uyss project update
play

(UYSS) Project Update Town of East Gwillimbury Cleantech Investment - PowerPoint PPT Presentation

Upper York Sewage Servicing (UYSS) Project Update Town of East Gwillimbury Cleantech Investment Strategy Workshop on Water Economic Development Opportunities March 31, 2015 Brian Wolf, P. Eng. Senior Project Manager Regional Municipality of


  1. Upper York Sewage Servicing (UYSS) Project Update Town of East Gwillimbury Cleantech Investment Strategy Workshop on Water Economic Development Opportunities March 31, 2015 Brian Wolf, P. Eng. Senior Project Manager Regional Municipality of York

  2. York Region Drinking Water Supply Keswick/Sutton Lake Simcoe Mount Albert Mount Albert Queensville/Holland Queensville/Holland Landing/Sharon Landing/Sharon Newmarket Newmarket Ansnorveldt Ansnorveldt Aurora Aurora Schomberg Schomberg Ballantrae- Ballantrae- Nobleton Nobleton Musselman Lake Musselman Lake Stouffville Stouffville King City King City Richmond Hill/ Kleinburg Kleinburg Lake Ontario Lake Ontario Vaughan/Markham Legend Blended Lake Lake Ontario Lake Simcoe Ground Water Ontario/Ground Water Slide 2

  3. York Region Sanitary Sewage Servicing Sutton Sutton Keswick Keswick Holland Landing Holland Landing Mount Albert Mount Albert Schomberg Schomberg Nobleton Nobleton Kleinburg Kleinburg Newmarket/Aurora/ Richmond Hill/ Peel Diversion/ West side of YDSS/Duffin Creek Markham/Stouffville Lakeview Vaughan East side of Vaughan Legend Lake Ontario via YDSS Lake Ontario via Peel Lake Simcoe via Keswick Local Communal and Sutton WPCP’s & Duffin Creek WPCP Lakeview WPCP System Slide 3

  4. York Durham Sewage System (YDSS) Slide 4

  5. Upper York Sewage Solutions Purpose/Opportunity To develop a EAST GWILLIMBURY sustainable sewage Pop n & Emp 91,500 servicing solution to Sewage Flow 28 MLD accommodate forecasted growth to 2031 in the UYSS AURORA service area Pop n & Emp 34,500 Sewage Flow 11 MLD 19 th Avenue NEWMARKET LEGEND Pop n & Emp 27,000 UYSS Service Area Sewage Flow 8 MLD Existing YDSS South East Collector 47 million litres per day (MLD) additional capacity required to 2031 Slide 5

  6. Two Viable Alternatives The Individual Environmental Assessment project team completed a detailed assessment of the following two viable alternatives: Lake Simcoe Water 2. 1. Discharge to Lake Ontario Reclamation Centre and YDSS Improvements Lake Simcoe Water Reclamation Centre East Gwillimbury Newmarket 28 MLD 5 MLD East Gwillimbury Newmarket 5 MLD 3 MLD 28 MLD 3 MLD New Sewer System Aurora Aurora 11 MLD 11 MLD Modifications to existing YDSS Modifications to existing YDSS Slide 6

  7. Preferred Alternative Key Design Elements Lake Simcoe Water Reclamation Centre Newmarket 5 MLD 3 MLD East Gwillimbury 28 MLD Aurora 11 MLD Modifications to existing YDSS Slide 7

  8. Upper York Sewage Solutions Recommended Ultimate Servicing Strategy The Upper York Sewage Solutions recommended ultimate servicing strategy will convey wastewater from the service area to a Water Reclamation Centre and discharge treated water to the East Holland River Proposed Lake Simcoe Water Reclamation Centre Proposed Pumping Station Proposed Treated Water Discharge Town of East Gwillimbury Outfall Proposed Sanitary Linear infrastructure Town of Newmarket Proposed Treated Water Discharge Linear Infrastructure Existing Newmarket Pumping Station Slide 8

  9. Water Reclamation Centre Site Slide 9

  10. Water Reclamation Centre Process Concept ADVANCED TREATMENT RAW SEWAGE PRELIMINARY TREATMENT PRIMARY TREATMENT ULTRA-VIOLET NUTRIENT RICH DISINFECTION RECLAIMED WATER FOR SECONDARY IRRIGATION TREATMENT MICROFILTRATION MEMBRANE DISINFECTION NUTRIENT RICH RECLAIMED WATER ULTRA PURE RECLAIMED REVERSE OSMOSIS ULTRA-VIOLET WATER FOR DISCHARGE DISINFECTION MEMBRANE TO LAKE SIMCOE WATERCOURCES Slide 10

  11. Lake Simcoe Watershed Key Considerations  Water Reclamation Centre must align with:  Lake Simcoe Protection Plan (LSPP)  Phosphorus Reduction Strategy (PRS)  Elements of Environmental Assessment approval include project specific:  Total phosphorus off-set strategy  Reclaimed water use guidelines Slide 11

  12. Total Phosphorus (TP) Off-set Strategy  Approximately 168 kg/yr of new 168 phosphorus would be discharged to the Lake Simcoe watershed by the Water Reclamation Centre 336  Project specific phosphorus off-setting program would address this increase 168 through removal of other phosphorus sources at an approximate ratio of 2:1 Result would be a net reduction of approximately 168 kg/yr of total phosphorus in the Lake Simcoe watershed Slide 12

  13. Total Phosphorous Off-Setting Program  Retrofitting 7 existing stormwater management ponds  Aurora – 1 pond  East Gwillimbury – 2 ponds  Newmarket – 4 ponds  Developing a new stormwater management pond in Georgina  Installing low impact development technologies within an existing stormwater catchment area in Newmarket The proposed off-sets will improve the water quality and quantity of the downstream watercourses that ultimately flow into Lake Simcoe Slide 13

  14. Reclaimed Water Use  Reclaimed water is recognized in the Region to help conserve regional water resources which are stressed in the summer  Nutrients in reclaimed water will provide for plant uptake through land irrigation, reducing need for chemical fertilizers  Prime beneficiaries for the use of reclaimed water:  Sod farms  Tree farms  Golf courses  Industry (Future) Slide 14

  15. Reclaimed Water Infrastructure The reclaimed water infrastructure will include three major components: The WRC 1. Distribution system to reach the 2. customers  Sod Farms and Golf Courses  Forests  Industrial (future) Off-site facilities at customer site 3.  Pressurized service and storage Slide 15

  16. 16 16 Upper York Sewage Servicing Project Status  Environmental Assessment Report submitted to Ministry of Environment and Climate Change (MOECC) for approval – July 25, 2014  MOECC approval – Anticipated for Q4 2015  Detailed design underway on all three key design elements  Geotechnical field investigations complete for WRC site and outfall conveyance route  Property acquisition process commenced  Landscape and building architectural design concepts in development Slide 16

  17. For More Information Brian Wolf Senior Project Manager Phone: (905) 830-4444 Ext. 75075 Email: brian.wolf@york.ca Slide 17

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend