davisville junior public school spectrum alternative
play

Davisville Junior Public School / Spectrum Alternative Senior School - PowerPoint PPT Presentation

Davisville Junior Public School / Spectrum Alternative Senior School CONSTRUCTION UPDATE Community Meeting April 16, 2019 1 CONSTRUCTION UPDATE April, 2019 AGENDA WELCOME/INTRODUCTIONS This meeting will update the community on key


  1. Davisville Junior Public School / Spectrum Alternative Senior School CONSTRUCTION UPDATE Community Meeting April 16, 2019 1

  2. CONSTRUCTION UPDATE – April, 2019 AGENDA • WELCOME/INTRODUCTIONS This meeting will update the community on key aspects of this complex project as we start the construction phase of the new Davisville/Spectrum building • PROJECT RECAP Reminder of the key aspects of the project - Evolution of the design • The Site • The Building • Key Events • TIMELINE The overall construction schedule – identifying key milestone dates to be anticipated • NEXT STEPS How will we keep the community updated? • QUESTIONS & ANSWERS 2

  3. CONSTRUCTION UPDATE – April, 2019 3

  4. CONSTRUCTION UPDATE – April, 2019 THE SITE Utilization - Key areas and features of the proposed site development • A new school building & integrated Childcare fronting on Davisville Ave • Provision for a future Aquatic Centre – to be built by the City of Toronto • Coordination with key aspects of the Midtown in Focus initiatives – through block pedestrian access & provision for a boulevard treatment along Davisville • Addressing community concerns – site access and vehicular circulation – one- way flow from Millwood Rd to Davisville Ave 4

  5. CONSTRUCTION UPDATE – April, 2019 5

  6. CONSTRUCTION UPDATE – April, 2019 THE BUILDING learning grounds student-centred Vision: 21 st century school daylight & views community 6

  7. CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Ground Floor Plan Davisville Entrance 7

  8. CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Ground Floor Plan 8

  9. CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Ground Floor Plan 9

  10. CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Ground Floor Plan North Entrance 10

  11. CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Ground Floor Plan feature wall (to be rendered) 11

  12. CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Ground Floor Plan Kindergarten Kindergarten Child Care play play play Entrance 12

  13. CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Ground Floor Plan 13

  14. CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Ground Floor Plan 14

  15. CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Parking Plan 15

  16. CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Parking Plan 16

  17. CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Ground Floor Plan 17

  18. CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Second Floor Plan 18

  19. CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Second Floor Plan 19

  20. CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Second Floor Plan 20

  21. CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Second Floor Plan 21

  22. CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Second Floor Plan 22

  23. CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Third Floor Plan Spectrum 23

  24. CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Third Floor Plan 24

  25. CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Classroom Configuration 25

  26. CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Cross-Sectional Perspective 26

  27. CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Massing Model 27

  28. CONSTRUCTION UPDATE – April, 2019 THE BUILDING: South-West 3D View 28

  29. CONSTRUCTION UPDATE – April, 2019 THE BUILDING: South Elevation 29

  30. CONSTRUCTION UPDATE – April, 2019 THE BUILDING: North-East 3D View 30

  31. CONSTRUCTION UPDATE – April, 2019 THE BUILDING: North Elevation 31

  32. CONSTRUCTION UPDATE – April, 2019 THE BUILDING learning grounds student-centred Vision: 21 st century school daylight & views community 32

  33. CONSTRUCTION UPDATE – April, 2019 KEY EVENTS – PROJECT TIMELINE: For the replacement JK-8 school; integrated Childcare - with provision for a future Aquatic Centre These events affected the approval and delivery of the new replacement school: • CITY OF TORONTO – Municipal Approvals – Site Plan Approval & Building Permit Notice of Approval Conditions (NOAC) • Demolition Permit • Conditional Building Permit • Formal Site Plan Agreement and Full Building Permit • • CITY OF TORONTO – Future Aquatic Centre – Land Lease & Shared Use Agreements Use Agreements • Release of Identified Funding • • PROVINCE OF ONTARIO – Ministry of Education (EDU) – Approval to Proceed to Tender Review of Cost and Program Compliance Submission • Review of Extra Ordinary Costs • Formal Release of “Approval to Proceed” (ATP) to Construction Tender • • CONSTRUCTION TENDER – Tender Period – 6-8 weeks • Tender Review & TDSB Board Approval to Award • • TENDER AWARD – MOBILIZATION & CONSTRUCTION START 33

  34. CONSTRUCTION UPDATE – April, 2019 Key Events Timeline: DAVISVILLE - Key Event Timeline 2018 2019 Activity J F M A M J J A S O N D J F M A M J J CITY - Municipal Approvals SPA Site Plan Approval NOAC Building Permit - Conditional Building Permit -Full CITY - Aquatic Centre Approvals LAND LEASE Shared Use Agreement Released Funding PROVINCE - Ministry Approvals Review of Compliance $ Extra Ordinary Costs ATP Approval To Proceed to Tender `` CONSTRUCTION TENDER Tender Period (6-8 weeks) TDSB Board Approval to Award Bid Hold Tender $ held Tender Award Letter of Intent CONSTRUCTION START Letter of Intent TDSB Confirmation of Sub-Trade Agreements Mobilization & Start of Work ONGOING ELECTION BLACK-OUT MUNICIPAL ELECTION PROVINCIAL ELECTION 34

  35. CONSTRUCTION UPDATE – April, 2019 TIMELINE: Key Stages of Construction – Identified per the Contractor`s Preliminary Schedule: • Anticipated duration of construction – 24 months from start of work 3 storey structure with below-grade garage • Complex site in an urban context • CONSRUCTION COMPONENTS: • Shoring, Excavation & Substructure – 100 Days • Superstructure – 165 Days • Building Envelope – 140 Days • Interior Finishes – 190 Days • Site Development-Exterior & Landscape Features – 135 Days Note: These are the major stages of construction and anticipated duration. Overlaps in schedule & efficiencies are currently being evaluated. TDSB Staff will be involved in regular construction meetings & will provide updates to the Trustee, Superintendent and Principal. 35

  36. CONSTRUCTION UPDATE – April, 2019 What does completion look like? Lessons learned from previous, recent projects – AVONDALE PS : GEORGE WEBSTER ES : Replacement School - 860 pupil place school: Replacement School - 840 pupil place school: This replacement school was opened at the This replacement school was opened in beginning of April, 2019 – School occupied; September, 2018 – School occupied; landscape development & Childcare to landscape development & Childcare to follow for September occupancy follow for September occupancy 36

  37. CONSTRUCTION UPDATE – April, 2019 NEXT STEPS: • Communication Plan – TDSB Facility staff will provide regular updates to the School Principal (who will also be involved in construction meetings). • As the work proceeds we will confirm the nature and timing of construction through updates that will be posted on the school’s website https://schoolweb.tdsb.on.ca/davisville/ click on “The New Build” . There is also a link to the parent page at https://davisvilleparents.com/redevelopment/ ; we will be getting quarterly construction reports which will also be posted. HEALTH & SAFETY: • All work will be done per industry standards, and per the City guidelines for environmental protection, noise suppression and dust control. IN AN EMERGENCY: • If you notice anything you can reach our Security Operations Centre at 416-395- 4620 37

  38. CONSTRUCTION UPDATE – April, 2019 THANK YOU FOR COMING – QUESTIONS & ANSWERS: 38

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend