Guernsey Renewable Energy Feasibility Report in co-operation with - - PowerPoint PPT Presentation

guernsey renewable energy feasibility report
SMART_READER_LITE
LIVE PREVIEW

Guernsey Renewable Energy Feasibility Report in co-operation with - - PowerPoint PPT Presentation

Guernsey Renewable Energy Feasibility Report in co-operation with the Guernsey Renewable Energy Team Introduction About us University of Exeter Final year, BSc Renewable Energy students Field trip module The need for renewable energy


slide-1
SLIDE 1

Guernsey Renewable Energy Feasibility Report

in co-operation with the Guernsey Renewable Energy Team

slide-2
SLIDE 2

Introduction

slide-3
SLIDE 3

About us

  • University of Exeter
  • Final year, BSc Renewable Energy students
  • Field trip module
slide-4
SLIDE 4

The need for renewable energy

  • Energy security
  • Human-caused global warming – sustainability
  • Financial

– Rising fossil fuel costs – Returns on investment

  • A new industry - diversity
slide-5
SLIDE 5

Project Scope

Focus on the strategic implementation of

  • ffshore wind, wave and tidal energy; to develop

an energy management strategy for Guernsey.

  • Commerce and Employment
  • Renewable Energy Team

(RET)

slide-6
SLIDE 6

Overview

Offshore wind Tidal Wave Onshore Infrastructure Public consultation Scenarios

slide-7
SLIDE 7

Overview

slide-8
SLIDE 8

Current Demand

  • 85 MW maximum demand
  • 35% increase in 10 years
  • 23 MW baseload
  • 2 MW increase in 5 years
  • Met by imported electricity and on island

generation

1 of 2

slide-9
SLIDE 9

Current Demand

Source: Guernsey Electricity

2 of 2

slide-10
SLIDE 10

Imported electricity

  • Guaranteed 16 MW
  • Can draw up to 55 MW if available –

depending on Jersey’s demand

slide-11
SLIDE 11

On Island Generation

  • 115 MW capacity
  • Five 2-stroke slow

speed diesel generators

  • Three gas turbines
slide-12
SLIDE 12

Current Cost

  • 400 GWh consumed in 2010/11
  • Average cost to consumers of 12.33p/unit

(kWh)

  • T
  • tal annual cost to Guernsey consumers of

£48.5m

slide-13
SLIDE 13

Technologies

slide-14
SLIDE 14

Constraints

  • Environmental

– Sea mammals – Fish – Flora and fauna

  • Fishing
  • Seabed/bathymetry
  • Visual impacts
  • Shipping
slide-15
SLIDE 15

Constraints - Shipping

slide-16
SLIDE 16

Constraints - Geology

slide-17
SLIDE 17

Offshore Wind

slide-18
SLIDE 18

Introduction

  • Feasibility study review
  • Further wind farm sites located

– 30MW capacity – 300MW capacity

slide-19
SLIDE 19

Feasibility Review

  • Identification of two wind farm sites:

– 12MW, 4 turbines (too small) – 30MW, 10 turbines

  • 30MW site could be developed in conjunction with a French
  • ffshore wind farm
  • Visual impact is a key issue
  • Recommendations

– Reliable wind speed estimates using met-mast at Chouet combined with airport wind speed data

slide-20
SLIDE 20

Source: Department of Commerce and Employment

slide-21
SLIDE 21

Wind Resource

  • Wind resource analysis

– 8.5m/s at 80m (Vestas V90 hub height) at Chouet – Weibull distribution applied

50 100 150 200 250 300 5 10 15 20 25 30 Annual Duration (hrs) Wind Speed (m/s)

80m Chouet Wind Speed Distribution

slide-22
SLIDE 22

Site Selection - Further Sites

  • Constraints considered

– Available resource – Distance from the shore – Geology – Bathymetry – Environmental factors

  • Potential wind farm sites

– North Herm 30 MW – North Guernsey 30 MW – North East Guernsey 300 MW

  • Energy yield

– 30 MW generates 100GWh/year (25%) – 300 MW generates 1200GWh/year (300%)

200 400 600 800 1000 1200 1400

Energy Yield (GWh/yr)

30MW Site 300MW Site

Predicted Energy Yields for 30MW and 300MW Sites

slide-23
SLIDE 23

Image for the proposed 30MW array off the west coast by Guernsey Press (15th February 2012)

slide-24
SLIDE 24

Photo Montage

Realistic image for 10 Vestas V90 turbines from 3km distance

slide-25
SLIDE 25

Turbine Selection and Foundation

  • Near shore 30MW sites

– 3MW ‘V90’ Vestas turbine

  • Far from shore 300MW site

– 5MW ‘5M’ RePower turbine – Maximises energy yield – Minimises cost per MW installed

  • Foundations

– Geology – Water depth – Monopile, jacket, tripod or concrete gravity-based – Geotechnical and hydrodynamic loading surveys

Source: renews.biz 2012

slide-26
SLIDE 26

Infrastructure

  • Offshore substation

– Not required for the 30MW wind farms – Required for 300MW wind farm – Costly electrical installation – Considerable power conditioning and protection equipment

  • Subsea cables

– Requires detailed seabed study

  • Operation and Maintenance

– Servicing – Ports

slide-27
SLIDE 27

Wave Energy

slide-28
SLIDE 28

Wave Resource

Wave height (m)

slide-29
SLIDE 29

Constraints - Bathymetry

slide-30
SLIDE 30

Near-shore Wave Modelling

Significant Wave Height (m) Using predominant sea state of 1.5m Hs and 5.5 s Period

slide-31
SLIDE 31

Wave Resource

Guernsey Sea State Probability Period (s) Significant Wave Height(m) 3 - 5 4 - 5 5 - 6 6 - 7 7 - 8 8 - 9 9 - 10 10 - 11 0 - 1 1.2 3.4 3.9 4.4 4.9 3.6 1.7 0.8 1 - 2 0.1 5.5 10.8 9.7 8.2 6.1 4.9 2.5 2 - 3 2.3 3.7 4.0 3.1 2.5 2.0 3 - 4 0.2 0.6 1.5 1.0 1.0 4 - 5 0.1 0.9 1.0 0.2 5 - 6 0.1 0.2 0.0 6 - 7 0.1 Wave Power (kW/m) Period (s) Significant Wave Height(m) 3.5 4.5 5.5 6.5 7.5 8.5 9.5 10.5 0.5 0.0 1.1 1.4 1.6 1.9 2.1 2.4 2.6 1.5 7.9 10.1 12.4 14.6 16.9 19.1 21.4 23.6 2.5 34.4 40.6 46.9 53.1 59.4 65.6 1.6 16.6 19.2 21.8 24.3 26.9 3.5 91.9 104.1 116.4 128.6 4.5 172.1 192.4 212.6 5.5 317.6

slide-32
SLIDE 32

Pelamis

slide-33
SLIDE 33

Wave Resource

Annual Energy Yield (kWh) Period (s) Significant Wave Height(m) 3 - 5 4 - 5 5 - 6 6 - 7 7 - 8 8 - 9 9 - 10 10 - 11 0 - 1 4823 6956 8159 5326 2145 730 1 - 2 21584 84760 98292 85128 57865 38559 15887 2 - 3 44874 92197 99575 68665 46127 31095 3 - 4 9545 25138 57789 30142 25179 4 - 5 3260 49898 46742 9168 5 - 6 5083 13370 2245 6 - 7 6526 Annual Yield (GWh) 41 Pelamis Power Matrix (kW) Period (s) Significant Wave Height(m) 3 - 5 4 - 5 5 - 6 6 - 7 7 - 8 8 - 9 9 - 10 10 - 11 0 - 1 14.0 18.0 19.0 17.0 14.0 11.0 1 - 2 44.5 90.0 115.5 119.0 108.0 90.0 73.0 2 - 3 109.0 220.0 282.0 285.0 254.0 211.0 178.0 3 - 4 408.0 489.0 477.0 426.0 355.0 300.0 4 - 5 544.0 684.0 668.0 616.0 515.0 427.0 5 - 6 750.0 750.0 744.0 685.0 575.0 6 - 7 750.0 750.0 750.0 743.0

Rated Capacity - 750 kW

  • No. of Devices - 37

Installed Capacity ~ 30MW Device Yield – 0.1 GWh p.a Array Yield – 41 GWh p.a

slide-34
SLIDE 34

Site Location

slide-35
SLIDE 35

Site Constraints

slide-36
SLIDE 36

Tidal

slide-37
SLIDE 37

Tidal Stream Technology

  • T

echnology types and industry front-runners

SeaGen (1.2MW,2MW) Open Hydro (2.2 MW) Hammerfest (1MW)

slide-38
SLIDE 38

Guernsey - Site Selection Criteria

Considerations and Constraints

  • Tidal resource (at least 2m/s spring tide)
  • Water depth (up to 50m)
  • Bathymetry (Seabed profile)
  • Environmental
  • Safety and navigation (shipping routes, etc.)
slide-39
SLIDE 39

GIS mapping - Guernsey

slide-40
SLIDE 40

Site Assessment - Methodology

  • Limited data available
  • Tidal profile for local area
  • Probability graph

derivation

  • Application of SeaGen

1.2 MW device power curve

slide-41
SLIDE 41

Site Assessment - Findings

3 nautical mile radius Big Russell (6km sq, < 40m depth)

  • Feasible potential 2 x 100 MW arrays (200 MW)
  • 83 x SeaGen 1.2 MW devices
  • Energy Production: 566 GWh/year (~140% of Guernsey’s

annual demand)

slide-42
SLIDE 42

Site Assessment - Findings

3 nautical mile radius South East of Sark

  • Feasible potential 2 x 200 MW arrays (400 MW)
  • 166 x SeaGen 1.2MW devices
  • Energy Production: 750 GWh/year (~190% of Guernsey’s

annual demand)

slide-43
SLIDE 43

Site Assessment - Findings

12 nautical mile radius South East of Sark

  • Hammerfest tech applicable (up to 70m depth)
slide-44
SLIDE 44

Energy (GWh/year)

100 200 300 400 500 600 700 800 900 0.5 1 1.5 2 2.5 3 3.5 4 4.5

Energy (GWh/year) Velocity Bin (m/s)

Annual Available Energy Big Russell Sark

0.0 1000.0 2000.0 3000.0 4000.0 5000.0 6000.0 Available Big Russell Production Big Russell Available Sark Production Sark 5759.9 565.8 5895.3 749.5 Energy (GWh/yr)

Energy Yield

slide-45
SLIDE 45
  • Lack of case studies to give accurate cost indication
  • R&D projects (£10m/MW)
  • T

echnology commercially available by 2014

  • Cost reductions estimated at 40% by 2040
  • CAPEX: ~£3.5m/MW in 2020
  • Cost of 30MW installation: £106m
  • Cost of 200MW installation: £712m
  • O&M costs: 2.1% of CAPEX

Tidal Stream Project Costs

slide-46
SLIDE 46

R&D and testing opportunity

  • R&D site used for commercial purposes in the future
  • Joint projects with other islands
  • Control over site licensing and leasing – attractive to

developers

  • Engage with selected developer(s) to speed up the

process

  • Introduction of the concept to the public
  • Key barrier – lack of incentive/subsidy
slide-47
SLIDE 47

Conclusions

  • Substantial tidal stream resource
  • Potential to generate >100% of Guernsey’s

demand

  • Further investigation into cost required
  • Early preparation will make process smoother
slide-48
SLIDE 48

Infrastructure

slide-49
SLIDE 49

Infrastructure

  • Electrical Grid Infrastructure
  • Port Infrastructure
  • Energy Storage
  • Transport Infrastructure
slide-50
SLIDE 50

Electrical Grid Infrastructure

  • Current case

– Capable and expandable network – Plans to improve and increase 33kV grid – Second interconnector discussions

slide-51
SLIDE 51

Electrical Grid Infrastructure

  • Base-load scenario

– 12.5MW maximum from renewable sources – GEL modelling up to 30MW – No large infrastructure changes required

15 17 19 21 23 25 27 29

2006 2008 2010 2012 2014 2016 2018 2020 Power (MW)

slide-52
SLIDE 52

Electrical Grid Infrastructure

  • Export scenario

– Second interconnector required – Grid strengthening if power comes onto the island – Further modelling and consultation with GEL

slide-53
SLIDE 53

Port Infrastructure

  • St Peter Port Harbour & St Sampson’s Harbour
slide-54
SLIDE 54

Port Infrastructure

  • Harbour requirements

– Mooring and refuelling for vessels

  • Surveying
  • Foundation Installation
  • Device Installation
  • Operations & Maintenance

– Storage space for technologies

slide-55
SLIDE 55

Port Infrastructure

  • Base-load scenario

– Too costly to expand at this level – Large vessels: use French harbours e.g., Cherbourg – Smaller vessels: use Guernsey harbours

slide-56
SLIDE 56

Port Infrastructure

  • Export scenario

– Use French harbours or – Include marine renewables in harbour master plan – Costly but part of overall master plan

slide-57
SLIDE 57

Energy Storage

CAES u/g CAES a/g Pumped Hydro CES Pb-acid 50 100 150 200 250 300 350 400 450 500 500 1000 1500 2000 2500 Cost (£/kWh) Capital Cost (£/kW)

(A. Evans, 2012)

Note: Size of circle represents the storage capacity of given technology

slide-58
SLIDE 58

Transport Infrastructure

  • Electrification of Transport

– Indirect impact – Increase demand on network – GEL models consider possibility – Energy storage provision

slide-59
SLIDE 59

Conclusion

  • Base-load possible with current plans
  • Export requires longer term plans
  • Keep open communication between

stakeholders

slide-60
SLIDE 60

Public Consultation

slide-61
SLIDE 61

Stakeholders

  • Public
  • Sustainable Guernsey
  • Fishermen
  • Local RE companies
  • Tourist industry
  • Harbourmaster
  • Local businesses
  • Energy utilities
slide-62
SLIDE 62

Education – Schools

  • Curriculum – review
  • Energy
  • Questionnaire
  • T

eaching aids

  • Awareness Program

Source: marcus-povey.co.uk

slide-63
SLIDE 63

Raising Awareness

  • Government
  • Planet Guernsey

– Towards A Sustainable Future – Riding The Storm

  • Role of employers – public and private
  • Training
slide-64
SLIDE 64

Recommendations

  • Planned
  • Level of engagement
  • Target specific groups
  • Phased approach
  • Questionnaire
slide-65
SLIDE 65

Scenarios

slide-66
SLIDE 66

Scenarios

  • 3 Scenarios:
  • 1. No renewables
  • 2. Baseload
  • 3. Export
slide-67
SLIDE 67

Scenario 1- Introduction

  • No renewables
  • Continuing reliance on imported electricity

and on island diesel generation

  • Rising demand
slide-68
SLIDE 68

Scenario 1 – Assumptions

  • Cost to consumer rises 5.5%/year
  • Electricity demand rises at 0.4%/year
slide-69
SLIDE 69

Scenario 1 – Conclusions

  • On island generation costs rise as oil prices

rise

  • Import costs to rise
  • Electricity supply therefore likely to become

substantially more costly.

  • Reliant on France
  • Does nothing to tackle emissions

1 of 2

slide-70
SLIDE 70

Scenario 1 – Conclusions

2 of 2

slide-71
SLIDE 71

Scenario 2 - Introduction

  • Meets Guernsey’s baseload with marine

renewables only

  • No access to French or UK subsidy
  • Tidal or offshore wind
slide-72
SLIDE 72

Scenario 2 - Projections

  • Baseload demand increased 4MW over last

ten years

  • Tidal stream capital cost £3.6m/MW by 2020

and £3.3m/MW by 2030

  • Offshore wind capital cost £2.9m/MW

currently

slide-73
SLIDE 73

Scenario 2 - Recommendations

  • Substantial financial undertaking will require

initial subsidy.

  • Cable contract until 2023 means a planned,

phased approach should be considered

  • Energy storage and balancing options greatly

affect viability and need to be considered.

  • Costs still uncertain
slide-74
SLIDE 74

Scenario 3 - Introduction

  • Based on the assumption that the electricity

will be predominantly exported.

  • UK and France primary options
  • Extensive legal challenges
  • Challenging to model and assess
slide-75
SLIDE 75

Scenario 3 – Export Options

  • UK
  • France

Can’t access either subsidy yet but discussions have been started

Technology Subsidy Feasibility Tidal 5 ROCs (~£200/MWh) 2020-2025 Offshore Wind 2 ROCs (~£80/MWh) Currently Wave 5 ROCs (~£200/MWh) 2030-2050 Technology Subsidy Feasibility Tidal €150/MWh (~£120/MWh) Not currently Offshore Wind €120/MWh (~£100/MWh Currently Wave €150/MWh (~£120/MWh) Not currently

slide-76
SLIDE 76

Scenario 3 - Capacity

  • 1GW total, producing ~ 2700GWh/year

(almost 7x Guernsey’s current annual demand)

Technology Capacity Annual Yield

  • No. of sites

Tidal 60MW 1130GWh 2 Offshore Wind 390MW 1500GWh 4 Wave 28MW 40GWh 1

slide-77
SLIDE 77

Scenario 3 – Conclusions

  • Export to the UK most attractive currently,

this could change

  • Infrastructure considerations
  • Legal and commercial research
  • Significant barriers restricting feasibility
slide-78
SLIDE 78

Conclusions

  • The non-financial advantages need to be fully

considered.

  • ‘No renewables’ leaves Guernsey vulnerable of

significant energy cost rises

  • A renewables programme with a mix of self-

use and export is most attractive yet needs access to appropriate subsidies

  • Just meeting baseload is currently most viable
slide-79
SLIDE 79

Conclusions

slide-80
SLIDE 80

Offshore wind

  • Good wind resource
  • 12MW too small, 30MW and 300MW potentially

feasible

  • Visual impact is a key concern for near-shore sites
  • Detailed environmental studies at chosen site
  • 1-2 year wind speed data collection at Chouet met-

mast

  • Obtain aviation, radar and communications data
  • Detailed cost analysis
slide-81
SLIDE 81

Wave

  • Early analysis – significant resource
  • Further research required

– Wave buoys – Radar wave monitoring

  • No complete wave energy converter solution
  • Costs still largely unknown
slide-82
SLIDE 82

Tidal

  • Very promising tidal stream resource
  • T

wo sites in 3nm radius could generate >100% of Guernsey demand

  • Costs still uncertain
  • Potential for R&D
  • Streamline licensing system
  • Prepare groundwork now, ready for the future
slide-83
SLIDE 83

50 100 150 200 250 300 350 400 450 500 Current usage in Guernsey Estimated usgae in Guernsey in 2020 Realistic potential

  • ffshore wind

Realistic potential wave Realistic potential tidal Realistic potential total Energy (GWh)

Realistic potential for macro-marine renewable energy in Guernsey by 2020-2025

slide-84
SLIDE 84

Potential Impacts

Impacts arising from different phases in the project :

  • Energy security
  • Environmental
  • Visual impacts
  • Employment diversity
  • Potential export revenue
  • Kudos and satisfaction
slide-85
SLIDE 85

Acknowledgements

slide-86
SLIDE 86

Acknowledgements

  • Commerce and Employment
  • Environment Department
  • Guernsey Renewable Energy T

eam

  • Guernsey Electricity Ltd.
  • All those who assisted in meetings
  • Sea Fisheries – RIB tour
  • Digimap
  • Harbour Master
slide-87
SLIDE 87

Thank you and questions