Davisville Junior Public School / Spectrum Alternative Senior School CONSTRUCTION UPDATE Community Meeting April 16, 2019 1 CONSTRUCTION UPDATE April, 2019 AGENDA WELCOME/INTRODUCTIONS This meeting will update the community on key


slide-1
SLIDE 1

Davisville Junior Public School / Spectrum Alternative Senior School CONSTRUCTION UPDATE

Community Meeting April 16, 2019

1

slide-2
SLIDE 2

AGENDA

  • WELCOME/INTRODUCTIONS

This meeting will update the community

  • n key aspects of this complex project as

we start the construction phase of the new Davisville/Spectrum building

  • PROJECT RECAP

Reminder of the key aspects of the project - Evolution of the design

  • The Site
  • The Building
  • Key Events
  • TIMELINE

The overall construction schedule – identifying key milestone dates to be anticipated

  • NEXT STEPS

How will we keep the community updated?

  • QUESTIONS & ANSWERS

2

CONSTRUCTION UPDATE – April, 2019

slide-3
SLIDE 3

3

CONSTRUCTION UPDATE – April, 2019

slide-4
SLIDE 4

4

CONSTRUCTION UPDATE – April, 2019

  • A new school building &

integrated Childcare fronting

  • n Davisville Ave
  • Provision for a future Aquatic

Centre – to be built by the City

  • f Toronto
  • Coordination with key aspects
  • f the Midtown in Focus

initiatives – through block pedestrian access & provision for a boulevard treatment along Davisville

  • Addressing community

concerns – site access and vehicular circulation – one- way flow from Millwood Rd to Davisville Ave

THE SITE Utilization - Key areas and features of the proposed site development

slide-5
SLIDE 5

5

CONSTRUCTION UPDATE – April, 2019

slide-6
SLIDE 6

6

CONSTRUCTION UPDATE – April, 2019

THE BUILDING

Vision: 21st century school

student-centred daylight & views learning grounds community

slide-7
SLIDE 7

7

CONSTRUCTION UPDATE – April, 2019

THE BUILDING: Ground Floor Plan

Davisville Entrance

slide-8
SLIDE 8

8

CONSTRUCTION UPDATE – April, 2019

THE BUILDING: Ground Floor Plan

slide-9
SLIDE 9

9

CONSTRUCTION UPDATE – April, 2019

THE BUILDING: Ground Floor Plan

slide-10
SLIDE 10

10

CONSTRUCTION UPDATE – April, 2019

THE BUILDING: Ground Floor Plan

North Entrance

slide-11
SLIDE 11

11

CONSTRUCTION UPDATE – April, 2019

THE BUILDING: Ground Floor Plan feature wall (to be rendered)

slide-12
SLIDE 12

12

CONSTRUCTION UPDATE – April, 2019

THE BUILDING: Ground Floor Plan

Child Care play Kindergarten play Kindergarten play Entrance

slide-13
SLIDE 13

13

CONSTRUCTION UPDATE – April, 2019

THE BUILDING: Ground Floor Plan

slide-14
SLIDE 14

14

CONSTRUCTION UPDATE – April, 2019

THE BUILDING: Ground Floor Plan

slide-15
SLIDE 15

15

CONSTRUCTION UPDATE – April, 2019

THE BUILDING: Parking Plan

slide-16
SLIDE 16

THE BUILDING: Parking Plan

16

CONSTRUCTION UPDATE – April, 2019

slide-17
SLIDE 17

THE BUILDING: Ground Floor Plan

17

CONSTRUCTION UPDATE – April, 2019

slide-18
SLIDE 18

THE BUILDING: Second Floor Plan

18

CONSTRUCTION UPDATE – April, 2019

slide-19
SLIDE 19

THE BUILDING: Second Floor Plan

19

CONSTRUCTION UPDATE – April, 2019

slide-20
SLIDE 20

20

CONSTRUCTION UPDATE – April, 2019

THE BUILDING: Second Floor Plan

slide-21
SLIDE 21

THE BUILDING: Second Floor Plan

21

CONSTRUCTION UPDATE – April, 2019

slide-22
SLIDE 22

THE BUILDING: Second Floor Plan

22

CONSTRUCTION UPDATE – April, 2019

slide-23
SLIDE 23

23

CONSTRUCTION UPDATE – April, 2019

THE BUILDING: Third Floor Plan

Spectrum

slide-24
SLIDE 24

THE BUILDING: Third Floor Plan

24

CONSTRUCTION UPDATE – April, 2019

slide-25
SLIDE 25

25

CONSTRUCTION UPDATE – April, 2019

THE BUILDING: Classroom Configuration

slide-26
SLIDE 26

26

CONSTRUCTION UPDATE – April, 2019

THE BUILDING: Cross-Sectional Perspective

slide-27
SLIDE 27

27

CONSTRUCTION UPDATE – April, 2019

THE BUILDING: Massing Model

slide-28
SLIDE 28

28

CONSTRUCTION UPDATE – April, 2019

THE BUILDING: South-West 3D View

slide-29
SLIDE 29

29

CONSTRUCTION UPDATE – April, 2019

THE BUILDING: South Elevation

slide-30
SLIDE 30

30

CONSTRUCTION UPDATE – April, 2019

THE BUILDING: North-East 3D View

slide-31
SLIDE 31

31

CONSTRUCTION UPDATE – April, 2019

THE BUILDING: North Elevation

slide-32
SLIDE 32

32

CONSTRUCTION UPDATE – April, 2019

THE BUILDING

Vision: 21st century school

student-centred daylight & views learning grounds community

slide-33
SLIDE 33

33

CONSTRUCTION UPDATE – April, 2019 KEY EVENTS – PROJECT TIMELINE: For the replacement JK-8 school; integrated Childcare - with provision for a future Aquatic Centre These events affected the approval and delivery of the new replacement school:

  • CITY OF TORONTO – Municipal Approvals – Site Plan Approval & Building Permit
  • Notice of Approval Conditions (NOAC)
  • Demolition Permit
  • Conditional Building Permit
  • Formal Site Plan Agreement and Full Building Permit
  • CITY OF TORONTO – Future Aquatic Centre – Land Lease & Shared Use Agreements
  • Use Agreements
  • Release of Identified Funding
  • PROVINCE OF ONTARIO – Ministry of Education (EDU) – Approval to Proceed to Tender
  • Review of Cost and Program Compliance Submission
  • Review of Extra Ordinary Costs
  • Formal Release of “Approval to Proceed” (ATP) to Construction Tender
  • CONSTRUCTION TENDER –
  • Tender Period – 6-8 weeks
  • Tender Review & TDSB Board Approval to Award
  • TENDER AWARD – MOBILIZATION & CONSTRUCTION START
slide-34
SLIDE 34

34

CONSTRUCTION UPDATE – April, 2019

Key Events Timeline:

J F M A M J J A S O N D J F M A M J J SPA Site Plan Approval NOAC Building Permit

  • Conditional

Building Permit

  • Full

LAND LEASE Shared Use Agreement Released Funding Review of Compliance $ Extra Ordinary Costs ATP Approval To Proceed to Tender `` Tender Period (6-8 weeks) TDSB Board Approval to Award Bid Hold Tender $ held Tender Award Letter of Intent Letter of Intent TDSB Confirmation of Sub-Trade Agreements Mobilization & Start of Work ONGOING MUNICIPAL ELECTION PROVINCIAL ELECTION

DAVISVILLE - Key Event Timeline

2018 2019 Activity CITY - Aquatic Centre Approvals ELECTION BLACK-OUT CONSTRUCTION TENDER CONSTRUCTION START CITY - Municipal Approvals PROVINCE - Ministry Approvals

slide-35
SLIDE 35

35

CONSTRUCTION UPDATE – April, 2019

TIMELINE: Key Stages of Construction – Identified per the Contractor`s Preliminary Schedule:

  • Anticipated duration of construction – 24 months from start of work
  • 3 storey structure with below-grade garage
  • Complex site in an urban context

CONSRUCTION COMPONENTS:

  • Shoring, Excavation & Substructure – 100 Days
  • Superstructure – 165 Days
  • Building Envelope – 140 Days
  • Interior Finishes – 190 Days
  • Site Development-Exterior & Landscape Features – 135 Days

Note: These are the major stages of construction and anticipated duration. Overlaps in schedule & efficiencies are currently being evaluated. TDSB Staff will be involved in regular construction meetings & will provide updates to the Trustee, Superintendent and Principal.

slide-36
SLIDE 36

36

CONSTRUCTION UPDATE – April, 2019 AVONDALE PS: Replacement School - 860 pupil place school: This replacement school was opened at the beginning of April, 2019 – School occupied; landscape development & Childcare to follow for September occupancy GEORGE WEBSTER ES: Replacement School - 840 pupil place school: This replacement school was opened in September, 2018 – School occupied; landscape development & Childcare to follow for September occupancy

What does completion look like? Lessons learned from previous, recent projects –

slide-37
SLIDE 37

37

CONSTRUCTION UPDATE – April, 2019

NEXT STEPS:

  • Communication Plan – TDSB Facility staff will provide regular updates to the School

Principal (who will also be involved in construction meetings).

  • As the work proceeds we will confirm the nature and timing of construction through

updates that will be posted on the school’s website https://schoolweb.tdsb.on.ca/davisville/ click on “The New Build” . There is also a link to the parent page at https://davisvilleparents.com/redevelopment/ ; we will be getting quarterly construction reports which will also be posted. HEALTH & SAFETY:

  • All work will be done per industry standards, and per the City guidelines for

environmental protection, noise suppression and dust control. IN AN EMERGENCY:

  • If you notice anything you can reach our Security Operations Centre at 416-395-

4620

slide-38
SLIDE 38

38

CONSTRUCTION UPDATE – April, 2019

THANK YOU FOR COMING – QUESTIONS & ANSWERS: