Warren BRF 013-4(32) Bridge 166 on VT 100 Over the Mad River - - PowerPoint PPT Presentation

warren brf 013 4 32 bridge 166 on vt 100 over the mad
SMART_READER_LITE
LIVE PREVIEW

Warren BRF 013-4(32) Bridge 166 on VT 100 Over the Mad River - - PowerPoint PPT Presentation

Warren BRF 013-4(32) Bridge 166 on VT 100 Over the Mad River Alternatives Presentation PROJECT LOCATION VT 100 BR 166 Meeting Outline Purpose of the Meeting Structures Section re-organization Existing bridge deficiencies


slide-1
SLIDE 1

Warren BRF 013-4(32) Bridge 166 on VT 100 Over the Mad River Alternatives Presentation

slide-2
SLIDE 2

VT 100 BR 166

PROJECT LOCATION

slide-3
SLIDE 3

Meeting Outline

  • Purpose of the Meeting
  • Structures Section re-organization
  • Existing bridge deficiencies
  • Alternatives considered
  • Summary and recommendation-
slide-4
SLIDE 4

Purpose of Meeting

  • Present the alternatives that we have considered
  • Explain the constraints to the project
  • Help you understand our approach to the project
  • Provide you with the chance to ask questions.
  • Provide you with the chance to voice concerns
  • Build consensus for the recommended alternative -
slide-5
SLIDE 5

Accelerated Bridge Program

  • Began in January 2012
  • Bridges are deteriorating faster than we can fix them
  • Accelerated Bridge Construction (ABC) is key
  • Impacts to property and resources is minimized
  • Standard details repeated on many projects
  • Shift from individual projects to programmatic approach
  • Accelerated Project Delivery (ABP)
  • Goal of 2 year design phase for ABP (5 years

conventional)

  • Goal of 25% of projects into Accelerated Bridge Program-
slide-6
SLIDE 6

Project Initiation & Innovation Team

  • Part of re-organization in January 2012
  • Currently team of 5
  • All projects will begin in the PIIT
  • Very efficient process
  • Look for innovative solutions whenever possible
  • Involved until Project Scope is defined
  • Hand off to PM to continue Project Design phase -
slide-7
SLIDE 7

Phases of Development

Project Definition Project Design Construction Project Funded Project Defined Contract Award

Identify resources & constraints Evaluate alternatives Public Participation

  • Quantify areas of

impact

  • Environmental

permits

  • Develop plans,

estimate and specifications

slide-8
SLIDE 8

Project Background

  • Priority 6 in the State Bridge Program
  • The structure is owned and maintained by the State (no

local funds)

  • VT 100 has a functional classification of Rural Minor

Arterial.

  • Existing bridge is a single-span steel beam bridge with a

concrete deck built in 1939

  • Bridge is structurally deficient and has a Federal

sufficiency rating of 33 (out of 100) -

slide-9
SLIDE 9

Project Background (Cont)

  • Traffic Data

TRAFFIC DATA

2014 2034 AADT 1,100 1,200 DHV 140 160 ADTT 65 110 %T 5.6 8.7

  • Comparative Traffic Volumes
  • VT 100 in Waitsfield = 6,300
  • VT 103 in Chester = 8,200
  • VT 14 in East Montpelier = 4,700
slide-10
SLIDE 10

Description of Terms Used

Beams (Superstructure) Deck Abutment (Substructure) Bridge Rail

slide-11
SLIDE 11

EXISTING BRIDGE DEFICIENCIES

Deficiencies Structural Capacity of the Bridge Deck Structural Stability of the Bridge Substructure Substandard Bridge Rail Travel Width on the Bridge Inspection Report Information (Based on a scale of 9) Bridge Deck Rating 4 Poor Superstructure Rating 6 Satisfactory Substructure Rating 4 Poor

slide-12
SLIDE 12

24’-0”

Width of Bridge

slide-13
SLIDE 13

Bridge Deck

slide-14
SLIDE 14

Abutments

slide-15
SLIDE 15

Bridge Railing

Missing Post

slide-16
SLIDE 16

Existing Site Conditions

  • Bridge Width (Face-Face Rail) = 24’-0”
  • Posted Speed Limit = 50 mph
  • No Postings for Weight Restriction
  • No Overhead Utilities present -
slide-17
SLIDE 17

Layout Showing Constraints

slide-18
SLIDE 18

Proposed Project

  • Complete bridge replacement needed
  • Use 11’ lanes and 4’ shoulders (30’ rail-rail width)
  • Increase bridge span to 85’
  • Maintain existing centerline and grade -
slide-19
SLIDE 19

Proposed Bridge Typical

slide-20
SLIDE 20

Options to Maintain Traffic

  • Two-way temporary bridge off alignment
  • One-way temporary bridge off alignment
  • One-way temporary bridge on alignment
  • Short-term road closure w/ ABC -
slide-21
SLIDE 21

Two-Way Temporary Bridge

slide-22
SLIDE 22

One-Way Temporary Bridge - Off

slide-23
SLIDE 23

One-Way Temporary Bridge - On

Traffic

Construction

Traffic Traffic

Construction Construction

slide-24
SLIDE 24

One-Way Temporary Bridge - On

slide-25
SLIDE 25

Bridge Closure w/ ABC

slide-26
SLIDE 26

Bridge Closure Details

  • Bridge 166 to be closed for 14 days (maximum)
  • Allow 24/7 construction during bridge closure
  • Contract incentives/dis-incentives to encourage contractor
  • Community would have input in time of closure
  • Detour would be on State highways
  • Public Outreach to provide advance notice for planning
  • Local bypass routes would not be considered detour route -
slide-27
SLIDE 27
  • Detour = 47 miles
  • Thru = 20 miles
  • Added = 27 miles

BRIDGE CLOSED

Proposed Detour

slide-28
SLIDE 28

Local Bypass Route

BRIDGE CLOSED

slide-29
SLIDE 29

Local Bypass Details

  • Local bypass route would not be considered detour route
  • State would not add signing on local roads
  • Can mitigate Town for impacts due to increased traffic by:

– Providing police presence to deter speeding – Providing DMV presence to enforce weight limits – Contract work to rebuild road to previous condition – OR Compensating Town a predetermined amount -

slide-30
SLIDE 30

Accelerated Bridge Construction

Driven steel piles with precast concrete cap for abutment

slide-31
SLIDE 31

Accelerated Bridge Construction

Precast Concrete Cap placed in two sections

slide-32
SLIDE 32

Accelerated Bridge Construction

Precast concrete Abutment in place

slide-33
SLIDE 33

Accelerated Bridge Construction

Precast Bridge Unit delivered to site

slide-34
SLIDE 34

Accelerated Bridge Construction

Precast Bridge Unit lifted onto abutments

slide-35
SLIDE 35

Accelerated Bridge Construction

Precast Bridge Unit connected together

slide-36
SLIDE 36

Alternatives Matrix

Road Closed One-lane Temporary Bridge On Alignment One-lane Temporary Bridge Off Alignment Two-lane Temporary Bridge Off Alignment Temporary Bridge $0 $80,000 $150,000 $250,000 Construction w/ Eng’ring + Conting $1,296,000 $1,510,000 $1,632,000 $1,781,000 Preliminary Engineering $216,000 $242,000 $251,000 $274,000 Right of Way $0 $0 $88,000 $96,000 Total Cost $1,512,000 $1,752,000 $1,971,000 $2,151,000 15.90% 30.40% 42.30% Project Development Duration 1 year 1 year 3 years 3 years Construction Duration 3 months 18 months 18 months 18 months Mobility Impact Duration 1 month 12 months 12 months 12 months

slide-37
SLIDE 37

Questions