WORK IN PROGRESS July 2011 AUBURN HIGH SCHOOL AUTO SHOP - - PowerPoint PPT Presentation
WORK IN PROGRESS July 2011 AUBURN HIGH SCHOOL AUTO SHOP - - PowerPoint PPT Presentation
A UBURN S CHOOL D ISTRICT N O . 408 CAPITAL PROJECTS DEPARTMENT WORK IN PROGRESS July 2011 AUBURN HIGH SCHOOL AUTO SHOP IMPROVEMENTS PROGRESS: Construction work substantially completed March 22, 2011. PERCENT COMPLETE: 99% Auburn High
AUBURN HIGH SCHOOL AUTO SHOP IMPROVEMENTS
PROGRESS: Construction work substantially completed March 22, 2011. PERCENT COMPLETE: 99%
Auburn High School Auto Shop Improvements
Steel framing for new overhead door to existing covered storage area.
Auburn High School Auto Shop Improvements
Partially enclosed wall at south side of covered storage area.
Auburn High School Auto Shop Improvements
Completed enclosure at covered storage area.
AUBURN RIVERSIDE HIGH SCHOOL TENNIS COURTS RESURFACING
PROGRESS:
Construction work substantially completed June 24, 2011.
PERCENT COMPLETE: 99%
Auburn Riverside High School Tennis Courts Resurfacing
Tennis courts prior to resurfacing work.
Auburn Riverside High School Tennis Courts Resurfacing
Tennis courts after pressure washing in preparation of resurfacing work.
Auburn Riverside High School Tennis Courts Resurfacing
Application of blue surfacing material at main court area.
Auburn Riverside High School Tennis Courts Resurfacing
Application of green surfacing material surrounding tennis courts.
Auburn Riverside High School Tennis Courts Resurfacing
Layout work being done for tennis court lines.
Auburn Riverside High School Tennis Courts Resurfacing
Newly resurfaced tennis court.
DICK SCOBEE CARPETING
PROGRESS: Work is substantially complete. Remaining work consists of punch list items and submittal of close out documents. PERCENT COMPLETE: 95%
Dick Scobee Carpeting
Carpet delivery by Great Floors.
Dick Scobee Carpeting
Carpet being removed from classroom.
Dick Scobee Elementary
Piles of carpet material removed from classrooms.
Dick Scobee Carpeting
Library after carpet removal.
Dick Scobee Carpeting
Beginning installation of carpet in classroom.
Dick Scobee Carpeting
New carpet and stair nosings in Library.
ASPHALT IMPROVEMENTS
PROGRESS:
Work is substantially completed at Alpac Elementary, Hazelwood Elementary, Chinook Elementary and Transportation Center. Work at Auburn Pool, Auburn Memorial Stadium and Evergreen Heights Elementary will be completed by late August. PERCENT COMPLETE: 85%
Asphalt Improvements
Student pathway at Chinook Elementary School before asphalt repair work.
Asphalt Improvements
Student pathway at Chinook Elementary School with new asphalt surface.
Asphalt Improvements
Settled and uneven asphalt at Alpac Elementary School playshed.
Asphalt Improvements
New asphalt at Alpac Elementary School.
Asphalt Improvements
Cracked and settled asphalt around storm drain at the Transportation Center.
Asphalt Improvements
Asphalt demolition work at the Transportation Center.
Asphalt Improvements
New asphalt at the Transportation Center.
HAZELWOOD ELEMENTARY & RAINIER MIDDLE SCHOOL MODERNIZATION
PROGRESS:
Hazelwood Elementary – Shingles partially removed and new ice and water shield membrane partially installed at roof, sealer applied to exterior brick walls, wheel chair ramp to stage partially constructed , interior demolition complete and wall framing underway at Health and Special Education classroom restrooms. Rainier Middle School – Shingles removed and new ice and water shield installed at roof, foundation built at storage room addition, interior demolition completed at Library and handicap restrooms, and wall framing started at handicap restrooms. PERCENT COMPLETE: 30%
Hazelwood Elementary & Rainier Middle School Modernization
Rainier Middle School: Removal of roof shingles as part of the reroofing process.
Hazelwood Elementary & Rainier Middle School Modernization
Rainier Middle School: Deteriorated roof deck that broke through during the removal of shingles.
Hazelwood Elementary & Rainier Middle School Modernization
Rainier Middle School: Installation of new ice and water shield roof membrane.
Hazelwood Elementary & Rainier Middle School Modernization
Rainier Middle School: West section of building after installation of new ice and water shield membrane.
Hazelwood Elementary & Rainier Middle School Modernization
Rainier Middle School: New cinders being added to running track.
Hazelwood Elementary & Rainier Middle School Modernization
Rainier Middle School: Floor demolition in Library where computer lab will be added.
Hazelwood Elementary & Rainier Middle School Modernization
Rainier Middle School: Construction of foundation wall form work where storage room addition will be built.
Hazelwood Elementary & Rainier Middle School Modernization
Rainier Middle School: Wall framing at Health Room Restroom to enlarge room for wheel chair access.
Hazelwood Elementary & Rainier Middle School Modernization
Hazelwood Elementary School: Removal of roof shingles as part of the reroofing process.
Hazelwood Elementary & Rainier Middle School Modernization
Hazelwood Elementary School: Contractor cleaning exterior brick walls.
Hazelwood Elementary & Rainier Middle School Modernization
Hazelwood Elementary School: Construction of ramp for wheel chair access to stage.
Hazelwood Elementary & Rainier Middle School Modernization
Hazelwood Elementary School: Wall demolition at restroom in Special Education classroom.
POOL AND STADIUM IMPROVEMENTS
PROGRESS:
Auburn Pool – Ceiling repair completed above the swimming pool; ductwork, plumbing and electrical conduit rough-in has begun inside the building; soil excavation, foundation and concrete slab completed at storage room addition; masonry installation has begun at storage room addition. Auburn Memorial Stadium – Site layout work has begun. Demolition work completed inside the Home and Visitor concession stands. PERCENT COMPLETE: 18% THROUGH END OF JUNE
Pool and Stadium Improvements
Swimming pool and bulkhead after water has been removed.
Pool and Stadium Improvements
Swimming pool bulkhead ready to be shipped to Arlington, Washington for reconditioning.
Pool and Stadium Improvements
Swimming pool with sheet plastic enclosure for asbestos abatement work.
Pool and Stadium Improvements
Workers removing asbestos containing plaster from bottom and sides
- f swimming pool.
Pool and Stadium Improvements
Demolition debris in mechanical room of pool building.
Pool and Stadium Improvements
Rusty lockers from the pool locker rooms before removal from the pool building.
Pool and Stadium Improvements
Workers removing roofing material at south side of pool building.
Pool and Stadium Improvements
South side of pool building where storage room addition will be built.
Pool and Stadium Improvements
Swimming pool after removal of plaster from bottom and sides of pool.
Pool and Stadium Improvements
Restroom where new water lines and plumbing fixtures will be installed at pool building.
Pool and Stadium Improvements
New plumbing lines and wall framing at restroom in locker room of pool building.
Pool and Stadium Improvements
Soil backfill work at storage room addition at pool building.
Pool and Stadium Improvements
Form work for concrete footings at storage room addition at pool building.
Pool and Stadium Improvements
Form work for concrete foundation walls at storage room addition at pool building.
Pool and Stadium Improvements
Masonry work at storage room addition at pool building.
Pool and Stadium Improvements
Home concession stand at Stadium where new serving counter and cabinets will be installed.
CHINOOK ELEMENTARY BUILDING STRUCTURE IMPROVEMENTS
PROGRESS:
Contractor has begun assessment of existing conditions and initial demolition work. Additional deterioration of wood beams was discovered when contractor removed metal flashing that covered the beams. The structural engineer is working on design modifications to correct the additional deterioration.
PERCENT COMPLETE: 10%Chinook Elementary Building Structure Improvements
Delamination of glu-lam beam at covered walkway at front of school.
Chinook Elementary Building Structure Improvements
Previous beam repair at covered walkway.
Chinook Elementary Building Structure Improvements
Deteriorated beam at Gym roof.
Chinook Elementary Building Structure Improvements
Deteriorated wood and carpenter ant infestation at roof overhang.
Chinook Elementary Building Structure Improvements
Drill bit showing depth of dry rot at covered walkway beam.
AUBURN HIGH SCHOOL MODERNIZATION AND RECONSTRUCTION
PROGRESS:
Design development is 80% complete. Value engineering study
- completed. Construction phasing analysis, energy life cycle cost
analysis, and infiltration testing underway. PERCENT COMPLETE: 30% (design phase)
Auburn High School Modernization and Reconstruction
Water infiltration test that will be used in design of the storm water detention system.
Auburn High School Modernization and Reconstruction
Agenda for first 3 days of 5 day value engineering study.
Auburn High School Modernization and Reconstruction
Preliminary schedule that is being used to analyze options for the phasing of construction.
Auburn High School Modernization and Reconstruction
Sketch of front entry used to study color and material options.