Potter Valley Project
Fish Passage Options
1
Ad Hoc Committee Meeting | October 2, 2019 Appendix D | Fish Passage Presentation to Ad Hoc
Potter Valley Project 1 Fish Passage Options 2 Scott Dam 3 Cape - - PowerPoint PPT Presentation
Appendix D | Fish Passage Presentation to Ad Hoc Ad Hoc Committee Meeting | October 2, 2019 Potter Valley Project 1 Fish Passage Options 2 Scott Dam 3 Cape Horn Dam 4 Fish Passage Working Group Charge: The Fish Passage Working Group
Fish Passage Options
1
Ad Hoc Committee Meeting | October 2, 2019 Appendix D | Fish Passage Presentation to Ad Hoc
2
3
4
´ Charge: The Fish Passage Working Group (FPWG) is developing information and recommendations on fish passage for the
Potter Valley Project Ad Hoc Committee. The FPWG is composed of Potter Valley Project stakeholders charged with
identifying a prioritized list of conceptual-level passage options that would meet three fish passage objectives for targeted anadromous fish species beyond Cape Horn and Scott
dams, located within the upper mainstem Eel River, California. If these fish passage objectives are
achieved, recommended fish passage options will promote the recovery and long-term viability of currently depressed fish populations in the Eel River. The FPWG strives to identify fish passage
§ Viable Fish Population (VFP)Concept: abundance, productivity, spatial structure, and diversity.
§ Access to sufficient habitat quantity and quality to complete essential life stages and promote long-term population viability. § Avoid exposing fish to low quality habitat that harbors introduced predatory fish species.
§ Safe, timely, reliable, and effective upstream and downstream passage. § Fish passage options that minimize stress, injury, delay and mortality ~ while maximizing efficiency.
5
This provided the “fish passage scorers” a defined concept for each passage option.
perspectives. 6
7
1 Fishway at
Existing Scott Dam Options
2 Trap &
Haul
3 Partial Scott
Dam Removal
4 Remove Scott
Dam and Modify Cape Horn Dam
Options
1. 1.1 1 Semi- Na Natural, Low- Gradient Bypass ss Ch Channel 1. 1.2 Original Me Mead & Hunt (M (M&H) Fish sh La Ladder 1. 1.3 Modified M&H Fish sh La Ladder 2. 2.1 Tr Trap & Ha Haul, Van Arsd sdale to Sc Scott Dam 2. 2.2 2 Trap & Ha Haul, at Sc Scott Da Dam 3. 3.1 Lo Lower Scott Da Dam to 80 80’ – Meet PVID demand and environmental flows 3. 3.2 Lower Scott Da Dam to 50’ – Retain accumulated sediment 4. 4.1 Re Remove Scott Da Dam and Modify Ca Cape Horn Dam 4. 4.2 Re Remove bot
Sc Scott Dam and Ca Cape Horn Dam 1) With Diversion (provides another baseline for flows and fish) 2) No Diversion
8
9
10
11
1.3 Modified M&H Fish Ladder:
migrating fish can use extended fish ladder/ exit gallery 1.2 M&H Fish Ladder:
12
13
2.1 - Trap at CHD Release at tributary 2.2 – Trap at SD Release in middle of reservoir
14
15
16
17
18
19 SCORING APPROACH ESSENTIALS ü Clearly define criteria parameters and option assumptions ü Score independently from other
ü Document range of scores ü Take detailed notes on assumptions, unknowns, and diverse perspectives
Fish Passage Scenarios & Options Table | Example
20
Link to Table
Scoring Key
(see Scoring Passage Matrix for complete parameter definitions)
21
22
23
Results: Averages and Ranges ~ Non-Biological (e.g., Ops and Engineering Feasibility)
24
Averages Ranges
25
´ Dam removal benefits all species and life stages evaluated. However, without other water supply options, may not satisfy two-basin solution. ´ Upstream passage options available for adult salmonids (juveniles?) and lamprey (with varying long-term biological viability), but success likely achievable. ´ Different perspectives on value of Scott Dam releases during dry season and associated water quality conditions downstream. ´ Downstream passage challenges for both salmonids and other species (lamprey) of interest à Likely most limiting factor for fish passage options that retain Scott Dam ´ Engineering passage with aging infrastructure may be major challenge. ´ Assumes Cape Horn Dam / Van Arsdale Fish Station meet NMFS/CDFW standards.
26
´ Integrate work with Water Supply Working Group ´ Issues requiring further investigation and/or additional expertise:
´Downstream passage options ´Non-biological factors ´Alternative flow schedules ´Cape Horn Dam conditions (e.g., flow Rx’s) ´Other non-passage factors described in report
27
´Flow Rx’s associated with desired water quality and habitat conditions downstream of Scott Dam ´Fish production and life cycle modeling ´Predatory fish suppression techniques ´Fish behavior / response to reservoir habitat conditions
28
29
30
31
Weir at entrance to a fishway (Nimbus Hatchery fish weir/ladder) 32
Surface Spill Bypass Example for Outmigration
(Wanapum Dam, Columbia River)
33
34
Upper Baker Lake Floating Surface Collector
35