wheelabrator parc adfer
play

Wheelabrator Parc Adfer Community Liaison Group Meeting 6 Apo - PowerPoint PPT Presentation

Wheelabrator Parc Adfer Community Liaison Group Meeting 6 Apo Sarandidis, Senior Project Manager Julian Harrison, Contractors Representative 25 July 2018 Community Liaison Group Meeting 6 Agenda 1. Welcome and introductions 2. Agreement of


  1. Wheelabrator Parc Adfer Community Liaison Group Meeting 6 Apo Sarandidis, Senior Project Manager Julian Harrison, Contractor’s Representative 25 July 2018

  2. Community Liaison Group Meeting 6 Agenda 1. Welcome and introductions 2. Agreement of minutes and actions from the last meeting 3. Project progress update 4. Focus topic: combustion technology 5. Community benefit fund update 6. North Wales Residual Waste Treatment Project – progress update 7. Agreement of actions and date of next meeting 8. AOB 2

  3. Project Progress Update

  4. Parc Adfer Construction Update Progress To Date • On time and on budget CNIM’s 2 nd construction Jobs Fair held on 22 nd May 2018 • Parc Adfer’s operations Jobs Fair held on 21 st June 2018 • • Support system development (IT, finance, maintenance systems, etc.) • Visitors’ Centre development continues Month Month Month 0 27 34 4

  5. Parc Adfer Construction Update May 2018 • First three passes of boiler erected • FGT erection commenced, with the Labloop erected • Administration building steel structure erection commenced • Electrical room building services installation • Bunker roof cladding commenced 5

  6. Parc Adfer Construction Update June 2018 • Waste fuel bunker wall cladding commenced • Installation of electrical switchgear • Dirty water pit construction commenced • FGT bag filter installation commenced 6

  7. Parc Adfer Construction Update July 2018 • Combustion air fan and associated air ducting • Admin building steel erection completed • Tipping hall steel erection commenced • Air cooled condenser foundations commenced 7

  8. Parc Adfer Construction Update Commissioning • Operator mobilized • Discussion with 3rd party fuel suppliers continues • Incinerator Bottom Ash (IBA) and Air Pollution Control Residues (APCR) offtake contracts continue to be developed • Discussions on construction completion and commission plan commenced 8

  9. Parc Adfer Construction Update Visitors’ Centre Sneak Peek (Reception & Lecture) 9

  10. Parc Adfer Construction Update Visitors’ Centre Sneak Peek (Interactive & Viewing) 10

  11. Combustion Control

  12. Parc Adfer Combustion Control Combustion Process • Combustion process requires three key elements: fuel, heat & oxygen • Once combustion is underway, it can be sustained by control of these inputs Exhaust Fuel Oil Heat Burner Heat Oxygen 12

  13. Parc Adfer Combustion Control Primary & Secondary Phase Combustion Primary Phase: • Main combustion undertaken here • Injection of under-fire air to control and enable complete combustion on grate • Monitoring of grate furnace line and temperature Secondary Phase Secondary Phase: • Further combustions of particles within flue gas Primary • Injection of secondary and Phase tertiary air • Complete combustion of particles within flue gas 13

  14. Parc Adfer Combustion Control Furnace Camera Screen 14

  15. Parc Adfer Combustion Control Understanding Combustion Computational Fluid Dynamics (CFD) is a node software simulation of a process in a defined system. • The system can be a component, area or fluid defined typically by computer aided design (CAD) drawing • The boiler furnace has been used for Parc Adfer • The system is divided into individual nodes • The modeling applies typically to equations of fluid motion and thermodynamics to understand the interaction of each node • The simulation is started and the equations are solved iteratively as a steady-state or transient 15

  16. Parc Adfer Combustion Control Computational Fluid Dynamics (CFD) Boiler combustion involves simultaneous fluid flow, chemical reactions and heat and mass transfer. CFD is a software simulation of the allowing estimation of: • Flue gas flow profile across the boiler • Flue gas temperature profile • Flue gas velocity profile • Impacts of combustion air • Performance at different boiler conditions 16

  17. Parc Adfer Combustion Control CFD Modelling for Parc Adfer Improves boiler design • Confirm boiler material selection against flue gas conditions • Check impact of changes to combustion air and grate operation • Confirm stable operation at different load conditions 17

  18. Parc Adfer Combustion Control CFD Modelling for Parc Adfer Environmental Permit Requirement (850˚C @ 2 seconds) • Conditions are set by the Industrial Emissions Directive • Demonstration through modelling submission to NRW during design • Demonstration during commissioning and performance testing to confirm compliance 18

  19. Community Benefit Fund Update

  20. Community Benefit Fund Update The Fund • £50,000 fund to cover 3-year construction period • Maximum contribution of £2,000 per project • For projects that are within, or benefit, the Deeside Partnership area 20

  21. Community Benefit Fund Update Activity to Date Fund Status £ • 30 applications received to date 23,716.64 APPROVED SPEND TO DATE 26,283.36 TOTAL REMAINING IN FUND • 13 applications approved 9,616.36 TOTAL REMAINING 2018 • 1 application approved subject to other funds being raised Examples of Approvals to date • 1 application deferred until other funds in place • Redecoration of public facilities • 13 applications rejected as outside • Purchase of defibrillators eligibility criteria and 1 withdrawn • Support and funding of community • 1 application pending awaiting events further evidence of benefit within • Educational events Deeside Partnership Area 21

  22. Community Benefit Fund Update Contributions to Date Enhancement Contribution Improved Health Environmental Project of Wider Awarded & Wellbeing Benefit Community ✔ ✔ Connah's Quay Old People's association £650 ✔ Daffodils £1,400 ✔ Eye 2 Eye £2,000 ✔ ✔ St John Ambulance £1,817 ✔ ✔ DangerPoint Ltd £1,980 ✔ YSGOL CROES ATTI £2,000 ✔ Connah's Quay Sea Cadets £2,000 ✔ Deeside Community First Responders £2,000 ✔ ✔ Plas Derw Trust Ltd £1,800 ✔ Friends of Flintshire CAB Ltd trading as Libby’s Cafe £520 ✔ Shotton Town Council £1,000 ✔ Connah's Quay Town Council £250 ✔ ✔ Sandycroft Community Centre £2,000 ✔ Connah’s Quay and Shotton Interservices Committee £2,000 ✔ Deeside Community Hospital League of Friends £2,000 22

  23. Community Benefit Fund Update Third Round of Applicants Our social responsibility begins with the communities in which our facilities operate, our customers live and our employees work • The third round of applicants have been assessed and approved providing funding to a diverse range of local community groups including: • Sandycroft Community Centre • Shotton Town Council • Connah’s Quay Town Festival • Connah’s Quay and Shotton Interservices 23

  24. THANK YOU www.wtiparcadfer.co.uk infoparcadfer@wtienergy.com

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend