 1 1/6/2017 Commissioning Benefits Fewer Change Orders - PDF document

1/6/2017 1 1/6/2017 Commissioning Benefits Fewer Change Orders Fewer corrective actions implemented while contractors are on-site Improved planning and coordination Reduced energy consumption during operation Lower operating


  1. 1/6/2017 1

  2. 1/6/2017 Commissioning Benefits • Fewer Change Orders • Fewer corrective actions implemented while contractors are on-site • Improved planning and coordination • Reduced energy consumption during operation • Lower operating costs overall • Better temperature and ventilation control • Reduced risk of equipment downtime (Data centers) Cx Requirements • Review Owner’s Project Requirments & Basis of Design • Develop Cx Plan • Confirm Cx requirements in construction docs • Develop construction checklists and test procedures and verify execution • Maintain issues and benefits log • Prepare Cx Report • Prepare Current Facility Requirments (CFR) and O&M Manual Cx Requirements • Commission systems as they relate to energy, water, indoor environmental quality, and durability • Report findings and recommendations to the owner throughout the process. • Full Envelope Cx is not required unless the project team pursues Enhanced Cx, Option 2 2

  3. 1/6/2017 3

  4. 1/6/2017 4

  5. 1/6/2017 5

  6. 1/6/2017 Elements of Systems Manual • Executive Summary • OPR & BOD • System single-line diagrams • Construction record documents • Approved Submittals • As-built drawings • As-built Sequence of Operation • Original set points for all systems commissioned • Recommended schedule for re-commissioning • Recommend schedule for senor recalibration • Equipment operations and maintenance manuals • Equipment preventive maintenance schedules • Confirmation of completed training • Ongoing system optimization procedures • Final Commissioning Report Ongoing Commissioning Plan • Recommended schedule for re-commissioning • Continuous updating of building operation plan and CFR • Blank testing materials including functional performance tests • Direction for testing new and retrofitted equipment Path 1 Enhanced Cx-Recap • Review contractor submittals • Verify inclusion of systems manual requirements in construction docs • Verify inclusion of operator and occupant training requirements in construction docs • Verify systems manual updates and delivery • Verify operator and occupant training delivery and effectiveness • Verify seasonal testing • Review building operations 10 months after substantial completion • Develop on-going Cx plan 6

  7. 1/6/2017 Path 2 Monitoring Based Cx • Achieve Path 1 • Develop procedures and identify points to be measured and evaluated to assess performance of energy and water systems. Must include: – Limits of acceptable values – Action plan for correction of errors and deficiencies – Training to prevent errors – Energy and water use profiles – Frequency of analyses in 1 st year of occupancy (at least quarterly) Path 2 Monitoring Based Cx • MBCx allow user to track energy consumption, detect fault equipment operations, and identify unusual energy or power consumption patterns as they occur Option 2. Envelop Cx Envelope Enhanced Cx • Review contractor submittals • Complete Cx in accordance with ASHRAE • Verify inclusion of systems manual requirements in Guideline 0 and NIBS Guideline 3 for thermal construction docs • Verify inclusion of operator and occupant training requirements envelope in construction docs • Can achieve without Option 1 • Verify systems manual updates and delivery • Verify operator and occupant training delivery and • Follow requirements of Option 1, Path 1 for effectiveness • Verify seasonal testing thermal envelope • Review building operations 10 months after substantial completion • Develop on-going Cx plan 7

  8. 1/6/2017 Envelope Enhanced Cx Envelope Enhanced Cx Testing Activities: System Tests • Infrared Camera • Air infiltration • Tracer smoke • Water infiltration • Water bottle • Exhaust re-entrainment • Calibrated water hose • Thermal performance • Moisture meter • Building envelope pressure • Field mock-up • Building envelope air leakage • Blower door Assembly • Daylighting glare control Cx Requirements (Data Center Only) For Projects that select option 1: • Conduct at least one Cx verification review of OPR, BOD, and design documents before mid-construction documents development • Back-check the review comments in all subsequent design submissions • Conduct an additionalfull verification review at 95% completion of the design documents and BOD 8

  9. 1/6/2017 • Sets baseline for HVAC, Lighting, Envelope, and Service Water Heating • Follow Appendix G for modeling • Comply with mandatory provisions • Based on Cost Savings 9

  10. 1/6/2017 Energy Model • 5 Energy Models – 1 design model (your building) – 4 baseline models (ASHRAE buildings) • 1 same orientation as design building + 3 more rotated 90 degrees each time Energy Model • Must meet minimum energy requirements first without Renewable Energy • Non Regulated loads kept identical unless following the exceptional calculation method – Can follow COMNET Modeling guidelines 10

  11. 1/6/2017 Data Centers-2% of the 5% energy savings must Retail: Process loads for retail may include come from building power and cooling refrigeration equipment, cooking and food infrastructure preparation, clothes washing, and other major support appliances. Some baseline equipment in Appendix 3 ASHRAE 50% Advanced Energy Design Guide-Eligible Buildings • Offices < 100,000 SF • Retail Buildings > 20,000 & <100,000 SF • K-12 School Buildings • Hospitals > 100,000 SF 11

  12. 1/6/2017 Advanced Buildings Core Performance Guide-Eligible Buildings • Must be less than <100,000 SF • Healthcare, Warehouse, and Laboratory projects are ineligible Decision Flow Chart Point (Except New Major Schools, Construction Renovation Core and Shell Healthcare 6% 4% 3% 1 8% 6% 5% 2 10% 8% 7% 3 12% 10% 9% 4 14% 12% 11% 5 16% 14% 13% 6 18% 16% 15% 7 20% 18% 17% 8 22% 20% 19% 9 24% 22% 21% 10 26% 24% 23% 11 29% 27% 26% 12 32% 30% 29% 13 35% 33% 32% 14 38% 36% 35% 15 42% 40% 39% 16 46% 44% 43% 17 50% 48% 47% 18 12

  13. 1/6/2017 Building-Level Energy Metering • Building-level or aggregated submeters • Electricity, natural gas, chilled water, steam, fuel oil, propane, biomass • Utility owned meters ok • Track minimum 1 month intervals • Commit to report to USGBC, 5 years 13

  14. 1/6/2017 Requirements Identifying major energy end uses is the first step in choosing what to meter. Often, in large commercial or industrial buildings, end uses are classified as systems composed of discrete pieces of equipment that can be Install advanced energy metering for the following: metered together. For example, � � Chilled water system: chillers, chilled water pumps all whole-building energy sources used by the building; and � Condenser water system: cooling tower, condenser water pumps any individual energy end uses that represent 10% or more of the total annual � � Hot water system (natural gas): boilers consumption of the building. � Hot water system (electricity): hot water pumps � Air-handling system: supply fan, return fan, damper motors The advanced energy metering must have the following characteristics. � Meters must be permanently installed, record at intervals of one hour or less , and Examples of typical end uses for a commercial office building that may require advanced metering include the following: transmit data to a remote location. � Receptacle equipment � Electricity meters must record both consumption and demand. Whole-building � Interior lighting electricity meters should record the power factor, if appropriate. � Space heating � � Space cooling The data collection system must use a local area network, building automation system, � Fans wireless network, or comparable communication infrastructure. � Pumps The system must be capable of storing all meter data for at least 36 months. � � Heat rejection � The data must be remotely accessible. � Exterior lighting All meters in the system must be capable of reporting hourly, daily, monthly, and � � Service water heating annual energy use. Monday Tuesday Wednesday Thursday Friday Saturday Sunday 14

  15. 1/6/2017 District Energy System (DES) Downstream: equipment must comply Upstream: 5 year phase out required Reduce annual leakage of CFC to <5% 15

  16. 1/6/2017 16

  17. 1/6/2017 17

  18. 1/6/2017 Commission DR Process including at least one full test of the DR Plan 18

  19. 1/6/2017 Follow requirements of Option 1 with ability for the building automation system to accept a future external price or control signal 19

  20. 1/6/2017 Community Solar / Solar Gardens Renewable Energy Credit • Project owns system or has 10 • If green attribute sold, purchase year lease replacement REC’s or Carbon Offset with 10 year contract • Located within same utility • Use Virtual Rate or Actual Rate service area Plus Demand to calculate cost Renewable Energy Credit Interactions • Must be sub-metered to comply with Advanced Energy Metering • Impacts energy cost for proposed building so has positive impact on Optimize Energy Performance 20

  21. 1/6/2017 CORE AND SHELL Energy usage of Core and Shell floor area defined by BOMA standards, but not < 15% floor area 21

  22. 1/6/2017 22

  23. 1/6/2017 23

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend