(UYSS) Project Update Town of East Gwillimbury Cleantech Investment - - PowerPoint PPT Presentation

uyss project update
SMART_READER_LITE
LIVE PREVIEW

(UYSS) Project Update Town of East Gwillimbury Cleantech Investment - - PowerPoint PPT Presentation

Upper York Sewage Servicing (UYSS) Project Update Town of East Gwillimbury Cleantech Investment Strategy Workshop on Water Economic Development Opportunities March 31, 2015 Brian Wolf, P. Eng. Senior Project Manager Regional Municipality of


slide-1
SLIDE 1

Upper York Sewage Servicing (UYSS) Project Update Town of East Gwillimbury Cleantech Investment Strategy Workshop on Water Economic Development Opportunities

March 31, 2015

Brian Wolf, P. Eng. Senior Project Manager Regional Municipality of York

slide-2
SLIDE 2

Slide 2

York Region Drinking Water Supply

Lake Ontario Lake Ontario Aurora Newmarket Stouffville Lake Simcoe Mount Albert Schomberg Nobleton King City Kleinburg Ballantrae- Musselman Lake Ansnorveldt Queensville/Holland Landing/Sharon Mount Albert Queensville/Holland Landing/Sharon Schomberg Nobleton King City Kleinburg Ballantrae- Musselman Lake Ansnorveldt Keswick/Sutton

Richmond Hill/ Vaughan/Markham

Aurora Newmarket Stouffville Lake Simcoe Ground Water

Blended Lake Ontario/Ground Water

Lake Ontario Legend

slide-3
SLIDE 3

Slide 3

York Region Sanitary Sewage Servicing

YDSS/Duffin Creek Peel Diversion/ Lakeview Keswick Sutton Mount Albert Holland Landing Schomberg Nobleton Kleinburg Newmarket/Aurora/ Richmond Hill/ Markham/Stouffville East side of Vaughan West side of Vaughan Keswick Sutton Mount Albert Holland Landing Schomberg Nobleton Kleinburg Lake Ontario via Peel Lakeview WPCP Lake Ontario via YDSS & Duffin Creek WPCP Lake Simcoe via Keswick and Sutton WPCP’s Local Communal System Legend

slide-4
SLIDE 4

Slide 4

York Durham Sewage System (YDSS)

slide-5
SLIDE 5

Slide 5

Upper York Sewage Solutions Purpose/Opportunity

47 million litres per day (MLD) additional capacity required to 2031 NEWMARKET Popn & Emp 27,000 Sewage Flow 8 MLD EAST GWILLIMBURY Popn & Emp 91,500 Sewage Flow 28 MLD AURORA Popn & Emp 34,500 Sewage Flow 11 MLD

To develop a sustainable sewage servicing solution to accommodate forecasted growth to 2031 in the UYSS service area

South East Collector UYSS Service Area Existing YDSS

LEGEND

19th Avenue

slide-6
SLIDE 6

Slide 6

Two Viable Alternatives

  • 1. Discharge to Lake Ontario

The Individual Environmental Assessment project team completed a detailed assessment of the following two viable alternatives:

2.

Lake Simcoe Water Reclamation Centre and YDSS Improvements

East Gwillimbury 28 MLD Newmarket 5 MLD 3 MLD Aurora 11 MLD Lake Simcoe Water Reclamation Centre Modifications to existing YDSS East Gwillimbury 28 MLD Aurora 11 MLD New Sewer System Newmarket 5 MLD 3 MLD Modifications to existing YDSS

slide-7
SLIDE 7

Slide 7

Preferred Alternative Key Design Elements

East Gwillimbury 28 MLD Newmarket 5 MLD 3 MLD Aurora 11 MLD Lake Simcoe Water Reclamation Centre Modifications to existing YDSS

slide-8
SLIDE 8

Slide 8

Upper York Sewage Solutions Recommended Ultimate Servicing Strategy

The Upper York Sewage Solutions recommended ultimate servicing strategy will convey wastewater from the service area to a Water Reclamation Centre and discharge treated water to the East Holland River

Proposed Lake Simcoe Water Reclamation Centre Proposed Pumping Station Proposed Treated Water Discharge Outfall Proposed Sanitary Linear infrastructure Proposed Treated Water Discharge Linear Infrastructure Existing Newmarket Pumping Station Town of Newmarket Town of East Gwillimbury

slide-9
SLIDE 9

Slide 9

Water Reclamation Centre Site

slide-10
SLIDE 10

Slide 10

Water Reclamation Centre Process Concept

RAW SEWAGE PRELIMINARY TREATMENT PRIMARY TREATMENT SECONDARY TREATMENT ULTRA-VIOLET DISINFECTION MICROFILTRATION MEMBRANE ULTRA PURE RECLAIMED WATER FOR DISCHARGE TO LAKE SIMCOE WATERCOURCES REVERSE OSMOSIS MEMBRANE ADVANCED TREATMENT ULTRA-VIOLET DISINFECTION NUTRIENT RICH RECLAIMED WATER FOR IRRIGATION DISINFECTION NUTRIENT RICH RECLAIMED WATER

slide-11
SLIDE 11

Slide 11

Lake Simcoe Watershed Key Considerations

 Water Reclamation Centre must align with:

 Lake Simcoe Protection Plan (LSPP)  Phosphorus Reduction Strategy (PRS)

 Elements of Environmental Assessment

approval include project specific:

 Total phosphorus off-set strategy  Reclaimed water use guidelines

slide-12
SLIDE 12

Slide 12

 Approximately 168 kg/yr of new

phosphorus would be discharged to the Lake Simcoe watershed by the Water Reclamation Centre

 Project specific phosphorus off-setting

program would address this increase through removal of other phosphorus sources at an approximate ratio of 2:1

Result would be a net reduction of approximately 168 kg/yr

  • f total phosphorus in the Lake Simcoe watershed

168 168 336

Total Phosphorus (TP) Off-set Strategy

slide-13
SLIDE 13

Slide 13

Total Phosphorous Off-Setting Program

 Retrofitting 7 existing stormwater

management ponds

 Aurora – 1 pond  East Gwillimbury – 2 ponds  Newmarket – 4 ponds  Developing a new stormwater

management pond in Georgina

 Installing low impact development

technologies within an existing stormwater catchment area in Newmarket

The proposed off-sets will improve the water quality and quantity of the downstream watercourses that ultimately flow into Lake Simcoe

slide-14
SLIDE 14

Slide 14

Reclaimed Water Use

 Reclaimed water is recognized in the Region

to help conserve regional water resources which are stressed in the summer

 Nutrients in reclaimed water will provide for

plant uptake through land irrigation, reducing need for chemical fertilizers

 Prime beneficiaries for the use of reclaimed

water:

 Sod farms  Tree farms  Golf courses  Industry (Future)

slide-15
SLIDE 15

Slide 15

Reclaimed Water Infrastructure

The reclaimed water infrastructure will include three major components:

1.

The WRC

2.

Distribution system to reach the customers

 Sod Farms and Golf Courses  Forests  Industrial (future)

3.

Off-site facilities at customer site

 Pressurized service and storage

slide-16
SLIDE 16

Slide 16

 Environmental Assessment Report

submitted to Ministry of Environment and Climate Change (MOECC) for approval – July 25, 2014

 MOECC approval – Anticipated for Q4 2015  Detailed design underway on all three key

design elements

 Geotechnical field investigations complete

for WRC site and outfall conveyance route

 Property acquisition process commenced  Landscape and building architectural design

concepts in development

16

16

Upper York Sewage Servicing Project Status

slide-17
SLIDE 17

Slide 17

For More Information

Brian Wolf Senior Project Manager Phone: (905) 830-4444 Ext. 75075 Email: brian.wolf@york.ca