School Construction Project Update October 12, 2011 Wednesday, - - PowerPoint PPT Presentation

school construction project update october 12 2011
SMART_READER_LITE
LIVE PREVIEW

School Construction Project Update October 12, 2011 Wednesday, - - PowerPoint PPT Presentation

School Construction Project Update October 12, 2011 Wednesday, October 12, 11 1 Project Timeline To Date In 2008, Town Meeting approved $350,000 for the completion of a feasibility study . Expected reimbursement $187,000. $191,000 placed back


slide-1
SLIDE 1

School Construction Project Update October 12, 2011

1 Wednesday, October 12, 11

slide-2
SLIDE 2

Project Timeline To Date

In 2008, Town Meeting approved $350,000 for the completion of a feasibility study. Expected reimbursement $187,000. $191,000 placed back to Stabilization May 2011. In November 2010, Town Meeting approved $495,000 for Schematic Design. Expected reimbursement $265,000. To be transferred to Stabilization November 2011. In March 2011, Town Meeting approved $49.9M for design and construction. Reimbursement 54% for Intermediate School Repair, 62% for New Elementary School. Most site costs not reimbursable.

2 Wednesday, October 12, 11

slide-3
SLIDE 3

Municipal Center Elementary School Intermediate School High School

PreK K 1 2 3 4 5 6 7 8 9 10 11 12 Town Police

3 Wednesday, October 12, 11

slide-4
SLIDE 4

Intermediate School Repair

Intermediate School (formerly Middle/High School) 25 years

  • ld, so major repairs are expected

Replace roof HVAC (boiler, air handler) Replace windows Replace most flooring Increase efficiency (lower cost of oil and electricity) Add sprinklers, other Building and ADA code issues Remove all portable classrooms Rename building as Douglas Middle School

4 Wednesday, October 12, 11

slide-5
SLIDE 5

New Elementary School

Approximately 82,000 SF 24 regular classrooms (six each, grades 2-5) Special Education classrooms Art, Music, Media Center, Gym LEED Silver

energy efficiency/sustainability = lower operating cost

5 Wednesday, October 12, 11

slide-6
SLIDE 6

Site Improvements

Traffic flow and student safety New playgrounds, athletic fields Track surface as project alternate

6 Wednesday, October 12, 11

slide-7
SLIDE 7

7 Wednesday, October 12, 11

slide-8
SLIDE 8

EXISTING SITE LAYOUT

ELEMENTARY SCHOOL, INTERMEDIATE ELEMENTARY SCHOOL, MODULARS

8 Wednesday, October 12, 11

slide-9
SLIDE 9

2 2 1 1

REVISIONS BY

DINISCO DESIGN PARTNERSHIP

06 OCTOBER 2011 12 OCTOBER 2011 2 1

TRAFFIC FLOW

9 Wednesday, October 12, 11

slide-10
SLIDE 10

NEW ELEMENTARY SCHOOL MIDDLE SCHOOL U8 FIELD U8 FIELD U10 FIELD NOTE: NEW SOCCER FIELD IS INCLUDED. TRACK SURFACE IS PROJECT ALTERNATE.

FIELDS

10 Wednesday, October 12, 11

slide-11
SLIDE 11

C D F G B A D E E C

East Elevation

EAST ELEVATION

DRIVING FROM MIDDLE SCHOOL TOWARDS PRIMARY SCHOOL

MATERIALS LEGEND A - GREEN ZINC PANEL B - LIGHT BROWN ZINC PANEL C - DARK BROWN ZINC PANEL D - CORRUGATED METAL PANEL E - PREFINISHED ALUMINUM F - BRICK VENEER G - STONE VENEER

11 Wednesday, October 12, 11

slide-12
SLIDE 12

WEST ELEVATION (GYM)

DRIVING FROM PRIMARY SCHOOL TOWARDS MIDDLE SCHOOL

12 Wednesday, October 12, 11

slide-13
SLIDE 13

TOP: SOUTH (VIEW FROM FIELDS) BOTTOM: NORTH (VIEW FROM EXISTING ROAD)

13 Wednesday, October 12, 11

slide-14
SLIDE 14

14 Wednesday, October 12, 11

slide-15
SLIDE 15

MUSIC 1,278 PRACTICE 123 ART 1,131 178 MEDIA CENTER 3,690 UPPER LEVEL ENTRY WALKWAY ELECTRIC ROOM EMERG GENERATOR WATER PUMP ROOM GENERAL STORAGE ROOM 311 MECHANICAL ROOM CUSTODIAL WORKSHOP & STORAGE 645 RECEIVING 302 CUST OFFICE 163 DRY STORAGE FREEZER COOLER RAMP UP KITCHEN/ SERVICE 1,632 KIT OFFICE TRASH T JC 71 TOILETS 180 ELEV CAFETERIA 4,170 PLATFORM 1,014 STORAGE 244 TOILETS 320 DESK WRKRM HEAD END 286 OFFICE

ST 30

ART STRG NURSE 650 EXAM T STAFF T CONF 240 T.O. 71 PRIN OFFICE 242 WRKRM GUID STRG 52 ADMIN 377 STAFF LUNCH/ WORK ROOM 295 TITLE 1 OFFICE 190 ENTRY STAIR RAMP UP RAMP UP ENTRY STAIR DT EL

REC ST 52

ENTRY STAIR STAIRS UP GUID OFFICE 132 GUID OFFICE 132 SPARE OFFICE 132

NEW ELEMENTARY SCHOOL

FIRST FLOOR

15 Wednesday, October 12, 11

slide-16
SLIDE 16

NEW ELEMENTARY SCHOOL

SECOND FLOOR (THIRD FLOOR SIMILAR)

16 Wednesday, October 12, 11

slide-17
SLIDE 17

4 8 2

Typical Classroom Grades 2nd thru 5th

C

ADJACENT CLASSROOM CORRIDOR COMPUTER WORKSTATIONS WINDOWS BUILT-IN STORAGE BELOW AND BEHIND SLIDING MB WALL CLOCK SLIDING MARKER BOARDS STORAGE CUBBIES 16'-0" MARKER BOARD HP SINK BASE AND WALL CABINETS AND SINK WINDOW COMPUTER DESK 8'-0" TACK BOARD WALL PHONE WALL MTD PROJECTOR WARDROBE DATA OUTLETS

17 Wednesday, October 12, 11

slide-18
SLIDE 18
  • GK.1

G2 G4.2

4 '
  • "
T B 4 '
  • "
T B G3.2 G1.9

3.5

G1.1 G3.9

GA G4 GB GH GH GJ GK G3

20' 20' 20' 11' 11' 11' 11' 11' 11' 11' 10'-6" 1'-4" 14'-11 3/4" 24'-9" 18'-4 1/2" 7' BOILER FLUE & GENERATOR EXHAUST LINE OF MOTORIZED DROP CURTAIN ABOVE (RAISE BRIDGING TO CLEAR 22' COURT HEIGHT) RETRACTABLE BLEACHERS LINES OF ROOF & GUTTER ABOVE

G Y M N A S I U M 2 4 1 G Y M O F F I C E 2 4 5 G Y M S T O 2 4 2 GYM LOBBY 200E G I R L S 2 4 3 B O Y S 2 4 4 GYM CORR 200F

9 3.9.05 5 3.9.05 7 3.9.05 11 3.9.05 TYP 15 3.9.05 11 11 11 6 5 5 11 11 11 11 5 # # 1 3.9.05 1 3.9.05 OPP SIM

GF GF GC GC GD GD GE GE GG GG

GYM

18 Wednesday, October 12, 11

slide-19
SLIDE 19

MIDDLE SCHOOL LIBRARY - REMOVE WALLS TO STORAGE AREAS, TECH. ED. ROOM

19 Wednesday, October 12, 11

slide-20
SLIDE 20

Project Schedule

Design Development: April-November, 2011 Construction (“Haul”) Road, November-December, 2011 Bids Awarded: January, 2012 New Elementary School Construction Begins: March, 2012 New Elementary School Opens: September, 2013 Intermediate Elementary School Repair Some repairs: Summer, 2012 Majority of repairs: July 2013 - January 2014 Students moved to new Elementary School Students move back in after February 2014 vacation Fields, road work completed: Spring, 2014

20 Wednesday, October 12, 11

slide-21
SLIDE 21

Construction Phasing Plan - Haul Road

21 Wednesday, October 12, 11

slide-22
SLIDE 22

Construction Phasing Plan - Phase 1

22 Wednesday, October 12, 11

slide-23
SLIDE 23

Construction Phasing Plan - Phase 2

23 Wednesday, October 12, 11

slide-24
SLIDE 24

Construction Phasing Plan - Phase 3

24 Wednesday, October 12, 11

slide-25
SLIDE 25

Construction Phasing Plan - Phase 4

25 Wednesday, October 12, 11

slide-26
SLIDE 26

Construction Phasing Plan - Phase 5

26 Wednesday, October 12, 11

slide-27
SLIDE 27

Grade Configuration During Construction Nancy Lane, Superintendent of Schools

27 Wednesday, October 12, 11

slide-28
SLIDE 28

Thank You! Questions?

28 Wednesday, October 12, 11