White Point Landslide City of Los Angeles White Point Landslide - - PowerPoint PPT Presentation

white point landslide
SMART_READER_LITE
LIVE PREVIEW

White Point Landslide City of Los Angeles White Point Landslide - - PowerPoint PPT Presentation

Christopher F. Johnson, P.E., G.E. White Point Landslide City of Los Angeles White Point Landslide Bureau of Engineering October 22, 2013 Eng.lacity.org Recommended Immediate Measures (Estimate $9.14 Million) FUNDING APPROVED BY CITY


slide-1
SLIDE 1

White Point Landslide

White Point Landslide October 22, 2013 Christopher F. Johnson, P.E., G.E. City of Los Angeles Bureau of Engineering Eng.lacity.org

slide-2
SLIDE 2

Recommended Immediate Measures (Estimate $9.14 Million)

FUNDING APPROVED BY CITY COUNCIL 09/18/2012 (CF-0600-S162) and 05/28/2013 (CF-13-0469)

Status For Immediate Repairs Install additional monitoring points – Done Grade surface topography around landslide edge – Done Install series of passive drains – Done Slope anchor system – In Construction Traffic improvements – Pending Construction Schedule For Immediate Repairs Slope Anchors/Traffic Improvements Construction: May 17, 2013 – start of procurement and fabrication February 14, 2014 – all anchors installed and in-service May 30, 2014 – surface improvements complete

slide-3
SLIDE 3

Completed Interim Grading

slide-4
SLIDE 4

Completed Interim Grading

slide-5
SLIDE 5

Horizontal Drains-Drilling

slide-6
SLIDE 6

Horizontal Drains-Plan

slide-7
SLIDE 7

Work and Containment Areas

slide-8
SLIDE 8

Work and Containment Areas

slide-9
SLIDE 9

Horizontal Drains - Discharge Containment

slide-10
SLIDE 10

Ground Anchors – Plan View

slide-11
SLIDE 11

Ground Anchors – Cross Section

slide-12
SLIDE 12

Groundwater Well and Instrumentation Map

Tree

slide-13
SLIDE 13

Groundwater Data Table

NOVEMBER 2011 - OCTOBER 2013

slide-14
SLIDE 14

Groundwater Piezometric Levels

February 2013 - October 2013

slide-15
SLIDE 15

DRAIN LOCATION PLAN

slide-16
SLIDE 16

DRAIN FLOW RATES

GALLONS PER MINUTE

slide-17
SLIDE 17

Inclinometer Data Table

JANUARY 2012 - OCTOBER 2013

slide-18
SLIDE 18

Crack Gauge West of B-7

slide-19
SLIDE 19

Traffic Counts

slide-20
SLIDE 20
slide-21
SLIDE 21

Street Improvement Plans

slide-22
SLIDE 22

Schedule For Immediate Repairs

  • DEWATERING IMPROVEMENTS

– Construction: COMPLETED

  • SLOPE ANCHORS/PHASE II GRADING/TRAFFIC

IMPROVEMENTS

May 17, 2013 – start of procurement and fabrication February 14, 2014 – all anchors installed and in-service May 30, 2014 – surface improvements complete

slide-23
SLIDE 23
  • Residents and visitors are warned to keep out
  • f the closed-off area.
  • Final Geotechnical Report can be viewed at

the following website:

http://eng.lacity.org/whitepoint/whitepointlandslide.htm

slide-24
SLIDE 24

Summary of Options

  • Abandon Roadway – Only interim repairs done
  • Restore Roadway Without A Retaining Wall
  • Restore Roadway With A Retaining Wall
  • Restore Roadway With A Bridge
  • Regrade Roadway
  • Reroute Roadway
slide-25
SLIDE 25

No further work other than Immediate Repairs

slide-26
SLIDE 26

OPTION 1 – Restore Roadway to Previous Location Without Retaining Wall - $43.8M

slide-27
SLIDE 27

OPTION 2 – Restore Roadway to Previous Location With Retaining Wall - $28.8M

slide-28
SLIDE 28

OPTION 3 – Restore Roadway to Previous Location With Bridge - $51.3M

slide-29
SLIDE 29

OPTION 4 – Regrade Roadway - $6.7M

slide-30
SLIDE 30

OPTION 5 – Reroute Roadway - $6.9M

slide-31
SLIDE 31
slide-32
SLIDE 32
slide-33
SLIDE 33
slide-34
SLIDE 34
slide-35
SLIDE 35
slide-36
SLIDE 36