Virginia Beach Project Goals
- Provide additional mobility opportunities in the east-west corridor
- Expand multi-modal transportation system that supports local land use
plans and initiatives (Strategic Growth Areas)
- Develop transportation infrastructure that supports the regional tourism
industry
Page 2 Page 2
Connections through Strategic Growth Areas
DEIS Alignment Alternatives
Page 3
Alignment Alternative Length (miles) Alternative 1A :Town Center 3.0 Alternative 1B: Rosemont 4.8 Alternative 2: NSRR 12.2 Alternative 3: Hilltop 13.5
Page 4
4 1 2 3 P&R
- Light Rail Transit (LRT)
- Bus Rapid Transit (BRT)
5
DEIS Technology Alternatives
VBTES Enhanced Bus System
Page 6
Tide LRT VBTES Alignment Alts. Proposed New-Realigned Bus Routes Existing HRT Bus Routes
Page 7
VBTES Capital Costs - LRT
LRT Estimated Capital Costs*
Town Center Alt ~3.0 miles Rosemont Alt 4.8 miles NSRR Alt 12.2 miles Hilltop Alt 13.5 miles Current Year Dollars (2013) $240 - $279 M $ 374 M $ 828 M $ 1,077M** Year of Expenditure (2018) $279 - $327 M $ 436 M $ 967 M $ 1,255 M**
* Costs Exclude Property already Purchased and Owned by the City of Virginia Beach ** Includes $53M(2013$) / $62M (2018$) for reconstruction of Laskin Road
Page 8
VBTES Capital Costs - BRT
BRT Estimated Capital Costs*
Town Center Alt ~3.0 miles Rosemont Alt 4.8 miles NSRR Alt 12.2 miles Hilltop Alt 13.5 miles Current Year Dollars (2013) $227 - $270 M $ 330 M $ 594 M $ 722 M** Year of Expenditure (2018) $264 - $315 M $ 384 M $ 693 M $ 839 M**
* Costs Exclude Property already Purchased and Owned by the City of Virginia Beach ** Includes $53M(2013$) / $62M (2018$) for reconstruction of Laskin Road
Page 9
VBTES Operating Costs – LRT
LRT - Annual Estimated Operating Costs*
Town Center Alt ~3.0 miles Rosemont Alt 4.8 miles NSRR Alt 12.2 miles Hilltop Alt 13.5 miles LRT Extension (2014) $2.2M
Local Share: $1.3M
$3.3M
Local Share: $2.0M
$10.6M
Local Share: $6.2M
$10.9M
Local Share: $6.4M
Local Bus Service (2014) $18.6M
Local Share: $7.1M
$18.4M
Local Share: $7.0M
$20.4M
Local Share: $7.8M
$20.4M
Local Share: $7.8M
Total Annual O&M (2014) $20.8M
Local Share: $8.4M
$21.7M
Local Share: $9.0M
$31.0M
Local Share: $14.0M
$30.1M
Local Share: $14.2M
- FY14 Local Share - Local Bus Service budget for the City of Virginia Beach = $3.0M
- FY14 Local Share - LRT budget for City of Norfolk = $5.3M
Page 10
VBTES Operating Costs – BRT
BRT - Annual Estimated Operating Costs*
Town Center Alt ~3.0 miles Rosemont Alt 4.8 miles NSRR Alt 12.2 miles Hilltop Alt 13.5 miles BRT Extension (2014) $1.6M
Local Share: $0.9M
$1.8M
Local Share: $1.0M
$3.4M
Local Share: $2.0M
$3.9M
Local Share: $2.3M
Local Bus Service (2014) $18.6M
Local Share: $7.1M
$18.4M
Local Share: $7.0M
$20.4M
Local Share: $7.8M
$20.4M
Local Share: $7.8M
Total Annual O&M (2014) $20.2M
Local Share: $7.8M
$20.2M
Local Share: $8.0M
$23.8M
Local Share: $9.8M
$24.1M
Local Share: $10.1M
- FY14 Local Share - Local Bus Service budget for the City of Virginia Beach = $3.0M
- FY14 Local Share - LRT budget for City of Norfolk = $$5.3M
Page 11
VBTES Ridership Forecast - LRT
LRT – Average Weekday Ridership Forecast 2034
Town Center Alt ~3.0 miles Rosemont Alt 4.8 miles NSRR Alt 12.2 miles Hilltop Alt 13.5 miles VB LRT 2,250 3,370 5,295 8,845 Norfolk LRT 7,050 7,180 7,535 7,820 Total LRT 9,300 10,550 12,830 16,665 Annualized 2,838,000 3,219,000 3,915,000 5,085,000 Annualized w/ Visitor 2,940,000 3,321,000 4,255,000 5,425,000
Page 12
VBTES Ridership Forecast - BRT
BRT – Average Weekday Ridership Forecast
Town Center Alt ~3.0 miles Rosemont Alt 4.8 miles NSRR Alt 12.2 miles Hilltop Alt 13.5 miles VB BRT 1,440 1,980 3,365 5,690 Norfolk LRT & BRT 5,430 & 900 5,460 & 980 6,425 & 1,030 6,665 & 1,040 Total LRT & BRT 7,770 8,420 10,820 13,385 Annualized 2,371,000 2,569,000 3,302,000 4,084,000 Annualized w/ Visitor 2,473,000 2,671,000 3,642,000 4,424,000
2014 2015 2016
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
DEIS Completion Update DEIS - New Alternative FTA Review/Approval of DEIS DEIS Circulation and Public Hearings Locally Preferred Alternative (LPA) LPA to HRTPO Fiscally Constrained LRTP HRT Request to Enter FTA "Project Development" Preparation of Final EIS/ROD HRT Request to Enter FTA “Engineering" Engineering FFGA/ Final Engineering /Construction Operations
Page 13
Schedule with FTA New Starts Funding
2014 2015 2016
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
DEIS Completion Update DEIS - New Alternative FTA Review/Approval of DEIS DEIS Circulation and Public Hearings Locally Preferred Alternative (LPA) LPA to HRTPO Fiscally Constrained LRTP HRT Request to Enter FTA "Project Development" Preparation of Final EIS/ROD HRT Request to Enter FTA “Engineering" Design Build FFGA/ Final Engineering /Construction Operations
Page 14
Schedule with State – City Funding
Formal Public Comment and Hearings
- 45 Public Comment Period
- Four Public Hearings - possibly as soon as Late
February or Early March
- City to Select Locally Preferred Alternative
- HRT will request an amendment to the TIP and
inclusion of project in fiscally constrained LRTP to reflect LPA decision
- VBTES PE/FEIS expected to begin this Summer
Page 15
For Public Comment or Further Information
Visit the VBTES Website or leave a message on the VBTES project hotline
- Website: www.gohrt.com/about/development/vbtes
- Study Hotline: 757-222-6098
Share your comments directly with HRT and the City of Virginia Beach
16
HAMPTON ROADS TRANSIT Julie Timm Transit Development Officer Department of Planning and Development 509 East 18th Street Norfolk, VA 23504 757-222-6000 ext. 6699 jtimm@hrtransit.org CITY OF VIRGINIA BEACH Brian Solis Transportation and Transit Manager Strategic Growth Area Office 4525 Main Street, Suite 710 Virginia Beach, VA 23462 757-385-2907 bsolis@vbgov.com