white point landslide
play

White Point Landslide City of Los Angeles White Point Landslide - PowerPoint PPT Presentation

Christopher F. Johnson, P.E., G.E. White Point Landslide City of Los Angeles White Point Landslide Bureau of Engineering October 22, 2013 Eng.lacity.org Recommended Immediate Measures (Estimate $9.14 Million) FUNDING APPROVED BY CITY


  1. Christopher F. Johnson, P.E., G.E. White Point Landslide City of Los Angeles White Point Landslide Bureau of Engineering October 22, 2013 Eng.lacity.org

  2. Recommended Immediate Measures (Estimate $9.14 Million) FUNDING APPROVED BY CITY COUNCIL 09/18/2012 (CF-0600-S162) and 05/28/2013 (CF-13-0469) Status For Immediate Repairs Install additional monitoring points – Done Grade surface topography around landslide edge – Done Install series of passive drains – Done Slope anchor system – In Construction Traffic improvements – Pending Construction Schedule For Immediate Repairs Slope Anchors/Traffic Improvements Construction: May 17, 2013 – start of procurement and fabrication February 14, 2014 – all anchors installed and in-service May 30, 2014 – surface improvements complete

  3. Completed Interim Grading

  4. Completed Interim Grading

  5. Horizontal Drains-Drilling

  6. Horizontal Drains-Plan

  7. Work and Containment Areas

  8. Work and Containment Areas

  9. Horizontal Drains - Discharge Containment

  10. Ground Anchors – Plan View

  11. Ground Anchors – Cross Section

  12. Tree Groundwater Well and Instrumentation Map

  13. Groundwater Data Table NOVEMBER 2011 - OCTOBER 2013

  14. Groundwater Piezometric Levels February 2013 - October 2013

  15. DRAIN LOCATION PLAN

  16. DRAIN FLOW RATES GALLONS PER MINUTE

  17. Inclinometer Data Table JANUARY 2012 - OCTOBER 2013

  18. Crack Gauge West of B-7

  19. Traffic Counts

  20. Street Improvement Plans

  21. Schedule For Immediate Repairs • DEWATERING IMPROVEMENTS – Construction: COMPLETED • SLOPE ANCHORS/PHASE II GRADING/TRAFFIC IMPROVEMENTS May 17, 2013 – start of procurement and fabrication February 14, 2014 – all anchors installed and in-service May 30, 2014 – surface improvements complete

  22. • Residents and visitors are warned to keep out of the closed-off area. • Final Geotechnical Report can be viewed at the following website: http://eng.lacity.org/whitepoint/whitepointlandslide.htm

  23. Summary of Options • Abandon Roadway – Only interim repairs done • Restore Roadway Without A Retaining Wall • Restore Roadway With A Retaining Wall • Restore Roadway With A Bridge • Regrade Roadway • Reroute Roadway

  24. No further work other than Immediate Repairs

  25. OPTION 1 – Restore Roadway to Previous Location Without Retaining Wall - $43.8M

  26. OPTION 2 – Restore Roadway to Previous Location With Retaining Wall - $28.8M

  27. OPTION 3 – Restore Roadway to Previous Location With Bridge - $51.3M

  28. OPTION 4 – Regrade Roadway - $6.7M

  29. OPTION 5 – Reroute Roadway - $6.9M

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend