2014 2015 2016
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
DEIS Completion Update DEIS - New Alternative FTA Review/Approval of DEIS DEIS Circulation and Public Hearings Locally Preferred Alternative (LPA) LPA to HRTPO Fiscally Constrained LRTP Preparation of Final EIS/ROD Design Build Operations
Page 9
10