virtual open house project overview
play

VIRTUAL OPEN HOUSE PROJECT OVERVIEW O l d R e s e r v e D - PowerPoint PPT Presentation

SEPT 10, 2020 5:30PM V I A Z O O M FOYS LAKE ROAD/US 93 ALT INTERSECTION MDT PROJECT VIRTUAL OPEN HOUSE PROJECT OVERVIEW O l d R e s e r v e D r W Reserve Dr Whitefish Stage Rd F o u r M i l e D r The current


  1. SEPT 10, 2020 5:30PM V I A Z O O M FOYS LAKE ROAD/US 93 ALT INTERSECTION MDT PROJECT VIRTUAL OPEN HOUSE

  2. PROJECT OVERVIEW O l d R e s e r v e D r W Reserve Dr Whitefish Stage Rd F o u r M i l e D r The current roundabout on Foys Lake Road will ALT be replaced with a full interchange . E Idaho St T h r e e M i l e D r T w o M i l e D r t S o h d a I W Foys Lake Rd Airport Rd ALT 1 2

  3. ROUNDABOUTS The roundabouts will allow both residents and recreationalists to safely use Foys Lake Road while also providing access to the Bypass .

  4. ROUNDABOUTS: THE SAFEST OPTION The Insurance Institute for Highway Safety found that on average, roundabouts reduce fatalities by 90%, serious injury crashes by 75%, and all kinds of crashes by 37%. 90% 75% 37% FATALITY SERIOUS INJURY ALL KINDS OF REDUCTION CRASHES CRASHES

  5. ROUNDABOUTS: SAFETY By splitting traffic between the added roundabouts and the Bypass, travelers will see significantly reduced congestion and safer transition points on all accounts.

  6. PHASE 1 TRAFFIC CONSTRUCTION 1. Place erosion control devices 8. Construct temporary 1. Place advance warning signs prior to construction. roundabout in final 10 days prior to construction configuration at the activity. 2. Relocation of utilities required intersection of northbound for overhead power and ramps and Foys Lake Road. underground gas. 2. Maintain traffic on existing 9. Install traffic control for roadway alignments. 3. Relocate City of Kalispell water temporary roundabout. main and sanitary sewer force 3. Utilize single-lane closures main. 10.New drainage at Meridian roundabout and ramps. and weekend closures in Foys 4. Construct temporary shared- Lake Road to construct use path and sidewalk. 11.Construct US 93 widening temporary roundabout. roadway south of Foys Lake 5. Complete Ashley Creek Road. streambank rehabilitation. 4. Maintain shared–use path 12.Construct roadway sections on access throughout entire 6. Construct precast gravity block Bypass and southbound phase. retaining wall. ramps. 7. Construct northbound off and 5. Maintain access to residential on ramps. and commercial property at all times.

  7. PHASE 1 TRAFFIC PLAN

  8. PHASE 2 TRAFFIC CONSTRUCTION 1. Maintain and expand erosion control devices as required. 1. Bypass traffic detoured onto northbound ramps and 2. Construct new storm water treatment pond in SW quadrant. temporary roundabout. 3. Construct remaining elements of storm sewer system, Foys 2. Utilize single lane and Lake road reconstruction, southbound ramp embankments, weekend closures for Foys and Valley View Drive. Lake road reconstruction. 4. Construct MSE walls for new bridge on US 93 over Foys Lake 3. Maintain shared-use path road and bridge embankment. access throughout entire phase. 5. Install vertical drains, embankment, surcharge, and start settlement on US 93 near new bridge and SB on ramp. 4. Maintain access to residential and commercial property at all times.

  9. PHASE 2 TRAFFIC PLAN

  10. BUDGET & 12.7 MILLION IN FEDERAL BUILDING GRANT MAINTENANCE FUNDING The interchange is anticipated to be a long- term solution for the growing Flathead Valley communities. This project was awarded to LHC/KLJ design- build team for $14.7 million. The federal BUILD Grant will cover $12.7 million of project expenditures. MDT’s NATIONAL HIGHWAYS FUNDING PROGRAM

  11. ENVIRONMENTAL A s h l e y C r e e k CONSIDERATIONS Streambank Stabilization Location Sec. 13 Sec. 18 T028N R022W T028N R021W e y l C h As r e e k Foys Lake Rd Review 2006 document Pedestrian Underpass V a l l e y New review of environmental impacts V i e w D r S u n n y s i d e D r Wetlands Streambanks Sunnyside Off-Ramp Social (traffic volumes, traffic noise, etc.) Ashley Creek streambank Shared-Use Path Sec. 24 Sec. 19 T028N R022W T028N R021W Construction permits KBP Project Location Sec. 25 Sec. 30 T028N R022W T028N R021W

  12. VISION ZERO Vision Zero is a multipronged initiative with the ultimate goal of eliminating deaths and injuries on Montana highways. The proposed interchange and roundabout plan has been designed to facilitate safer travel for all.

  13. PUBLIC INVOLVEMENT MDT is working on an accelerated schedule to complete this project in alignment with the BUILD grant restrictions and timeline. MDT welcomes any feedback on project plans.

  14. STAY IN THE KNOW EMAIL BECCA AT: Becca@BigSkyPublicRelations.com Please reach out with any questions. MDT welcomes any feedback on project plans. CALL THE PROJECT HOTLINE: Monday-Friday from 9 a.m. to 5 p.m. at (406) 207-4484 VISIT: https://www.mdt.mt.gov/pubinvolve/ kalispellbypass/

  15. CONSTRUCTION CONSTRUCTION WILL + BEGIN IN TIMELINE ROUTE DETAILS SPRING OF 2021 RESIDENTS MAY EXPERIENCE SOME DRIVING DELAYS AS CONSTRUCTION IS OCCURRING DURING DAYLIGHT HOURS 1 2

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend