w 29 th avenue bicycle lane
play

W 29 th Avenue Bicycle Lane Central St to Sheridan Blvd Project - PowerPoint PPT Presentation

W 29 th Avenue Bicycle Lane Central St to Sheridan Blvd Project Update November 2015 Background Purpose Safety traffic calming Create more complete street Expand the bike network Denver Moves: Phase 1 project


  1. W 29 th Avenue Bicycle Lane Central St to Sheridan Blvd Project Update November 2015

  2. Background  Purpose  Safety – traffic calming  Create more complete street  Expand the bike network  Denver Moves:  Phase 1 project  Moderate ease-of-use  Important E-W connection

  3. Project Updates  Project timeline pushed due to additional public feedback  No significant changes to the final design as presented in September 2015  Central to Federal: mix of treatments (bike lane, buffered bike lane, sharrow)  Federal to Sheridan: bike lane  Anticipate January 2016 install (weather permitting)

  4. Final Project Map

  5. 29 th Ave: Proposed Facility Type Bike lane Buffered bike lane Sharrow

  6. 29 th Ave: Proposed Operational Changes No change Lane removal (one side) Parking addition (one side) Parking removal (one side) Center turn lane removal

  7. P UBLIC I NVOLVEMENT

  8. 2015 Public Outreach  May 2015: Presented to WHNA and JPUN  9/23/15: emailed RNO’s and other stakeholders project update  9/29/15: flyered properties affected by parking  9/29 – 10/6/15: PW staff met with many stakeholders on corridor  10/1 – 10/31/15: PW staff receiving feedback  10/13/15: presented design plans to HUNI PDC  11/19/15: final project decision emailed to RNO’s and other stakeholders

  9. Public Feedback: Design Issue/Concern Public Works (PW) Response Need for an east-bound dedicated PW will study the feasibility of a bike bike lane from Umatilla to Platte lane on 15th Street to connect into Street downtown/west Denver in 2016 and this section will be considered with this study. In the Highland neighborhood, At specific locations, PW will adjust request to curve parking lane the final plans to curve the parking markings at specific locations lane line so that it is clear where the parking is being introduced. Request for green pavement markings PW has included green pavement to be incorporated in the designs markings at areas of high vehicle conflict where the bicycle lane crosses Speer.

  10. Public Feedback: Design Issue/Concern Public Works (PW) Response Request for a more enhanced bicycle PW will upgrade the bicycle lane at lane to make it more comfortable for certain sections between Federal and people on bikes Zuni to introduce a buffer and further separate bicycles and vehicles. Request to extend the western extent PW will extend the bicycle lane to to Sheridan Blvd Sheridan Blvd from the previous terminus at Yates. Request to extend the eastern extent PW will extend the facility to the intersection of Central St and 15th St.

  11. Public Feedback: Parking Issue/Concern Public Works (PW) Response Concerns with PW staff evaluated four different design scenarios to proposed address parking concerns while maintaining a northside of W westbound bicycle facility. Unfortunately, these designs 29th Ave parking result in net loss in parking on corridor greater than repurposing what is currently proposed. Based on this analysis, PW will maintain the original design as planned with parking to be repurposed on the northside of W 29th Ave from Lowell to Sheridan for the bike lane. Parking challenges PW staff met with the Tennyson Center to discuss at Tennyson existing parking challenges associated with high parking Center demand and low parking supply at their facility. PW recommended parking management strategies to alleviate on-street parking demands and is able to further study the issue as the need arises.

  12. Public Feedback: Planning Issue/ Public Works (PW) Response Concern Wheat Ridge Denver's proposed bicycle network in the Denver Moves does not have network plan was developed to provide a high ease-of-use a planned bicycle facility within 1/4 mile of all Denver households. In a bicycle few cases, this means that a bicycle facility is proposed on a connection on street that does not have a connection to an adjacent 29th Ave municipality, but this does not preclude Denver from completing the bicycle network within the city limits to achieve Denver Moves goals. Concerns PW staff is coordinating with Street Maintenance staff based about on work programs. At this time, the 2016 street resurfacing pavement plan is still being determined. Once the 2016 street condition resurfacing plan is known, the bike lane will be painted with waterborne paint on the section of W 29th Ave that is to be repaved. Waterborne paint is a cost-effective material and will be replaced with a more durable material after 29th is repaved.

  13. Public Feedback: Other Issue/ Public Works (PW) Response Concern Traffic To accommodate a rapidly increasing population on a congestion relatively fixed street network, Denver is focusing on multi- modal forms of transportation to move people around the City. Providing enhanced bicycle facilities is one of the city's strategies to address this growing travel demand. Bike lane will PW has not seen evidence to indicate a reduction in reduce property values occurring to residential properties in Denver property or elsewhere in the US as a result of bicycle lanes. Available value/resale research shows the contrary - that bicycle lanes and other potential bicycle facilities improve values.

  14. Public Feedback: Other Issue/ Public Works (PW) Response Concern Education PW will install a Variable Message Sign to alert street users campaign of the roadway changes. PW will work with communications needed to staff to provide project construction updates to the public. educate people PW will work with partner organizations such as BikeDenver about the to provide outreach to users about how to use this type of change facility.

  15. F INAL DESIGN

  16. C ENTRAL TO U MATILLA

  17. Existing: Central to Umatilla

  18. Proposed: Central to Umatilla

  19. U MATILLA TO ZUNI

  20. Existing: Umatilla to Zuni

  21. Proposed: Umatilla to Zuni

  22. Z UNI TO S PEER

  23. Existing: Zuni to Speer

  24. Proposed: Zuni to Speer

  25. S PEER TO F EDERAL

  26. Existing: Speer to Federal

  27. Proposed: Speer to Federal

  28. F EDERAL TO L OWELL

  29. Existing: Federal to Lowell

  30. Proposed: Federal to Lowell

  31. L OWELL TO S HERIDAN

  32. Existing: Lowell to Sheridan

  33. Proposed: Lowell to Sheridan

  34. Next Steps  November-December: PW staff coordinate installation  January:  Notify RNOs, Council and stakeholders prior to installation  Installation (weather permitting)

  35. Thank you. Rachael Bronson – rachael.bronson@denvergov.org 720-865-2658

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend