viaduct location study
play

VIADUCT LOCATION STUDY October 19, 2009 Background Information - PowerPoint PPT Presentation

VIADUCT LOCATION STUDY October 19, 2009 Background Information Traffic Study Alternative Evaluation Public Involvement Preferred Concept Next Steps Evaluate alternatives for the location of a viaduct to serve central


  1. VIADUCT LOCATION STUDY October 19, 2009

  2. • Background Information • Traffic Study • Alternative Evaluation • Public Involvement • Preferred Concept • Next Steps

  3. • Evaluate alternatives for the location of a viaduct to serve central and eastern Waverly spanning U.S. Highway 6 and the BNSF Railway

  4. Waverly Rd. N. 141st St. Oldfield St. Bluff Road Legend N. 162nd St. Study Area Waverly High School Waverly Middle School Waverly Intermediate School N. 148 th St. Amberly Road Waverly (Hamlow) Elem. School

  5. North

  6. • Conduct Grade Separation Study • A minimum exposure factor of 50,000 for a single crossing shall be required for identification as a potential location. (Exposure factor = # trains/day x # cars/day) • A new grade separation project will require closing a minimum of two public at-grade crossings.

  7. • Train Data • Fire Station Locations • Vehicle Data • Project Location • Cost-Benefit Analysis • Accident History • Pedestrian Traffic • Nearby Development • Adjacent RR crossings • Right-of-Way/Relocation • Impact on Community • Sight Distance • Local Support & Funding • School Locations/Bus Routes • Hospital Locations • Railroad Support & Funding

  8. • Existing Traffic • Pedestrians • Operations • Safety • Train Volumes • Exposure Factors • Alternatives / Impacts • Future Growth Scenarios • Development Impacts • Schools & Bus Routes • Emergency Vehicles

  9. • Data Collection • Counts • Field Review • Analysis • Operations • Crash History • Exposure Factors • Trains vs. Vehicles • Traffic Modeling • Current Land Use • Travel Patterns

  10. Crossing Location Crash Data • 141st Street and BNSF Crossing • 2 Train / Vehicle Crashes: PDO • 148th Street and BNSF Crossing • 1 Train / Vehicle Crash: PDO • 162nd Street and BNSF Crossing • 3 Train / Vehicle Crashes: 1 PDO, 1 injury, 1 fatality Intersection Crash Data Sideswipe Intersection Angle Rear-End Other Total Same Opposite US 6 & Amberly Rd 12 1 2 0 3 18 US 6 & N 141st St 5 2 1 1 1 10 US 6 & N 148th St 3 2 2 0 5 12 US 6 & N 140th St 5 4 1 0 0 10

  11. Yearly train counts through Waverly, NE (2009 - 2034 growth, using 2008 as base and increasing 2.43% per year) 120 110 100 90 80 70 60 50 40 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 Average day Peak day

  12. Exposure Factor Calculations Exposure Factor Calculations - Exposure Factor of 50,000 Warrants a Viaduct - Existing Factor is More Than 5 Times Greater

  13. Average Train Delay at Crossings = 2:45

  14. • Ability to eliminate crossing hazard and improve safety • Cost • Connectivity to existing/future roadway network • Impact to private property, including access • Public support • Ability to accommodate truck and farm machinery traffic • Environmental impacts • Utility impacts • Benefits (how much traffic is served)

  15. N. 141st St. Jamestown St. Heywood St. N. 162nd St.

  16. Concept #1: Viaduct at 148 th Street (Alternate 1) • Estimated construction cost: $ 8.2 Million • Grade-separated pedestrian crossing at 141 st Street: $2.3 Million • Projected traffic: 4,400 vehicles per day Reasons for Consideration • Relative close proximity to downtown • Reduces area required for right-of-way acquisition • Accommodates largest volume of traffic, including truck traffic • Sidewalk/trail along this alignment would best accommodate future residential development and present school locations • Continuity to existing road network Disadvantages • Impacts to Millard Lumber employee parking • Impacts to agricultural property • Lengthy access/frontage roads required

  17. Concept #2: Viaduct at 148 th Street (Alternate 2) • Estimated construction cost: $8.4 Million • Grade-separated pedestrian crossing at 141st Street: $2.3 Million • Projected traffic: 4,400 vehicles per day Reasons for Consideration • Relative close proximity to downtown • Reduces area required for right-of-way acquisition • Accommodates largest volume of traffic, including truck traffic • Sidewalk/trail along this alignment would best accommodate future residential development and present school locations • Continuity to existing road network • More direct connection to US-6 Disadvantages • Impacts to future development west of 148th Street • Impacts to agricultural property • Impacts to commercial property

  18. Concept #3A: Viaduct at 148 th Street (Alternate 3A) • Estimated construction cost: $7.7 Million • Grade-separated pedestrian crossing at 141 st Street: $2.3 Million • Projected traffic: 4,300 vehicles per day Reasons for Consideration • Relative close proximity to downtown • Reduces area required for right-of-way acquisition • Accommodates largest volume of traffic, including truck traffic • Sidewalk/trail along this alignment would best accommodate future residential development and present school locations • Existing 148 th Street is maintained as the primary alignment including connection to Highway 6 • Continuity to existing road network Disadvantages • Impacts to future development west of 148 th Street • Impacts to agricultural property

  19. Concept #3B: Viaduct at 148 th Street (Alternate 3B) • Estimated construction cost: $10.0 Million • Grade-separated pedestrian crossing at 141 st Street: $2.3 Million • Projected traffic: 4,300 vehicles per day Reasons for Consideration • Relative close proximity to downtown • Access to downtown • Reduces area required for right-of-way acquisition • Accommodates largest volume of traffic, including truck traffic • Sidewalk/trail along this alignment would best accommodate future residential development and present school locations • Existing 148 th Street is maintained as the primary alignment including connection to Highway 6 • Continuity to existing road network Disadvantages • Impacts to future commercial development • Impacts to commercial property • Impacts to agricultural property

  20. Concept #4: Viaduct at 152nd Street (Eliminated) • Estimated construction cost: $7.4 Million • Grade-separated pedestrian crossing at 141 st Street: $2.3 Million • Projected traffic: 2,900 vehicles per day Reasons for Elimination • Distance from central Waverly: • Increased vehicle travel distance/times • Too remote to provide pedestrian access across BNSF Railway and U.S. Highway 6 • Increased emergency response times • Lower traffic utilization • No direct access to downtown • Property impacts Reasons for Initial Consideration • Provided an alternate viaduct location to 148th Street • Viaduct constructed near eastern edge of future land use plan

  21. Concept #5: Viaduct at 162 nd Street (Eliminated) • Estimated construction cost: $5.0 Million • Grade-separated pedestrian crossing at 141 st Street: $2.3 Million • Projected traffic: 300 vehicles per day Reasons for Elimination • Distance from central Waverly: • Increased vehicle travel distance/times • Too remote to provide pedestrian access across BNSF Railway and U.S. Highway 6 • Increased emergency response times • Lowest traffic utilization • No direct access to downtown Reasons for Initial Consideration • Lower construction cost • Fewer property impacts • Better accommodate future growth in far eastern reaches of future city limits

  22. Concept #6: Viaduct at 141 st Street (Eliminated) • Estimated construction cost: $7.0 Million • Grade-separated pedestrian crossing at 148th Street: $2.3 Million • Projected traffic: 5,800 vehicles per day Reasons for Elimination • Property impacts: • Home relocations • Residential and commercial driveway and access closures/reconfiguration • Retaining wall in close proximity to homes • Intersecting street closures necessary • Increased traffic volumes on residential streets • Difficult turning movements for viaduct truck traffic • Does not accommodate farm machinery Reasons for Initial Consideration • Provides direct access to north and south of U.S. Highway 6 near center of Waverly • Along same alignment as existing 141st Street

  23. Concept #7: Underpass at 141 st Street (Eliminated) • Estimated construction cost: Not Calculated For This Concept • Grade-separated pedestrian crossing at 148th Street: $2.3 M • Projected traffic: 5,800 vehicles per day Reasons for Elimination • Property impacts: • Residential and commercial driveway and access closures/reconfiguration • Retaining wall in close proximity to homes • Increased traffic volumes on residential streets • Difficult turning movements for viaduct truck traffic • Does not meet Nebraska Minimum Design Standards- steep grades • Does not accommodate farm machinery • Long term maintenance and operational costs Reasons for Initial Consideration • Provides direct access to north and south of U.S. Highway 6 near center of Waverly • Along same alignment as existing 141st Street

  24. • Public Meetings (2) • June 24, 2008 • September 9, 2008 • One-on-one / stakeholder meetings (9)

  25. Public Meeting #1 • 36 comments received • 20 residents • 13 business owners • 3 unknown • 7 – support • 19 – oppose • 4 – support & oppose • 6 – undecided

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend