zackuse creek fish passage and stream restoration project
play

Zackuse Creek Fish Passage and Stream Restoration Project PUBLIC - PowerPoint PPT Presentation

Zackuse Creek Fish Passage and Stream Restoration Project PUBLIC OPEN HOUSE NO. 2 JANUARY 10, 2018 Project Partners City of Sammamish King County Kokanee Work Group Snoqualmie Tribe Trout Unlimited Private Property


  1. Zackuse Creek Fish Passage and Stream Restoration Project PUBLIC OPEN HOUSE NO. 2 JANUARY 10, 2018

  2. Project Partners  City of Sammamish  King County  Kokanee Work Group  Snoqualmie Tribe  Trout Unlimited  Private Property Owners

  3. Agenda  Project Overview and Status  East Lake Sammamish Parkway Culvert Design  Stream Restoration Design  King County Trail and Shore Lane Culvert Design  Project Schedule

  4. Project Overview and Status  Replace existing culvert on ELSP with fish passable box culvert  Restore and realign degraded stream channel upstream of ELSP  90% design completed  Some permits have been issued, waiting for others  Finalizing Interlocal Agreement with King County  Construction start June 2018

  5. Project Layout

  6. East Lake Sammamish Parkway Culvert Design  Precast concrete culvert (12‐ft span x 55‐ft long)  Sewer and water temporary bypass and relocate  Finalize geotechnical analysis  Analysis of best construction method  Permitting

  7. Zackuse Creek at ELSP

  8. ELSP Culvert Profile

  9. Construction Impacts East Lake Sammamish Parkway Culvert  Full road closure East Lake Sammamish Parkway (max 2 week)  Vertical shoring – impact driving noise and vibration  Stream bypassing/dewatering – pump and generator noise  Sewer and water temporary bypass  Construction staging  Construction trailer/porta potty  Typical construction noise

  10. Detour Route Options Snake Hill (212 th Way) X 1 SE 24 th Way 2 SE 43 rd Way 3 2 1 3 10

  11. Example of Culvert Head and Wing Wall

  12. Example of Weathering Steel Guardrail

  13. Stream Restoration Design  Design a stream channel to support spawning habitat  Step, pool, riffle design selected  Inclusion of additional large woody debris to address Tribes comments  Plantings!!!!

  14. Existing Stream

  15. Stream Channel Grading Plan

  16. Step, Pool, Riffle Section

  17. Construction Impacts Stream Restoration  Construction staging  Materials hauling  Typical construction noise

  18. Staging Plan

  19. King County Trail and Shore Lane Culverts  Interlocal Agreement with King County  King County design  City manages construction  King County reimburse City of KC Trail and Shore Lane culverts

  20. King County Trail Culvert

  21. Shore Lane Culvert

  22. Shore Lane and Trail Culverts Plan View

  23. Shore Lane and Trail Culvert Profile

  24. Construction Impacts Trail and Shore Lane Culverts  KC Trail closed during construction  Shore Lane driveway at culvert temporarily closed  Construction vehicles on KC trail and Shore Lane  Stream bypassing/dewatering – pump and generator noise  Sewer, water, gas temporary bypass, temp. interruptions  Construction staging  Typical construction noise

  25. Construction Staging

  26. Construction Staging

  27. Project Schedule Feb 22 100% Design Complete, Project Bid Advertisement March 15 Contractor Bid Opening April 3 City Council Bid Award, ILA approved June 4 Construction starts July 1‐Sept 30 Culvert construction (Fish Window) July 5‐July 19 Target for full road closure of ELSP Sep 30 Project Substantially Completed

  28. Questions

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend