DAVISVILLE JUNIOR PUBLIC SCHOOL & SPECTRUM ALTERNATIVE SCHOOL - - PowerPoint PPT Presentation
DAVISVILLE JUNIOR PUBLIC SCHOOL & SPECTRUM ALTERNATIVE SCHOOL - - PowerPoint PPT Presentation
DAVISVILLE JUNIOR PUBLIC SCHOOL & SPECTRUM ALTERNATIVE SCHOOL New School Review Team Meeting 23 March 2017 1 AGENDA # ITEM ACTION Senior Manager, Major Capital Projects & Building 1.1 Introductions Partnerships: Jeff Latto
AGENDA
# ITEM ACTION 1.1 Introductions
Senior Manager, Major Capital Projects & Building Partnerships: Jeff Latto Trustee Shelley Laskin
1.2 Project Recap and Status Report
Senior Manager, Major Capital Projects & Building Partnerships: Jeff Latto
1.3 Evolution of Design
- a. Site Aspects – Reaction to City Planning & Other Comments
- b. Evolution of the Building Plan – Walk Through Functional Areas
Snyder Architects
1.4 Next Steps
Senior Manager, Major Capital Projects & Building Partnerships: Jeff Latto
2
PROJECT RECAP AND STATUS REPORT
SITE
3
EVOLUTION OF DESIGN
SITE ASPECTS
Future Community Centre Millwood Road Davisville Avenue Existing School
existing easement TDSB property line midblock pedestrian connection buffer
New 3-Storey School
setback current traffic flow
4
EVOLUTION OF DESIGN
SITE PLAN
5
EVOLUTION OF DESIGN
UNDERGROUND PARKING PLAN
STAIR PARKING SPRINKLER LOBBY STAIR STAIR
6
KINDERGARTEN 6 KINDERGARTEN 5 KINDERGARTEN 4 KINDERGARTEN 3 KINDERGARTEN 2 KINDERGARTEN 1 GYMNASIUM STAGE KITCHENETTE STOR TABLE/CHAIR STORAGE STOR ELEC OFFICE LUNCH RECEIVING ADMIN CHANGE ROOM STAIR CHANGE ROOM LAN TODDLER 2 SLEEP LOBBY STAIR B STAIR C STAIR D STAIR A EXT. STOR ATRIUM CUST INFANT KITCHEN OFFICE TODDLER 1 STAIR E STORAGE STORAGE ELEC WR CORRIDOR EXT. STOR
EVOLUTION OF DESIGN
GROUND FLOOR PLAN
7
EVOLUTION OF DESIGN
KITCHEN LAYOUT
8
EVOLUTION OF DESIGN
SECOND FLOOR PLAN
MULCH PLAY TALL GRASSES/PERENNIALS
LEARNING COMMONS CLASSROOM 8 CLASSROOM 7 CLASSROOM 6 CLASSROOM 5 RESOURCE/ WORKROOM RESOURCE RESOURCE RESOURCE CLASSROOM 9 CLASSROOM 10 CLASSROOM 12 CLASSROOM 11 CLASSROOM 4 CLASSROOM 3 CLASSROOM 2 CLASSROOM 1 STAIR C UPPER LOBBY STAIR D PRESCHOOL MECH STAIR A ELEC LAUNDRY /STOR STAFF PRESCHOOL STOR CUST STAIR B RESOURCE RESOURCE PLAY AREA OPEN TO GYM BELOW
9
EVOLUTION OF DESIGN
THIRD FLOOR PLAN
Tall grasses/perennials Painted Hard-surface Hard-surface Children's Garden Mulch Play Sand Play Hard-surface Mound Limestone Path Hard-surface Play Children's Garden Tall grasses/ perennials Seating CLASSROOM 21 CLASSROOM 22 CLASSROOM 20 CLASSROOM 19 CLASSROOM 18 CLASSROOM 17 RESOURCE /WORKROOM RESOURCE RESOURCE RESOURCE CLASSROOM 16 CLASSROOM 15 CLASSROOM 14 CLASSROOM 13 MUSIC CLASSROOM 24 STAFF ART CLASSROOM 23 STAIR A STAIR C WORK RM STAIR B (MAKER SPACE) RESOURCE RESOURCE MECH GREEN ROOF
10
EVOLUTION OF DESIGN
CLASSROOM CONFIGURATION
11
EVOLUTION OF DESIGN
MASSING MODEL
Future Community Aquatics Centre Triple Gym School Childcare Field & Learning Grounds Vehicular Access & Ramp
MILLWOOD ROAD DAVISVILLE AVENUE