workshop 3 workshop 3
play

Workshop 3 Workshop 3 Cost Estimating and Cost Estimating and - PowerPoint PPT Presentation

SWVP-0719 Workshop 3 Workshop 3 Cost Estimating and Cost Estimating and Financial Assurance Financial Assurance SWVP-028586 Reviews financial mechanism for Hal Hong Financial Administrator adequacy and completeness Communicates with


  1. SWVP-0719 Workshop 3 Workshop 3 Cost Estimating and Cost Estimating and Financial Assurance Financial Assurance SWVP-028586

  2. Reviews financial mechanism for Hal Hong Financial Administrator adequacy and completeness Communicates with Project Manager Groundwater Section financial/TSU/applicant Reviews/approves cost estimate Technical Support Unit Review detail and adequacy Groundwater Section OR Expedited Consultant A.R.S. § 49-243(N) requires a demonstration of financial capability or competence before the Department issues the permit. SWVP-028587

  3. Rules & Regulations • Arizona Administrative Code (A.A.C.) Title 18, Chapter 9 http://www.azsos.gov/public_services/Title_18/18_table.htm • Arizona Revised Statutes (A.R.S.) Title 49, Chapter 2, Article 3 http://www.azleg.state.az.us/ArizonaRevisedStatutes.asp?Title=49 SWVP-028588

  4. The Beginning… • Individual APPs require closure and post- closure cost estimates per A.A.C. R18-9- A201(B)(5). • The closure and post-closure plans (R18-9- A202[A][10])must be signed and sealed by an Arizona-registered P.E. per BTR (§ 32- 125 and R4-30-304). • The costs , based upon the plans, must be derived by an engineer, controller, or accountant per R18-9-A201(B)(5)(a). SWVP-028589

  5. What to include in the plan Example: WWTPs • Capital costs (new plants only) • One year of O&M costs (new plants only) • Associated labor, equipment, materials • Documentation preparation • Sampling • Remediation, if required • Demolition and disposal • Filling and grading • Mobilization/demobilization of equipment • Report preparation Note that all calculations for volume, time, etc. should be included in the plan and sealed by an Arizona-registered professional. SWVP-028590

  6. What to include in the plan Example: Impoundment • Design costs (for re-design after closure) • Sampling to determine horizontal and vertical extent of contamination, if present • Remediation costs • Confirmation sampling • Hauling and Disposal costs • Associated labor, equipment (mob/demob), materials • Backfilling and grading • Report preparation SWVP-028591

  7. Assigning Costs Industry Standard Costing • Publications/Databases (RSMeans) • Actual vendor quotes (competitive bids) • Operating history for similar facilities • Up-to-date software • Other appropriate sources SWVP-028592

  8. SWVP-028593 Example Capping

  9. SWVP-028594 Example Capping

  10. SWVP-028595 Example Excavation/Disposal

  11. SWVP-028596 Example Excavation/Disposal

  12. SWVP-028597 Example Excavation/Disposal

  13. SWVP-028598 Example Excavation/Disposal

  14. SWVP-028599 Example Excel Estimate

  15. SWVP-028600 Example Excel Estimate

  16. Financial Mechanisms R18-9-A203 Hal Hong reviews all mechanisms Demonstrate the financial capability to construct, operate, close, and ensure proper post-closure care of the facility in compliance with A.R.S. Title 49, Chapter 2, Article 3, conditions of the individual permit, and A.A.C. Articles 1 and 2 of Title 18, Chapter 9. SWVP-028601

  17. What you must do… 1. Submit a letter signed by the CFO stating the applicant is financially capable of meeting the costs described in R18-9- A201(B)(5). Note: state or federal agency, county, city, town, or other local governmental entity, submit a statement specifying the details of the financial arrangements used to meet the costs. SWVP-028602

  18. What you must do… 2. Submit information required for at least one of the financial assurance mechanisms under R18-9-A203(C). Include the following: • The selected mechanism or mechanisms; • The amount covered by each mechanism; • The institution or company that is responsible for each mechanism; and • Other details that demonstrate how the applicant is financially capable of meeting the costs described in R18-9-A201(B)(5). SWVP-028603

  19. Available Mechanisms 1. Financial test for self-assurance No consolidation of financial statement with parent or sibling company and include one of the following: • A ratio of total liabilities to net worth less than 2.0 and a ratio of current assets to current liabilities greater than 1.5; • A ratio of total liabilities to net worth less than 2.0 and a ratio of the sum of the net annual income plus depreciation, depletion, and amortization to total liabilities greater than 0.1; or • A ratio of the sum of net annual income plus depreciation, depletion, and amortization to total liabilities greater than 0.1 and a ratio of current assets to current liabilities greater than 1.5. SWVP-028604

  20. Formula Version of Self-assurance 1. A ratio of total liabilities to net worth less than 2.0 and a ratio of current assets to current liabilities greater than 1.5; Total Liabilities < 2.0 Net Worth Current Assets > 1.5 Current Liabilities SWVP-028605

  21. Formula Version of Self-assurance 2. A ratio of total liabilities to net worth less than 2.0 and a ratio of the sum of the net annual income plus depreciation, depletion, and amortization to total liabilities greater than 0.1; or Total Liabilities < 2.0 Net Worth Net Annual Income + Depreciation + Depletion+ Amortization > 0.1 Total Liabilities SWVP-028606

  22. Formula Version of Self-assurance 3. A ratio of the sum of net annual income plus depreciation, depletion, and amortization to total liabilities greater than 0.1 and a ratio of current assets to current liabilities greater than 1.5. Net Annual Income + Depreciation + Depletion+ Amortization > 0.1 Total Liabilities Current Assets > 1.5 Current Liabilities SWVP-028607

  23. Self-assurance (continued) The net working capital and tangible net worth of the applicant each are at least six times the closure cost estimate; and The applicant has assets in the US of at least 90 percent of total assets or six times the cost estimate. SWVP-028608

  24. Self-assurance (continued) The applicant may demonstrate: – The applicant’s senior unsecured debt has a current investment-grade rating as issued by Moody’s Investor Service, Inc.; Standard and Poor’s Corporation; or Fitch Ratings; – The tangible net worth of the applicant is at least six times the cost estimate; and – The applicant has assets in the US of at least 90 percent of total assets or six times the cost estimate. SWVP-028609

  25. Self-assurance (continued) Lastly, the applicant shall submit: – A letter from the CFO indicating which criterion specified previously is used to satisfy the requirements of the rule, how the applicant meets the criterion, and certification of the letter’s accuracy; and – A statement from an independent certified public accountant verifying that the demonstration submitted is accurate based on a review of the applicant’s financial statements for the latest completed fiscal year or more recent financial data and no adjustment to the financial statement is necessary. SWVP-028610

  26. Available Mechanisms 2. Performance Surety Bond a. Company on bond must be listed as acceptable surety on federal bonds in Circular 570 of the US Dept. of Treasury; b. Bond covers entire cost estimate by the surety, or by payment into a standby trust fund of an amount equal to the penal amount f the permittee fails to perform the required activities; c. The penal amount of the bond is at least equal to the cost estimate, if the bond is the only method used to satisfy the requirements of rule or a pro-rata amount if used with another financial assurance mechanism; SWVP-028611

  27. Available Mechanisms d. Surety bond names ADEQ as beneficiary; e. Original surety bond is submitted to the Director; f. Under the terms of the bond, the surety is liable on the bond obligation when the permittee fails to perform as guaranteed by the bond; and g. Surety payments under the terms of the bond are deposited directly into the Standby Trust Fund. SWVP-028612

  28. Available Mechanisms 3. Certificate of Deposit (COD) a. Applicant submits one or more CODs made payable to or assigned to ADEQ to cover the cost estimate or a pro-rata amount, if used with another mechanism; b. COD is insured by the Federal Deposit Insurance Corporation and is automatically renewable; c. The bank assigns the COD to ADEQ; d. Only ADEQ has access to the COD; and e. Interest accrues to the permittee during the period the applicant gives the COD as financial assurance, unless the interest is required to satisfy the cost estimate. SWVP-028613

  29. Available Mechanisms 4. Trust Fund a. ADEQ must be named beneficiary; b. The trust fund must be initially funded in an amount at least equal to: • Cost estimate under R18-9-A201(B)(5); • The amount specified in a compliance schedule approved in the permit; or • A pro-rata amount if used with another mechanism. SWVP-028614

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend