workshop on addressing barriers to scaling up renewable
play

Workshop on Addressing Barriers to Scaling - Up Renewable Energy - PowerPoint PPT Presentation

Organised by Supported by Workshop on Addressing Barriers to Scaling - Up Renewable Energy Session 2: Theme Presentation On Issues in Scaling - Up of RE Deployment 9 May, 2017 Mumbai 1 Outline of the Theme Renewable Energy


  1. Organised by Supported by Workshop on “Addressing Barriers to Scaling - Up Renewable Energy” Session 2: Theme Presentation On “Issues in Scaling - Up of RE Deployment” 9 May, 2017 Mumbai 1

  2. Outline of the Theme Renewable Energy – Growth so far • • Renewable Energy – Capacity Addition Target • The Task Ahead • Objective of the workshop Key Issues for Deliberation • – Changing modalities of RE Procurement – Implementation of RPO – Project Financing – Project development – Evacuation Planning & Connectivity Issues – Addressing Variability Risk - Implementation of F&S, Ancillary services – Innovative technology options & support systems • Action plan for RE scale up 2

  3. Renewable Energy- Growth so far 57 GW CAGR- 19% Key Statistics and Drivers • Cumulative capacity of 57,260 MW of Grid connected RE ~10 GW installed as on April 2017 • Wind capacity has the lion’s share among RE technologies (around 56%) • RE capacity comprises 17.5% of total generation capacity of India • Current level of RE Penetration is only 7.5% but the RE Penetration expected to happen by 2022 is between 15% to 20%. 3

  4. Renewable Energy – Capacity Addition Target MNRE Target by 2022 Small Hydro Biomass • Targets 175 GW by 2022 6% 3% • Includes 100 GW from Solar, 60 GW Wind from Wind, 10 from Biomass & 5 34% GW from SHP • 90% of the targeted RE capacity Solar 57% addition planned from Wind and Solar source which are inherently variable in nature 410 GW CEA perspective plan for FY 2032 350 GW • CEA has projected RE capacity additions till 2036 250 GW • Transmission capacity planned commensurate with RE capacity addition of • 250 GW by 2026-27, • 350 GW by 2031-32, 2026-27 2031-32 2035-36 • 410 GW by 2035-36. Thermal Hydro Nuclear Total RE 4

  5. The Task Ahead Task appreciation & Gearing up • 175 GW by 2022 translates to 23 GW per annum of RE capacity addition over the coming years • Considering the past trend of capacity addition, the task ahead is challenging • Collaborative and concerted efforts need to be taken to achieve the targets set. • Challenges and issues faced by the sector to be resolved and clear roadmap to be set. • Short, medium and long term solutions to be discussed and implemented 5

  6. Objective of the Workshop The present workshop aims to identify the barriers to implement renewable • energy technologies in the Western Region and discuss policy, regulatory and technical issues, both at the Central and State level. To deliberate issues/problems being faced in implementing renewable energy projects Address gaps in the policy and regulatory framework at the State and Central level Identify challenges in scale-up of solar rooftop projects Frame a feasible plan of action 6

  7. Scaling Up RE Deployment - Key Issues for deliberation Changing RE Procurement models Implementation of RPO Evacuation Planning & Connectivity Issues Project Financing Project development Addressing Variability Risk - Implementation of F&S, Ancillary services Support system for Emerging Technologies 7

  8. Changing RE Procurement models RE Off-take options in India Competitive bidding Vs FIT FIT has worked well in the RE sector. However ERC  determined FITs to be benchmark for reverse auctions. Buyers  Competitive bidding in RE introduced in 2012 which has resulted in low Solar & Wind tariff discovery  Recently held Competitive bidding in solar & wind has resulted in tariff plummeting to 3.33 Rs/Unit and 3.46 Distribution Open Access Rs/Unit respectively. Companies Consumers  How can sustainability of Competitive off-take be ensured? Alternate Market Mechanism (REC) Through FiT 3 rd Party Open  REC inventory piling up owing to lack of adequate RPO Route Access monitoring & enforcement  Uncertainty prevails on future REC prices and APPC Lenders are cautious while lending to REC projects  Competitive Captive Bidding Route Generating Plants OA/Captive Route  OA charges tend to be prohibitive – affecting the viability REC route of such options  Captive Rules getting amended RE captive transactions under scanner in various States  and Discoms denying captive transactions? 8

  9. Implementation of RPO Renewable Purchase Obligation RPO Regulations formulated by almost all SERCs   Despite Regulations, only few States comply fully  Not may states have robust institutional mechanisms for monitoring & verification of RPO Mechanism lacks stringent enforcement   In case of non-compliance, penal provisions are unclear Section 86(1): The State Commission shall RPO & Tariff Policy 2016 discharge the following functions, namely:  RPO trajectory to be fixed such that RE to reach 17% in  (e) promote cogeneration and the total energy mix by 2022 including minimum 8% generation of electricity from from Solar renewable sources of energy by SERCs are yet to revise RPO target on the lines of tariff  providing suitable measures for policy connectivity with the grid and sale of RPO for OA/Captive consumers electricity to any person, and also  RPO enforcement on Captive and OA consumers – and specify, for purchase of electricity from need for RPO repository – few States initiated process such sources, a percentage of the total  Web based tool required so as to Monitor, Record & consumption of electricity in the area Report RPO compliance status of OEs to SERC of a distribution licensee; 9

  10. RE Evacuation Planning & Connectivity Issues Issues for Discussion  Need for devising separate planning standards for RE Aligning grid planning for RE evacuation & the required institutional arrangement?  Standardization of interconnection procedures at national Uniform Interconnection level at similar voltage levels? Process  Uniform and just model for sharing the responsibility and Funding for cost of evacuation infrastructure for RE generators? Infrastructure  Mobilizing fund for setting up transmission infrastructure; Provisions for encouraging private participation Technical Standards for grid integration  Applicability of new technical standards by CEA irrespective of age, make & size – CEA to provide adequate clarity Renewable Energy Management Centers Roles and responsibilities & Operational protocol for  REMCs to be defined ; State Level Vs Regional level 10

  11. Project Financing & Fund Mobilization Issues for Discussion Debt tenure Unavailability of longer tenure debt  Interest Rate  High interest rate environment in India Non-recourse debt Debt is not strictly non-recourse  Innovative Funding  Allocation of funds from the NCEF to meet Mechanism critical viability gaps Total Investment requirement of ~7 Lakh Cr by 2022 (estd) Priority sector lending status for RE Financing  Capacity Addition in GW& Investment in INR Lakh'Crs  Earmarking at least 20% for RE by Banks & FIs 1.50 30.00 2.00 1.40 1.39 1.27 1.16 Lakh Crore 20.00 GW 17.50 1.00 17.00 15.74 16.00 15.00 10.00 4.70 5.30 6.00 6.70 6.33 Avenues for encouraging retail investors in  0.00 0.00 the sector – SMEs interested in setting up 2017-18 2018-19 2019-20 2020-21 2021-22 Achsentitel captive RE to be supported with interest rebates Wind Small Hydro Solar Biomass Investment (in INR 1000 Crs) 11

  12. Project development Clearances Site Resource Land Infrastructure and Identification Assessment Acquisition Development Permissions Identification Land Consent to Infra Transport Development of Potential Conversion Establish and and Site of Land Bank Sites Issues Operate Development Key Issues Non Uniform Socio-Political Hoarding of Monitoring/ State Specific Clearance Issues Sites Data Analysis Practices across States Number of Socio- Lack of Site Sites/MW Load Analysis RoW Economic and and Grid Installed Enviro Impacts Connectivity Issues for Discussion  Single window clearance  Preparation of Land Bank at State level Availability of Resources Potential Map/Atlas  Clarity on cost sharing of setting up of grid infra-  battery limit of developers Addressing RoW issues & compensation  12

  13. Addressing Variability Risk - Implementation of F&S, Ancillary services Issues for Discussion Implementation of F&S Grid Stability becomes a major issue especially when  there is high penetration of Renewable Energy Ancillary services  Inter-State F&S Regulations in place - notified by CERC Why RE Forecasting & Scheduling? FOR has published model state level framework for  Forecasting and Scheduling. However, • Limited ability to back-down thermal implementation of such mechanism at state level generation (limitation due to technical would be quite challenging 1 minimum)  Most states does not have a operational ABT/DSM • Low availability of hydro power for balancing mechanism in place, which would be prerequisite for (low share of pumped storage) 2 implementation of DSM Development of ancillary market can be used by  • Low availability of gas-fired thermal power system operator as one of the tool for grid (low availability, high cost) 3 management. • Lack of regional balancing (lack of inter-State,  Effective Policy and Regulatory framework are inter-regional corridor) required for developing ancillary market in the 4 Country. 13

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend