Zackuse Creek Fish Passage and Stream Restoration Project PUBLIC - - PowerPoint PPT Presentation

zackuse creek fish passage and stream restoration project
SMART_READER_LITE
LIVE PREVIEW

Zackuse Creek Fish Passage and Stream Restoration Project PUBLIC - - PowerPoint PPT Presentation

Zackuse Creek Fish Passage and Stream Restoration Project PUBLIC OPEN HOUSE NO. 2 JANUARY 10, 2018 Project Partners City of Sammamish King County Kokanee Work Group Snoqualmie Tribe Trout Unlimited Private Property


slide-1
SLIDE 1

Zackuse Creek Fish Passage and Stream Restoration Project

PUBLIC OPEN HOUSE NO. 2 JANUARY 10, 2018

slide-2
SLIDE 2

Project Partners

  • City of Sammamish
  • King County
  • Kokanee Work Group
  • Snoqualmie Tribe
  • Trout Unlimited
  • Private Property Owners
slide-3
SLIDE 3

Agenda

  • Project Overview and Status
  • East Lake Sammamish Parkway Culvert Design
  • Stream Restoration Design
  • King County Trail and Shore Lane Culvert Design
  • Project Schedule
slide-4
SLIDE 4

Project Overview and Status

  • Replace existing culvert on ELSP with fish passable box culvert
  • Restore and realign degraded stream channel upstream of ELSP
  • 90% design completed
  • Some permits have been issued, waiting for others
  • Finalizing Interlocal Agreement with King County
  • Construction start June 2018
slide-5
SLIDE 5

Project Layout

slide-6
SLIDE 6

East Lake Sammamish Parkway Culvert Design

  • Precast concrete culvert (12‐ft span x 55‐ft long)
  • Sewer and water temporary bypass and relocate
  • Finalize geotechnical analysis
  • Analysis of best construction method
  • Permitting
slide-7
SLIDE 7

Zackuse Creek at ELSP

slide-8
SLIDE 8

ELSP Culvert Profile

slide-9
SLIDE 9

Construction Impacts East Lake Sammamish Parkway Culvert

  • Full road closure East Lake Sammamish Parkway (max 2 week)
  • Vertical shoring – impact driving noise and vibration
  • Stream bypassing/dewatering – pump and generator noise
  • Sewer and water temporary bypass
  • Construction staging
  • Construction trailer/porta potty
  • Typical construction noise
slide-10
SLIDE 10

Snake Hill (212th Way) SE 24th Way SE 43rd Way

10

1 2 3 X 1 2 3

Detour Route Options

slide-11
SLIDE 11

Example of Culvert Head and Wing Wall

slide-12
SLIDE 12

Example of Weathering Steel Guardrail

slide-13
SLIDE 13

Stream Restoration Design

  • Design a stream channel to support spawning habitat
  • Step, pool, riffle design selected
  • Inclusion of additional large woody debris to address Tribes

comments

  • Plantings!!!!
slide-14
SLIDE 14

Existing Stream

slide-15
SLIDE 15

Stream Channel Grading Plan

slide-16
SLIDE 16

Step, Pool, Riffle Section

slide-17
SLIDE 17

Construction Impacts Stream Restoration

  • Construction staging
  • Materials hauling
  • Typical construction noise
slide-18
SLIDE 18

Staging Plan

slide-19
SLIDE 19

King County Trail and Shore Lane Culverts

  • Interlocal Agreement with King County
  • King County design
  • City manages construction
  • King County reimburse City of KC Trail and Shore Lane culverts
slide-20
SLIDE 20

King County Trail Culvert

slide-21
SLIDE 21

Shore Lane Culvert

slide-22
SLIDE 22

Shore Lane and Trail Culverts Plan View

slide-23
SLIDE 23

Shore Lane and Trail Culvert Profile

slide-24
SLIDE 24

Construction Impacts Trail and Shore Lane Culverts

  • KC Trail closed during construction
  • Shore Lane driveway at culvert temporarily closed
  • Construction vehicles on KC trail and Shore Lane
  • Stream bypassing/dewatering – pump and generator noise
  • Sewer, water, gas temporary bypass, temp. interruptions
  • Construction staging
  • Typical construction noise
slide-25
SLIDE 25

Construction Staging

slide-26
SLIDE 26

Construction Staging

slide-27
SLIDE 27

Project Schedule

Feb 22 100% Design Complete, Project Bid Advertisement March 15 Contractor Bid Opening April 3 City Council Bid Award, ILA approved June 4 Construction starts July 1‐Sept 30 Culvert construction (Fish Window) July 5‐July 19 Target for full road closure of ELSP Sep 30 Project Substantially Completed

slide-28
SLIDE 28

Questions