A UBURN S CHOOL D ISTRICT N O . 408 CAPITAL PROJECTS DEPARTMENT WORK IN PROGRESS July 2011 AUBURN HIGH SCHOOL AUTO SHOP IMPROVEMENTS PROGRESS: Construction work substantially completed March 22, 2011. PERCENT COMPLETE: 99% Auburn High


slide-1
SLIDE 1

AUBURN SCHOOL DISTRICT NO. 408 CAPITAL PROJECTS DEPARTMENT

WORK IN PROGRESS July 2011

slide-2
SLIDE 2

AUBURN HIGH SCHOOL AUTO SHOP IMPROVEMENTS

PROGRESS: Construction work substantially completed March 22, 2011. PERCENT COMPLETE: 99%

slide-3
SLIDE 3

Auburn High School Auto Shop Improvements

Steel framing for new overhead door to existing covered storage area.

slide-4
SLIDE 4

Auburn High School Auto Shop Improvements

Partially enclosed wall at south side of covered storage area.

slide-5
SLIDE 5

Auburn High School Auto Shop Improvements

Completed enclosure at covered storage area.

slide-6
SLIDE 6

AUBURN RIVERSIDE HIGH SCHOOL TENNIS COURTS RESURFACING

PROGRESS:

Construction work substantially completed June 24, 2011.

PERCENT COMPLETE: 99%

slide-7
SLIDE 7

Auburn Riverside High School Tennis Courts Resurfacing

Tennis courts prior to resurfacing work.

slide-8
SLIDE 8

Auburn Riverside High School Tennis Courts Resurfacing

Tennis courts after pressure washing in preparation of resurfacing work.

slide-9
SLIDE 9

Auburn Riverside High School Tennis Courts Resurfacing

Application of blue surfacing material at main court area.

slide-10
SLIDE 10

Auburn Riverside High School Tennis Courts Resurfacing

Application of green surfacing material surrounding tennis courts.

slide-11
SLIDE 11

Auburn Riverside High School Tennis Courts Resurfacing

Layout work being done for tennis court lines.

slide-12
SLIDE 12

Auburn Riverside High School Tennis Courts Resurfacing

Newly resurfaced tennis court.

slide-13
SLIDE 13

DICK SCOBEE CARPETING

PROGRESS: Work is substantially complete. Remaining work consists of punch list items and submittal of close out documents. PERCENT COMPLETE: 95%

slide-14
SLIDE 14

Dick Scobee Carpeting

Carpet delivery by Great Floors.

slide-15
SLIDE 15

Dick Scobee Carpeting

Carpet being removed from classroom.

slide-16
SLIDE 16

Dick Scobee Elementary

Piles of carpet material removed from classrooms.

slide-17
SLIDE 17

Dick Scobee Carpeting

Library after carpet removal.

slide-18
SLIDE 18

Dick Scobee Carpeting

Beginning installation of carpet in classroom.

slide-19
SLIDE 19

Dick Scobee Carpeting

New carpet and stair nosings in Library.

slide-20
SLIDE 20

ASPHALT IMPROVEMENTS

PROGRESS:

Work is substantially completed at Alpac Elementary, Hazelwood Elementary, Chinook Elementary and Transportation Center. Work at Auburn Pool, Auburn Memorial Stadium and Evergreen Heights Elementary will be completed by late August. PERCENT COMPLETE: 85%

slide-21
SLIDE 21

Asphalt Improvements

Student pathway at Chinook Elementary School before asphalt repair work.

slide-22
SLIDE 22

Asphalt Improvements

Student pathway at Chinook Elementary School with new asphalt surface.

slide-23
SLIDE 23

Asphalt Improvements

Settled and uneven asphalt at Alpac Elementary School playshed.

slide-24
SLIDE 24

Asphalt Improvements

New asphalt at Alpac Elementary School.

slide-25
SLIDE 25

Asphalt Improvements

Cracked and settled asphalt around storm drain at the Transportation Center.

slide-26
SLIDE 26

Asphalt Improvements

Asphalt demolition work at the Transportation Center.

slide-27
SLIDE 27

Asphalt Improvements

New asphalt at the Transportation Center.

slide-28
SLIDE 28

HAZELWOOD ELEMENTARY & RAINIER MIDDLE SCHOOL MODERNIZATION

PROGRESS:

Hazelwood Elementary – Shingles partially removed and new ice and water shield membrane partially installed at roof, sealer applied to exterior brick walls, wheel chair ramp to stage partially constructed , interior demolition complete and wall framing underway at Health and Special Education classroom restrooms. Rainier Middle School – Shingles removed and new ice and water shield installed at roof, foundation built at storage room addition, interior demolition completed at Library and handicap restrooms, and wall framing started at handicap restrooms. PERCENT COMPLETE: 30%

slide-29
SLIDE 29

Hazelwood Elementary & Rainier Middle School Modernization

Rainier Middle School: Removal of roof shingles as part of the reroofing process.

slide-30
SLIDE 30

Hazelwood Elementary & Rainier Middle School Modernization

Rainier Middle School: Deteriorated roof deck that broke through during the removal of shingles.

slide-31
SLIDE 31

Hazelwood Elementary & Rainier Middle School Modernization

Rainier Middle School: Installation of new ice and water shield roof membrane.

slide-32
SLIDE 32

Hazelwood Elementary & Rainier Middle School Modernization

Rainier Middle School: West section of building after installation of new ice and water shield membrane.

slide-33
SLIDE 33

Hazelwood Elementary & Rainier Middle School Modernization

Rainier Middle School: New cinders being added to running track.

slide-34
SLIDE 34

Hazelwood Elementary & Rainier Middle School Modernization

Rainier Middle School: Floor demolition in Library where computer lab will be added.

slide-35
SLIDE 35

Hazelwood Elementary & Rainier Middle School Modernization

Rainier Middle School: Construction of foundation wall form work where storage room addition will be built.

slide-36
SLIDE 36

Hazelwood Elementary & Rainier Middle School Modernization

Rainier Middle School: Wall framing at Health Room Restroom to enlarge room for wheel chair access.

slide-37
SLIDE 37

Hazelwood Elementary & Rainier Middle School Modernization

Hazelwood Elementary School: Removal of roof shingles as part of the reroofing process.

slide-38
SLIDE 38

Hazelwood Elementary & Rainier Middle School Modernization

Hazelwood Elementary School: Contractor cleaning exterior brick walls.

slide-39
SLIDE 39

Hazelwood Elementary & Rainier Middle School Modernization

Hazelwood Elementary School: Construction of ramp for wheel chair access to stage.

slide-40
SLIDE 40

Hazelwood Elementary & Rainier Middle School Modernization

Hazelwood Elementary School: Wall demolition at restroom in Special Education classroom.

slide-41
SLIDE 41

POOL AND STADIUM IMPROVEMENTS

PROGRESS:

Auburn Pool – Ceiling repair completed above the swimming pool; ductwork, plumbing and electrical conduit rough-in has begun inside the building; soil excavation, foundation and concrete slab completed at storage room addition; masonry installation has begun at storage room addition. Auburn Memorial Stadium – Site layout work has begun. Demolition work completed inside the Home and Visitor concession stands. PERCENT COMPLETE: 18% THROUGH END OF JUNE

slide-42
SLIDE 42

Pool and Stadium Improvements

Swimming pool and bulkhead after water has been removed.

slide-43
SLIDE 43

Pool and Stadium Improvements

Swimming pool bulkhead ready to be shipped to Arlington, Washington for reconditioning.

slide-44
SLIDE 44

Pool and Stadium Improvements

Swimming pool with sheet plastic enclosure for asbestos abatement work.

slide-45
SLIDE 45

Pool and Stadium Improvements

Workers removing asbestos containing plaster from bottom and sides

  • f swimming pool.
slide-46
SLIDE 46

Pool and Stadium Improvements

Demolition debris in mechanical room of pool building.

slide-47
SLIDE 47

Pool and Stadium Improvements

Rusty lockers from the pool locker rooms before removal from the pool building.

slide-48
SLIDE 48

Pool and Stadium Improvements

Workers removing roofing material at south side of pool building.

slide-49
SLIDE 49

Pool and Stadium Improvements

South side of pool building where storage room addition will be built.

slide-50
SLIDE 50

Pool and Stadium Improvements

Swimming pool after removal of plaster from bottom and sides of pool.

slide-51
SLIDE 51

Pool and Stadium Improvements

Restroom where new water lines and plumbing fixtures will be installed at pool building.

slide-52
SLIDE 52

Pool and Stadium Improvements

New plumbing lines and wall framing at restroom in locker room of pool building.

slide-53
SLIDE 53

Pool and Stadium Improvements

Soil backfill work at storage room addition at pool building.

slide-54
SLIDE 54

Pool and Stadium Improvements

Form work for concrete footings at storage room addition at pool building.

slide-55
SLIDE 55

Pool and Stadium Improvements

Form work for concrete foundation walls at storage room addition at pool building.

slide-56
SLIDE 56

Pool and Stadium Improvements

Masonry work at storage room addition at pool building.

slide-57
SLIDE 57

Pool and Stadium Improvements

Home concession stand at Stadium where new serving counter and cabinets will be installed.

slide-58
SLIDE 58

CHINOOK ELEMENTARY BUILDING STRUCTURE IMPROVEMENTS

PROGRESS:

Contractor has begun assessment of existing conditions and initial demolition work. Additional deterioration of wood beams was discovered when contractor removed metal flashing that covered the beams. The structural engineer is working on design modifications to correct the additional deterioration.

PERCENT COMPLETE: 10%
slide-59
SLIDE 59

Chinook Elementary Building Structure Improvements

Delamination of glu-lam beam at covered walkway at front of school.

slide-60
SLIDE 60

Chinook Elementary Building Structure Improvements

Previous beam repair at covered walkway.

slide-61
SLIDE 61

Chinook Elementary Building Structure Improvements

Deteriorated beam at Gym roof.

slide-62
SLIDE 62

Chinook Elementary Building Structure Improvements

Deteriorated wood and carpenter ant infestation at roof overhang.

slide-63
SLIDE 63

Chinook Elementary Building Structure Improvements

Drill bit showing depth of dry rot at covered walkway beam.

slide-64
SLIDE 64

AUBURN HIGH SCHOOL MODERNIZATION AND RECONSTRUCTION

PROGRESS:

Design development is 80% complete. Value engineering study

  • completed. Construction phasing analysis, energy life cycle cost

analysis, and infiltration testing underway. PERCENT COMPLETE: 30% (design phase)

slide-65
SLIDE 65

Auburn High School Modernization and Reconstruction

Water infiltration test that will be used in design of the storm water detention system.

slide-66
SLIDE 66

Auburn High School Modernization and Reconstruction

Agenda for first 3 days of 5 day value engineering study.

slide-67
SLIDE 67

Auburn High School Modernization and Reconstruction

Preliminary schedule that is being used to analyze options for the phasing of construction.

slide-68
SLIDE 68

Auburn High School Modernization and Reconstruction

Sketch of front entry used to study color and material options.