Zackuse Creek Fish Passage Project Road Closure Options City Council Meeting July 18, 2017 Public Works Department: Tawni Dalziel, PE Senior Stormwater Program Manager Cheryl Paston, PE Deputy Public Works Director 2 Project Overview and


slide-1
SLIDE 1

City Council Meeting July 18, 2017

Zackuse Creek Fish Passage Project

Road Closure Options

Public Works Department: Tawni Dalziel, PE Senior Stormwater Program Manager Cheryl Paston, PE Deputy Public Works Director

slide-2
SLIDE 2

Project Overview and Status

  • Replace existing culvert on ELSP with fish

passable box culvert

  • Restore and realign degraded stream

channel upstream of ELSP

  • 30% design completed
  • Permits have been submitted
  • Construction start June 2018

2

slide-3
SLIDE 3

Decision needed tonight

Obtain direction on project road closures:

3

Option 1. Full road closure Option 2. Partial road closure

slide-4
SLIDE 4

Traffic Control Options

4

Full road closure Partial road closure

slide-5
SLIDE 5

Considerations

  • Stream and habitat impacts
  • Duration for culvert construction
  • Traffic impacts
  • Detour route options
  • Cost difference

5

slide-6
SLIDE 6

Stream Impacts

Full Road Closure

  • Reduced physical impact to sensitive areas
  • Reduced duration of impact
  • Increased time for stream to stabilize

Partial Road Closure

  • Increased physical impact to sensitive areas
  • Additional mitigation required
  • Increase duration of impact
  • Reduced time for stream to stabilize

6

slide-7
SLIDE 7

Duration for Culvert Construction

Full Road Closure = 7 days

7

Partial Road Closure = 6 weeks

slide-8
SLIDE 8

Traffic Impacts Full Road Closure

  • High impact/short duration
  • Impacts commuter traffic
  • Adds time depending on detour route taken
  • Impacts residents along ELSP & detour routes
  • Greater vehicle and construction safety

Partial Road Closure

  • High impact/significantly longer duration
  • Impacts commuter traffic
  • Adds time due to construction queue delay
  • Reduced vehicle and construction safety

8

slide-9
SLIDE 9

Traffic Impacts

9

  • 2017 average daily traffic for

ELSP road section = 8,500.

  • 6000 trips diverted to

proposed detour route.

slide-10
SLIDE 10

Detour Route Options

SE 24th Way ex ADT 1270 Snake Hill ex ADT 4790 SE 43rd Way ex ADT 17270

10

1 2 3 X 1 2 3

slide-11
SLIDE 11

Cost Comparison

11

*All costs provided are at 30% estimate level

Project Financial Summary Option 1: Full Road Closure Estimate Option 2: Partial Road Closure Estimate Design $381,189 $381,189 Construction Contract* $1,050,000 $1,340,000 Construction Inspection* $150,000 $200,000 Management Reserve* $105,000 $134,000 Expense Sub-total $1,686,189 $2,055,189 Grants $821,906 $821,906

Total cost to City after grant use $864,283 $1,233,283

slide-12
SLIDE 12

Additional Considerations

Ways to shorten time of road closures:

─ Provide monetary incentives to contractor for finishing early ─ Allow night-time work, weekend work or extended hours 12

slide-13
SLIDE 13

Recommendation

It is recommended that a full road closure be approved.

13